WorksheetsNSPS
Total questions: 9
Worksheet time: 5mins
What is NSPS ?
New Special Protection Scheme
Northern Special Protection Scheme
Northern Load Shedding Scheme
Ayer Tawar- Junjung Scheme
How many CP for NSPS 2024
4
3
2
1
What is CP1 of NSPS
n-2 ATWR-BTRK and JMJG-BTRK 500kV
n-2 ATWR-JNJG 500kV L1 and L2
n-2 BGJH-PAPN 275KV L1 and L2
n-2 BMRH-JJNG 275kV L1 and L2
What is Violation Circuit During N-2 ATWR-JJNG 500kV during low Northern Generation
BGJH-PAPN 275kV L1 and L2
BMRH-JJNG 275kV L1 and L2
BDOR-KSTR 275kV L1 and L2
PLPS-KSTR 275kV L1 and Line 2
How many Staggered Load Shedding Scheme available in NSPS
1 Area
2 Area
3 Area
4 Area
What is Design Control Actions in NSPS , During Violation of 275kV BGJH-PAPN 275kV L1 or L2 or 275kV BMRH-JJNG 275kV L1 or L2. After 4sec are ....
Initiate HVDC Ramp Up/Back
Initiate DHIS Function
Initiate Start Up PLPS
Initiate Start Up SKPS
Why GSO need Northern SPS?
Low Northern Generation
Low Southern Generation
Low Eastern Generation
Low Central Generation
What are PMU in small Area (Kota Star) load Shedding Area?
PMU Kota Star
PMU KSSM
PMU OLPT
PMU JJNG
What is Power Plant available in Northern Region in the System.
New Prai Power Plant
Janamanjung Power Plant
Tanjung Bin Power Plant
Kuala Langat Power Plant