which of the following types of drawing shows a plan view of the building site and surrounding arera
which of the following scales should should be used to draw a block plan
1:1250
what piece of equipment should be used to interpret dimensions and measurements on an original working drawing
if an inaccuracy is found on a working drawing what action should be taken?
report to the supervisor
what is a site datum used for?
what does the abreviation RWP on a working drtawing stand for?
rain water pipe
Reinforced Waste Pipe
what must be completed before new construction work commences
laying concrete foundations
erect steel frames
removal of vegetation
why is it important to clear the site before setting out
to allow drains to be laid
to prepare for offices
to remove any obstacles
to clear the way for deliverys
what is the MOST important reason for locating an existing drainage system before site work begins
to make sure plans can be updated
to make sure the working area is safe
to prevent interuptions to the service
to establish the site datum
what document should be used to locate existing services
detailed drawing
programme of work
risk assesment
local authority records
which document should detail the safe sequence for isolating existing services
programme of work
risk assessment
detailed drawing
method statement
what welfare facilities are required on a construction site with 5 workers present
security office and drying room
toilets and first aid box
first aid box and tool store
drying room and toilets
which tool is needed when setting out a right angled quoin
builders square
line and pins
brick trowel
bolster
what tool is best to transfer levels across the site
wheelbarrow
laser level
string line
hard hat
how can an optical level be checked for accuracy
vertically check it against a door
compare it against a straight edge
rotate it 180 degrees
manufacturers calibration
which one of the following is used top calculate the perimeter of a building
l x w x 2
l2 x w2
2l x 2w
2l + 2w
which ratio can be used when setting out a right angled corner
2.4.6
3.5.9
3.4.5
1.2.3
during the setting out process where should a datum height be transferred to
corners of the building
ceiling joists
middle of the floor
window head
what action should be used before using an optical square for the firs time
ensure the staff fully extends
chevck the lens caps are secure
ensure the carry case is intact
read the manufacturers instructions
why is it important to use temporary profiles when setting out
to enable site to be cleared
to check dimensions accuratley
to give support to foundations
cos temporary ones are well good
why should profiles be set back from the proposed building
to avoid damage whilst excavating
so you dont trip over them
for access to lay drains
so the string can be pulled tighter
what is the main reason that profiles should be protected from damage
to prevent the trench collapsing
because wood is expensive
to avoid inaccuracies
because nobody will repair them
which of the following should be used to transfer information from a datum to the concrete foundation
ranging line
tape measure
builders square
timber profile
which tool is essential for ensuring accurate vertical alignment during construction?
spirit level
tape measure
compass
protractor
what is the main reason for conducting a risk assessment before starting construction work?
to estimate the project cost
to identify potential hazards and implement safety measures
to determine the number of workers needed
to finalize the construction timeline
how do you transfer the string line down onto the concrete foundation to mark ready for brickwork
stick your head over the line and guess
drop a quid from the string to the floor and mark where it lands
get Dinaras to do it cos he's a legend
use a spirit level and plumb down marking 2 points and joining up to create your line