1.

What is the title of the project mentioned in the document?

a)

North Eastern Airport Upgrades

b)

South Western Airport Renovations

c)

Central City Airport Expansion

d)

Western Regional Airport Development

2.

Who is the project sponsor for the North Eastern Airport Upgrades?

a)

Mr Ward

b)

Ms Smith

c)

Dr Johnson

d)

Mr Brown

3.

Who is the project manager for the North Eastern Airport Upgrades?

a)

Asma Usman

b)

John Doe

c)

Jane Smith

d)

Michael Brown

e)

You

4.

What is the completion date for the North Eastern Airport Upgrades project?

a)

03/04/2020

b)

03/03/2020

c)

03/05/2020

d)

03/06/2020

5.

What is one of the key aims of the airport project mentioned in the document?

a)

Increase the number of flights by 50%

b)

Improve efficiency of passenger movement by at least 30%

c)

Reduce ticket prices by 20%

d)

Expand the airport terminal by 40%

6.

Who is the Director of IT according to the document?

a)

Mr. Ward

b)

Mrs. Evans

c)

Mr. Smith

d)

Mrs. Johnson

7.

What is first one of the purposes of the Project Initiation Document?

a)

To list key aims of the project

b)

To finalize the project budget

c)

To hire new staff

d)

To design the project logo

8.

What is one of the goals for increasing the number of flights in and out of the airport?

a)

To reduce passenger complaints

b)

To increase the number of airlines

c)

To increase flights by 10,000 to 94,500 in the first year

d)

To decrease the number of flights

9.

check-in times errors can be fixed through?

a)

Hiring more staff

b)

Increasing efficiency

c)

Reducing the number of flights

d)

Offering free Wi-Fi

10.

Which tool is suggested for passengers to check in?

a)

Kiosk machines

b)

Smartphone app

c)

Paper tickets

d)

Email confirmation

11.

What is one of the responsibilities of a project manager mentioned in the text?

a)

Designing the airport layout

b)

Managing and controlling the project

c)

Flying the planes

d)

Selling tickets

12.

What strategy you can use to ensure project tasks were not delayed due to engineer absence?

a)

Hiring temporary workers

b)

Assigning more than one engineer to each task

c)

Reducing the number of tasks

d)

Increasing the budget

13.

What was the budget for developing the smartphone app?

a)

£1980

b)

£1440

c)

£2200

d)

£1750

14.

How many general function points were assigned to the task of creating a customised interface?

a)

It depends on PM

b)

6-8

c)

5-7

d)

10-15

15.

Who was assigned to build the relational database?

a)

Junior Software Engineer 1

b)

Senior Software Engineer

c)

Project Manager

d)

Client

16.

How many days should it take to integrate the smartphone app and relational database? give an estimate, remember that it is integrating not developing.

a)

5 days

b)

12 days

c)

7 days

d)

10 days

17.

On what date did the integration of the smartphone app and relational database finish?

a)

26/02/2020

b)

18/02/2020

c)

19/02/2020

d)

03/02/2020

18.

Who is responsible for installing check-in desks and network infrastructure terminals, and how long will it take?

a)

Senior Network Engineer, 21 days

b)

Junior Network Engineer, 32 days

c)

Junior Network Engineer, 22 days

d)

Junior Software Engineer, 34 days

19.

What is the cost of installing and configuring software for each server?

a)

£3600

b)

£5100

c)

£2916

d)

£7062

20.

What is the main purpose of the Airport project?

a)

Increase passenger movement efficiency by 50%

b)

Improve efficiency of passenger movement by at least 30%

c)

Decrease aircraft time at the airport by 10%

d)

Increase the number of flights by 20%

21.

Who is responsible for installing check-in terminals?

a)

Junior Network Engineers

b)

Junior Software Engineers

c)

Senior Network Engineer

d)

Senior Software Engineer

22.

What task is the Senior Software Engineer responsible for?

a)

Installing network infrastructure

b)

Developing the relational database

c)

Creating a customized interface

d)

Planning and delivering training for staff

23.

Which team is responsible for developing the smartphone app?

a)

Junior Network Engineers

b)

Junior Software Engineers

c)

Senior Network Engineer

d)

Senior Software Engineer

24.

What is one of the tasks of the Senior Network Engineer?

a)

Integrating the smartphone app and relational database

b)

Installing check-in terminals

c)

Building and connecting servers

d)

Software testing

25.

Which of the following tasks is the Database Administrator responsible for?

a)

Installing network cables

b)

Designing user interfaces

c)

Server software testing for each server

d)

Developing mobile applications

26.

What is the cost of the check-in terminals?

a)

£8700

b)

£11733

c)

£53000

d)

£25000

27.

Who is responsible for installing check-in desks and network infrastructure terminals?

a)

Senior Software Engineer

b)

Junior Network Engineer

c)

Senior Network Engineer

d)

Junior Software Engineer 3

28.

What is the cost of server software testing for each server?

a)

£2430

b)

£972

c)

£3600

d)

£5100

29.

What is the definition of product scope?

a)

The features and functionalities of the product or deliverable.

b)

All the tasks that must be done to produce, complete, and deliver the product.

c)

This is where extra things are put in your project that are outside the original scope.

d)

The cost and time required to complete the project.

30.

What does project scope include?

a)

The features and functionalities of the product or deliverable.

b)

All the tasks that must be done to produce, complete, and deliver the product.

c)

This is where extra things are put in your project that are outside the original scope.

d)

The cost and time required to complete the project.

31.

What is scope creep?

a)

The features and functionalities of the product or deliverable.

b)

All the tasks that must be done to produce, complete, and deliver the product.

c)

This is where extra things are put in your project that are outside the original scope.

d)

The cost and time required to complete the project.

32.

What is one of the main goals for the first year regarding the number of flights in and out of the airport?

a)

Increase by 5,000 flights

b)

Increase by 10,000 flights

c)

Decrease by 10,000 flights

d)

Maintain the current number of flights

33.

How does the new system plan to improve passenger satisfaction?

a)

By offering free meals

b)

By allowing smartphone check-ins

c)

By reducing ticket prices

d)

By providing in-flight entertainment

34.

What is the expected improvement in passenger movement efficiency with the new system?

a)

At least 10%

b)

At least 20%

c)

At least 30%

d)

At least 40%

35.

When is the project scheduled to start and end?

a)

January 1st to March 1st

b)

February 3rd to April 3rd

c)

March 1st to May 1st

d)

April 3rd to June 3rd

36.

What is the budget for the project?

a)

£100,000

b)

£120,000

c)

£130,000

d)

£150,000

37.

Who validated the assumption to improve efficiency of passenger movement by at least 30%?

a)

Asma Usman

b)

Mr Ward

c)

Director of Operations

d)

Project Manager

38.

Who is responsible for ensuring all staff will be trained on the systems?

a)

Mr Ward

b)

Director of Operations

c)

Asma Usman

d)

Project Manager

39.

Who is responsible for ensuring everyone is available when planned for?

a)

Mrs Ward

b)

Mr Ward

c)

You (PM)

d)

Mr Carson

40.

Who is responsible for the requirements specification of the app, database, and interface?

a)

Asma Usman

b)

Mr Ward

c)

Mr Carson, Mr Ahmed, and Mrs Evans

d)

Mrs Ward

41.

What are the three main constraints mentioned in the Exam Paper?

a)

Time, Money, Quality

b)

Resources, Budget, Time

c)

Quality, Resources, Budget

d)

Time, Budget, Resources

42.

Who validated the constraint that the app and database must be finished before integration?

a)

Mr. Carson

b)

Mr. Ahmed

c)

You (PM)

d)

Senior Software and Network

43.

What is the potential impact if only one senior developer is available?

a)

Increased costs

b)

Delayed project delivery

c)

No work can be finished

d)

Improved efficiency

44.

What is your rale in the risk management strategy?

a)

Developer

b)

Database Admin

c)

Project Manager

d)

Tester

45.

What is the probability score out of 3 for the 'Medium' risk?

a)

1

b)

2

c)

3

d)

4

46.

What is the severity score for the 'High' risk?

a)

3

b)

2

c)

1

d)

0

47.

What is the contingency plan for the 'High' risk?

a)

Replace Resources

b)

Delay the project

c)

Increase budget

d)

Reduce scope

48.

What should be demonstrated in the risk management strategy in your exam paper?

a)

Understanding of software development

b)

Understanding of risk management.

c)

Understanding of marketing strategy

d)

Understanding of financial planning

49.

What is a suggested solution if a software engineer is sick?

a)

Hire a new team

b)

Use a senior developer or a contractor

c)

Cancel the project

d)

Delay the project

50.

What should be ensured for junior developers to avoid producing software with more bugs?

a)

They work overtime

b)

They understand the technology and have previous experience

c)

They are given less responsibility

d)

They work independently

51.

What is the recommended action if a database administrator is not available?

a)

Postpone the project

b)

Use a contractor as security and software cannot be tested without them

c)

Assign the task to a junior developer

d)

Ignore the issue

52.

What should be done if equipment does not work or is not delivered?

a)

Wait for the original supplier

b)

Reorder from a different supplier quickly

c)

Cancel the order

d)

Use old equipment

53.

What is a solution if training of staff does not happen?

a)

Cancel the training

b)

Ensure all staff receive training guide, and if the trainer is ill, use another engineer

c)

Postpone the training indefinitely

d)

Ignore the training

54.

What is the purpose of the upgraded check-in desks?

a)

Store flight details

b)

Allow app and terminals to communicate

c)

Increase flow of passengers

d)

Provide redundancy

55.

Who is responsible for developing the system according to the stakeholders section?

a)

North East Airport

b)

MT Solutions

c)

Staff

d)

Customers

56.

What is the role of the two additional servers mentioned in the document?

a)

Store flight details

b)

Overcome redundancy

c)

Allow staff to see reports

d)

Interface for customers to check in

57.

Who is responsible for running IT and hiring the right people?

a)

Director of Operations

b)

Project Manager

c)

Director of IT

d)

Senior Software Engineer

58.

What is the primary responsibility of the Director of Operations?

a)

Deliver projects on time and within budget

b)

Run IT and hire the right people

c)

Run the operation or company

d)

Manage junior engineers

59.

What is the main role of the Project Manager?

a)

Hire IT staff

b)

Run the operation or company

c)

Deliver projects on time and within budget

d)

Communicate with stakeholders

60.

Who is responsible for upward and downward communication to seniors and directors?

a)

Project Manager (PM)

b)

Director of IT

c)

Development Team

d)

Senior Software Engineer

61.

What is the purpose of the daily communication with the development team?

a)

Discuss hiring and firing

b)

Find out progress of team

c)

Daily standup to remove blockers, allocate tasks

d)

Give overall report of delivery

62.

Which external body is mentioned for communication by the PM?

a)

Hospital

b)

School

c)

Airport

d)

Library

63.

Is this objective is smart "To increase flights by 10,000 to 94,500 in the first year"
If no how can you make it smart?

4 lines