1.

When was Occupational Safety and Health Act (OSHA) was enacted?

a)

25 February 1967

b)

15 February 1994

c)

24 February 1984

d)

25 February 1994

2.

What is the human resources aspects in post-completion review and in use phase?

a)

General assessment and comments on staff welfare, morale and motivation

b)

Communication channels and reporting feedback

c)

Handle the complaints from the worker

d)

Industrial relations working schedule

3.

Function of the OSHA Department is to enforce the following legislation:

a)

Factories and Machinery Act 1967 and its regulations

b)

Occupational Safety and Health Act 1984 and its regulations

c)

Part of Petroleum Act 1967 (Safety Measures) and its regulations

4.

What should be included in the close-out report?

a)

A formal record of the project's comments and feedbacks

b)

A formal record of the project's delivery and outcome

c)

A formal record of the project's progress

d)

A formal record of the project's issues and uncompleted task

5.

Which are NOT the key benefits of the Post-Occupancy evaluation?

a)

Identification of and finding solutions to problems in buildings

b)

Built-in capacity for building adaptation to organisational change and growt

c)

Accountability for building performance by contractors

d)

Strategic performance review

6.

Select the principle of Quality Management

a)

Customer engagement

b)

Evidence-based feedback making

c)

Process method

d)

Improvement

7.

Why is the project audit taken part in the post-completion review and in use phase?

a)

Brief description of the progress of the project

b)

Unusual developments and difficulties encountered and their solutions

c)

To improve the organization structure, its effectiveness, and adequacy of expertise/skills

d)

Summary of any amendments to the original project requirements and their feedback

8.

Which is the CORRECT sequence of the project manager's role?

a)

Design - Site meetings - Site inspections - Initial - Report

b)

Initial - Site inspections - Site meetings - Design - Report

c)

Site meetings - Site inspections - Initial - Design - Report

d)

Design - Initial - Site meetings - Site inspections - Report

9.

You have THREE basic rights in Occupational Health and Safety (OHS) legislation EXCEPT

a)

The right to refuse dangerous work and know that you’re protected from reprisal

b)

The right to report any workplace issues to the supervisor and protect yourself from hazards

c)

The right to participate in health and safety discussions and health and safety committees

d)

The right to know about workplace hazards and have access to basic health and safety information

10.

Project feedback form should include all of these criteria EXCEPT

a)

Form of contract and value

b)

Technical design

c)

Any technical lessons to be learnt

d)

Comments on contractor appointments