WorksheetsProject Management Plan Schedule - MC - 30 - 1
Total questions: 10
Worksheet time: 5mins
In a project management plan, what is the purpose of the schedule?
To identify and mitigate project risks
To define and communicate specific, measurable, achievable, relevant, and time-bound goals and objectives
To outline the specific tasks, milestones, and deadlines for completing the project
To allocate resources and assign tasks to team members
Which of the following best describes the application of the critical path method (CPM)?
A tool used to identify and mitigate project risks
A method for tracking and managing project costs
A technique for identifying the sequence of project tasks that must be completed on time in order for the project to be completed on schedule
A method for allocating resources and assigning tasks to team members
Which of the following tasks is considered to be a defining (really important) task in project management?
Marketing and advertising the project results
Managing and allocating project resources
Conducting project risk analysis
Planning employee vacation schedules
Which of the following methods is considered to be the most accurate for estimating the duration of tasks in project management?
Three-point estimation
Expert judgment
Analogous estimation
Bottom-up estimation
Which of the following is NOT a tool or technique used for identifying dependencies between tasks in project management?
Network diagrams
Predecessor and successor tables
Gantt charts
Surveying team members
Which of the following is NOT a characteristic of the critical path?
It is the longest path through the project network
It has the least amount of total float
It has the least amount of free float
It is the shortest path through the project network
Schedule Variance (SV) is calculated by:
Subtracting the planned value from the earned value (EV - PV)
Subtracting the earned value from the planned value (PV - EV)
Subtracting the actual cost from the planned cost (PC - AC)
Subtracting the planned cost from the actual cost (AC - PC)
In a Work Breakdown Structure (WBS), what is the lowest level of the hierarchy referred to as?
Deliverable
Work package
Project
Task
Which of the following is NOT a key component of a quality management plan?
Employee training program
Procurement management
Risk management
Quality control procedures
Which of the following is NOT a key responsibility of the project manager regarding integration management?
Developing the project charter
Managing the project budget
Managing the project team's performance evaluations
Identifying and managing project dependencies