1.
(1) As part of a periodic risk review, the steering committee members express concern about a significant risk that the project team missed identifying while planning the previous sprint. At the following sprint planning meeting, the project manager and team devise an appropriate, cost-effective, and realistic response plan and assign a risk owner.
What else should the project manager do?
a)
A. Implement the planned risk response
b)
B. Record the risk, risk response, and owner in the issue log
c)
C. Gain agreement by relevant stakeholders
d)
D. Submit a change request to revise the risk register
2.
(2) A senior executive proposes starting a project to replace a significant portion of the company’s labor force with an automated production line. Other executives express skepticism about whether this approach is the best way to boost profit margins and question whether they are prepared to sponsor such an initiative.
What should be the first step in this scenario?
a)
A. Performing a needs assessment
b)
B. Consulting with the project management office
c)
C. Appointing a project sponsor to create a project charter
d)
D. Providing a project manager with the authority to apply organizational resources
3.
(3) You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle charges, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle.
With the project life cycle selected, how will risk and cost be controlled?
a)
A. By adhering to the cost baseline and implementing risk responses
b)
B. By grooming the backlog as requirements and constraints emerge
c)
C. By increasing the cost baseline for each newly identified risk
d)
D. By progressively elaborating the initial plans with new information
4.
(4) You take over a project that has just been baselined. You review the project management plan and realize that while the development phase of the project will use an adaptive lifecycle, the development team does not have any experience with agile methodologies. The resource management plan does not specify any agile training.
What should you do first?
a)
A. Hire an agile coach to assist with the development phase of the project
b)
B. Submit a change request to revise the project management plan
c)
C. Change the life cycle description of the development phase to predictive
d)
D. Adjust the roles and responsibilities in the resource management plan
5.
(5) A project manager is monitoring the status of the project schedule for a product development project. The project deliverables are being produced in an iterative fashion, and the project has just completed seven of twelve planned sprints. The project manager has gathered the following information:
- 17 story points were completed and accepted in the seventh sprint
- 20 story points were planned for sprint #7
- One feature worth 3 story points was completed but rejected and placed back in the product backlog
- The value of the features developed to date is $172,000
- Actual costs to date are $167,000
- The BAC for the project is $300,000
- The project backlog contains 250 story points
- The project team has successfully completed 137 story points to date
Which of the following accurately describes the schedule performance of the project for the seventh iteration?
a)
A. The schedule variance (SV) is 0 story points, and the schedule performance index (SPI) is 1.0
b)
B. The cost variance (CV) is $5,000, and the cost performance index (CPI) is 1.03
c)
C. The schedule variance (SV) is -3 story points, and the schedule performance index (SPI) is 0.85
d)
D. There is not enough information in the scenario to determine the schedule performance
6.
(6) Just after the daily scrum, the project sponsor stops by the war room and introduces a new member of the organization whose role will be impacted by the project.
Now that a new stakeholder has been identified, what should the agile leader do next?
a)
A. Seek to understand the stakeholder's feelings, emotions, beliefs, and values
b)
B. Perform stakeholder analysis by using a power/influence grid
c)
C. Monitor the stakeholder to ensure that they have the appropriate level of engagement
d)
D. Prioritize the stakeholder to determine the level of engagement needed going forward
7.
(7) The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics.
At the retrospective, the team determines that the cost performance index (CPI) of the iteration was _______.
(On the actual exam, you will be requested to fill in the blank with the letter representing the correct answer. But here in the simulator, please select the answer below.)
a)
A. 1.333
b)
B. 0.750
c)
C. 1.143
d)
D. 0.857
8.
(8) Your project to produce a new vending machine is almost over, and you are now in the process of handing over the product to the operations team. You are meeting with the company president who initiated the project and with operations senior managers to demonstrate the vending machine functionality.
Which of the following is most important for you to achieve when meeting with these individuals?
a)
A. Understanding of the specific features of the vending machine
b)
B. Confirming the formal acceptance of the vending machine
c)
C. Getting support from operations management
d)
D. Being recognized for project completion
9.
(9) The project team reports that they have finished creating the requirements management plan, the requirements documentation, and the requirements traceability matrix. The team informs that they are going to start working on the project work breakdown structure (WBS) next.
What has the project team forgotten to do?
a)
A. Create the project scope statement
b)
B. Complete the project management plan
c)
C. Update the lessons learned register
d)
D. Perform the Validate Scope process
10.
(10) Team members are complaining that they cannot get their work done because the new sponsor, who is not familiar with agile practices, keeps contacting them for project details.
How should the scrum master address this?
a)
A. Ask one of the team members to serve as a spokesperson so the others can get their work done
b)
B. Meet with the product owner and ask for their assistance in dealing with the sponsor
c)
C. Tell the team that the scrum master's permission is required before discussing project details with the sponsor
d)
D. Contact the sponsor and request that they should direct all questions to the scrum master
11.
(11) A company undertakes its first hybrid project. The project schedule is measured against the baseline, and the product is developed using Scrum. Agile training is provided to the team. The project completion date is due, and the team submits what they were able to complete so far. The customer inspects the product and indicates that an important feature was not delivered.
What was the most likely reason that caused this situation?
a)
A. The project team refused to work evenings and weekends to complete the entire product backlog.
b)
B. A product owner was not included in agile training or was not even assigned to the project.
c)
C. The project team did not consult with the customer on how to prioritize the product backlog.
d)
D. The schedule baseline was too short for all the items in the product backlog to be developed.
12.
(12) An agile practitioner would like to see their company start using Scrum for future projects, but getting buy-in at the executive level has been challenging since executives are not familiar with the benefits of agile methodologies.
How should you describe to the executive team the benefits of using Scrum over other agile methodologies?
a)
A. Scrum does not have many roles or artifacts because it's more of a general agile mindset than a true methodology.
b)
B. Scrum has strict artifacts, roles, and rules, and although it's not flexible, it is most successful in providing benefits when applied correctly.
c)
C. Scrum is lightweight and easily paired with other methodologies, making it flexible to anyone with any type of previous project management experience.
d)
D. Scrum is the least likely agile methodology to be used by organizations due to its overly strict roles, rules, and artifacts.
13.
(13) You are managing a hotel construction project, and you have asked your project team to calculate the current earned value metrics to determine the project performance. Your team reports back that the project’s to-complete performance index (TCPI) is 0.9 based on the budget at completion (BAC).
Which of the following is true regarding your project’s current situation as reflected by this TCPI value?
a)
A. The project is within budget
b)
B. The project is over budget
c)
C. The project is behind schedule
d)
D. The project is ahead of schedule
14.
(14) As the project manager, you are in the process of assisting the project sponsor with creating the project charter for a project which will design and launch a new social media platform. In order to create the project charter, you need to get a better understanding of the project's objectives.
What should you do to obtain this information?
a)
A. Consult the project management plan
b)
B. Review the assumption log
c)
C. Check the project needs analysis documents
d)
D. Review the business case and benefits management plan
15.
(15) You are managing a project team that has recently been expanded by new team members working remotely from another country. Their roles have been outlined to form a preliminary team charter. Nevertheless, you have noticed a considerable lack of acceptance of cultural differences in the team, resulting in frequent conflicts.
Which of the following techniques could help you in this situation? (Choose three.)
a)
A. Focus groups
b)
B. Role definition
c)
C. Ground rules
d)
D. Ability tests
e)
E. Meetings
16.
(16) After successfully completing several one-week iterations, an agile team is in agreement that the weekly iteration retrospectives have not been productive as the team is already working very efficiently. The team members say that holding weekly retrospectives is not the best use of their time.
What is the best course of action for the project leader?
a)
A. Advise the team that iteration retrospectives are a best practice and should always be adhered to
b)
B. Cancel the retrospectives for the remainder of the project and use the freed-up time to deliver value
c)
C. Suggest having a monthly retrospective with the option to hold ad hoc retrospectives as needed
d)
D. Thank the team for their input and refer the issue to the project sponsor for review and approval
17.
(17) You are the project manager for a large healthcare organization managing the installation of an electronic medical record (EMR) system. The installation requires a lot of different hardware purchases since this will be the first time an EMR has been used in the organization. You have been working through the procurement process, and you are now in the Control Procurements process.
Which of the following activities will you perform as part of that process?
a)
A. Close contracts with sellers
b)
B. Identify potential sellers
c)
C. Review sellers' responses
d)
D. Perform source selection analysis
18.
(18) Which of the following is not true about iteration planning meetings?
a)
A. The recommendation is a high-level summary timeline of the release schedule based on the product roadmap and the vision for the product's evolution.
b)
B. The goal is to commit to working on prioritized product backlog items in the upcoming iteration.
c)
C. The task is to break down user stories into tasks, validating the time estimates for them are achievable based on team capacity.
d)
D. The outcome is an iteration backlog, as well as assumptions, concerns, risks, dependencies, decisions, and actions.
19.
(19) After completing several sprints, it becomes evident that the project won't be able to achieve its objectives. The company decides to terminate the project. At the project retrospective, the participants agree that the lack of adoption of necessary changes by stakeholders resulted in the organization's failure to realize the project's intended benefits.
What was the most likely cause of the failure?
a)
A. Engaging stakeholders and using motivational approaches to assist in change adoption
b)
B. Using effective change management to drive the organization to the desired future state
c)
C. Maximizing change saturation to overcome stakeholder resistance to change
d)
D. Reminding stakeholders of the change benefits during each sprint planning meeting
20.
(20) As you are monitoring the cost baseline for your project, you notice that project expenses are higher than expected at this point in the project.
What is the most likely cause of the variance?
a)
A. Overestimated material costs
b)
B. Lack of stakeholder support
c)
C. An incomplete milestone list
d)
D. Excess inventory
21.
(21) A project is carried out using traditional methods. To produce project deliverables more frequently, the project manager wants to incorporate some agile practices into the team's work. An agile coach is brought in to conduct a workshop with the project team.
What should the project manager do next to verify that the team has acquired the agile skill set needed to meet the project objectives?
a)
A. Facilitate a focus group to evaluate the effectiveness of the workshop and then prepare a team performance assessment
b)
B. Schedule a team-building event to enhance team cohesiveness, improve collaboration, and strengthen interpersonal skills
c)
C. Hold a retrospective and then submit a change request to update the lessons learned register with the knowledge gained
d)
D. Update the RACI chart with the agile knowledge and skills acquired by the project team members during the workshop
22.
(22) The project you are leading is supposed to upgrade the application developed by your company on desktop computers and mobile devices. Last week, a major supplier of electronics unexpectedly released a new mobile device. You realize that your application, with a little bit of modification, can run much faster and more securely on the new device.
What should you do next in regards to this opportunity?
a)
A. Create a cost forecast and communicate it to stakeholders
b)
B. Submit a change request to modify the application
c)
C. Update project funding requirements in consideration for the unexpected work
d)
D. Conduct variance analysis for an appropriate reserve amount
23.
(23) You are leading a project to build single residential houses. The houses will be powered by solar energy. The requirements are very clear, and the project is one of many you have managed in the past. However, due to a technological advance in solar panels, the client requested that you install the latest panels available on the market.
What project management approach is best for you to select for this project?
a)
A. Predominantly agile with some predictive components
b)
B. Predictive during planning and agile during execution
c)
C. Agile during planning and predictive during execution
d)
D. Predominantly predictive with some agile components
24.
(24) As the current sprint is approaching its target date, the project manager measures the queue size of the various Kanban board columns and becomes concerned that the team might miss the sprint goal. The project manager shares their concern with the product owner.
What is the most likely reason for the project manager's concern?
a)
A. The work in progress limits set for the Kanban board columns are too wide for this project.
b)
B. The rate at which the work items arrive in the queue is slower than their completion rate from the queue.
c)
C. The sprint goal the project team committed to has not been coordinated with the product owner.
d)
D. The rate at which the work items arrive in the queue is faster than their completion rate from the queue.
25.
(25) The United Nations initiates a project to develop digital catalogs for every country represented in the organization. The catalogs are supposed to be relatively similar in size and scope. After the scope and cost baselines are approved, the sponsor requests that the catalogs be delivered as they are completed, rather than in bulk at the end of the project.
Which scheduling approach should the project manager avoid for this project?
a)
A. Iterative
b)
B. On-demand
c)
C. Critical path
d)
D. Pull-based
26.
(26) As part of continuous improvement, the team members are looking for ways to optimize the process they use to conduct the work. At the iteration retrospective, an agile coach suggests using a lean production method, which would allow the team to analyze the process and identify and subsequently remove waste.
How should the team implement the agile coach's suggestion?
a)
A. Apply value stream mapping
b)
B. Utilize Wideband Delphi technique
c)
C. Develop a prototype of the process
d)
D. Conduct what-if scenario analysis
27.
(27) A project manager is leading a hybrid project with some project aspects managed using the waterfall framework while others using agile. The product of the project will be developed using an incremental and iterative approach with regular customer feedback and reviews. The project manager is currently conducting an analysis of the stakeholders' influence.
What should the project manager take into account during this analysis?
a)
A. Stakeholder influence will remain strong throughout project execution.
b)
B. Stakeholder influence will be the greatest after the product is released to the market.
c)
C. Stakeholder influence will be greatest during requirements gathering and then decline.
d)
D. Stakeholder influence is not affected by the project management framework.
28.
(28) You have been requested to fill in for a scrum master during the upcoming sprint. As you get yourself familiar with the project team, you feel that the team works as a well-organized unit and only needs you when a decision is required to be made at a higher level within the organization.
Based on your observations, where is the team on the Tuckman ladder?
(On the actual exam, you will be requested to click the correct area in the image. But here in the simulator, please select the answer below.)
a)
A
b)
B
c)
C
d)
D
e)
E
29.
(29) You are leading a project that was supposed to be managed using agile methods. Every week, however, the product owner holds a five-hour backlog refinement meeting with the project team where she presents the project scope broken down to the work package level. After three iterations, the project team's velocity is slower than expected.
What is your best course of action?
a)
A. Ask the product owner to decompose the scope down to the task level and assign the tasks to the team members
b)
B. Advise the product owner to hold two five-hour backlog refinement meetings per week to gain further clarity on the scope
c)
C. Coach the product owner on presenting the overall story concept with one-hour weekly backlog refinement meetings
d)
D. Hold a team-building exercise with the team members and product owner to improve the communication between them
30.
(30) During a sprint retrospective, an issue is raised that some project team members are slow to respond to inquiries resulting in degraded project performance. The identified team members become defensive and claim that no standard had been established for response times.
What might the agile leader do differently going forward to improve project performance?
a)
A. Establish a standard that all inquiries must be responded to within 24 hours
b)
B. Report the underperforming team members to their functional managers for disciplinary action
c)
C. Update the lessons learned register with the delays caused by the slow responses
d)
D. At every subsequent retrospective, review the team's social contract and revise it as needed
31.
(31) The cost of quality is among the data analysis techniques associated with the Plan Quality Management process.
Which of the following are examples of the cost of quality? (Choose three)
a)
B. Costs related to the prevention of poor quality in the products, deliverables, or services of the specific project
b)
E. Costs related to evaluating, measuring, auditing, and testing the products, deliverables, or services of the specific project
c)
F. Costs related to nonconformance of the products, deliverables, or services to the needs or expectations of the stakeholders
d)
A. Forecast project costs to be paid that are derived from the cost baseline for total or periodic requirements
e)
C. Money allocated in the cost baseline for known risks with active response strategies
32.
(32) A company is about to undertake a project that will use new technology. It is expected that the customer will request a very large number of changes throughout the entire project life cycle. The project sponsor indicated that delivering incremental value to the customer frequently while maintaining the cost baseline under control is of the utmost importance for the project.
Which of the following would help the most in addressing the frequent changes?
a)
A. Time-boxing
b)
B. Integrated change control
c)
C. Risk register
d)
D. Quality control measurements
33.
(33) A company considers a project to develop a new mobile app. Since it's unclear how target users will adopt the app, the company decides to develop an early release of the app incrementally with only the must-have features, and then, if feedback from the users is positive, proceed with the full-featured app using a predictive project management approach.
What does the early release of the mobile app represent?
a)
A. Agile release planning
b)
B. Minimum viable product
c)
C. Fully functioning prototype
d)
D. Work breakdown structure
34.
(34) A business considers engaging with a vendor to develop project deliverables. While most of the deliverables have well-defined requirements, some are still unclear and will be discovered and elaborated as the project progresses.
Which of the following is best for the business to use to contract with the vendor?
a)
A. Vendor and contractor conference
b)
B. Request for proposal (RFP)
c)
C. Master services agreement (MSA)
d)
D. Procurement management plan
35.
(35) A project manager is in the process of developing the stakeholder register. As the first step in this process, she needs to create a list of potential stakeholders and decides to use a data gathering technique called brain writing.
What is the first thing to do when using that technique?
a)
A. Convene a data gathering meeting with the participants
b)
B. Develop your own template for a stakeholder register
c)
C. Send a list of questions to participants before the creativity session
d)
D. Consult the stakeholder engagement plan to understand how the stakeholders are to be identified
36.
(36) What are the key benefits of the processes that are part of the Project Communications Management Knowledge Area? (Choose three)
a)
B. Ensuring the optimal information flow as defined in the communications management plan and the stakeholder engagement plan
b)
C. Having a documented approach to engage stakeholders by presenting relevant information in a timely manner
c)
E. Enabling an efficient and effective information flow between the project team members and the stakeholders
d)
A. Providing an actionable and well-documented plan to interact effectively and efficiently with project stakeholders
e)
D. Allowing the project team and the project manager to increase support and minimize resistance from project stakeholders
37.
(37) An agile team is trying to determine the ideal iteration length. The team members are having a long and intense argument about it, but no one is willing to compromise. The scrum master is called in to help resolve the conflict.
What is the best course of action for a scrum master?
a)
A. Avoid being involved in the process and let the team work out toward a consensus
b)
B. Recommend evaluating the pros and cons of each one of the suggested iteration lengths
c)
C. Threaten the team with disciplinary actions if they are unable to come to an agreement
d)
D. Break the impasse by making the decision for the team before relationships are damaged
38.
(38) The resource management plan calls for six developers to serve on the project team who are all internal employees. In the process of putting together the project team, the project manager discovers that only three developers with the necessary skillset are available for the project due to attrition and higher priority projects.
What should the project manager do next?
a)
A. Hire outside contractors to supplement the project team
b)
B. Submit a change request to update the necessary project plans and/or documents
c)
C. Cancel the project since the required resources are not available
d)
D. Run the project with the three available developers and use overtime to stay on schedule
100 %