Set A - DPWH

Total questions: 46

Worksheet time: 23mins

Name
Class
Date
1.

What is the technical term for the slight convexity required in the construction of bridges and is provide to compensate for dead load deflection?

a)

Arc

b)

Cantilever

c)

Camber

d)

Caisson

2.

Which of the following is not included in the exploration of foundation strata?

a)

Driving Test Rod

b)

Drilling Test Hole

c)

Boring with auger

d)

Nuclear Density Test

3.

What is the technical term for a bridge abutment that sits high up on the river bank?

a)

Bank Seat

b)

Caisson

c)

Ballast Wall

d)

Wing wall

4.

What is the usual measure undertaken to stop a river for charging its path?

a)

Shore protection works

b)

Bank seat

c)

River training works

d)

wing wall

5.

Splicing for top bar of continuously reinforced concrete beam?

a)

L/3

b)

L/4

c)

Midspan

d)

NOTA

6.

1059.130 Tones bituminous material, how many kilograms is needed for the testing?

a)

10kg

b)

20kg

c)

15kg

d)

25kg

7.

The application of liquid asphaltic material on a prepared untreated base is?

a)

Prime Coat

b)

Seal coat

c)

Tack coat

d)

NOTA

8.

The application of liquid asphaltic material to an existing surface of base.

a)

Prime Coat

b)

Seal coat

c)

Tack coat

d)

NOTA

9.

Which of the following is not considered as slope protection work?

a)

Piled walls

b)

Stone pitching

c)

Gabions

d)

Cofferdams

10.

When concrete piles are lifted or moved, they should be supported at what point?

a)

Quarter point

b)

Mid-point

c)

Third point

d)

both ends

11.

Which of the following items is not a structured of dam?

a)

Impervious fill

b)

Outlet protection works

c)

Random fill

d)

Distribution canal

12.

The moisture density relation test determines the.

a)

Natural water content

b)

Degree of compaction

c)

Maximum dry density

d)

Organic content

13.

In the Memorandum Circular No. 38 dated 12 November 1981,.a certificate of Quality Control Assurance (CQCA) should be accomplished.

a)

Daily

b)

Weekly

c)

Monthly

d)

Yearly

14.

For testing reinforcing steel bars, the sample for every 10 tons should be:

a)

0.5 meter long

b)

1.5 meter

c)

1.0 meter

d)

2.0 meter long

15.

For a compacted pavement, what does the stability value in the Marshall test measure.

a)

Cohesion resistance

b)

Diametric distortion

c)

Resistance to displacement

d)

Skid resistance

16.

What should the Resident Engineer do when an asphalt pavement under construction attains a density of 85% at the time of compaction?

a)

Require the contractor to spread additional bituminous mixture and compact it to the required density

b)

Require the Materials Engineer to redesign the Job-Mix Formula

c)

Require additional rolling until the minimum density requirement is attained

d)

Require the contractor to replace the roller

17.

The Plasticity Index (PI) required for item 201, Aggregate Base Course materials, should not be greater than:

a)

8%

b)

12%

c)

6%

d)

9%

18.

Adequate compaction of item 201 will result to which of the following:

a)

greater stability

b)

greater resistance to water absorption

c)

decrease in the thickness of base course

d)

A and B.

19.

Under item 310, the asphalt content of bituminous mix on the basis of total dry aggregate should be between:

a)

4% to 8%

b)

5% to 8%

c)

3% to 5%

d)

5% to 7%

20.

Which of the following statements is/are not true regarding traffic controllers on a construction work area?

a)

I only

b)

III only

c)

II only

d)

I and II

21.

The shall monitor all ongoing projects being unimplemented by the Department and reported that contractor/s and implementing offices who are not observing/implementing the Road Works Safety and Traffic Management and Construction Survey and Health requirements.

a)

Bureau of Construction

b)

Bureau of Design

c)

Bureau of Quality and Safety

d)

Bureau of Maintenance

22.

When constructing along the road, there are possible choices of traffic control, one of which is by the use of traffic controller/flagmen. Which of the following would not need flagmen to control the movement of traffic at worksite?

I. Where one lane of a two-way road or bridge is closed.
II. Where distance to the work sites is limited.
III. Where traffic is directed through red traffic signals.
IV. Where construction machinery regularly closes or enters a road.
V. Where there is a need to slow the traffic down to an acceptable speed.

a)

I and II only

b)

III only

c)

V only

d)

I, II, III and IV

23.

For general construction work, the required basic PPEs for all workers shall be Safety Helmet, Safety Gloves and Safety Shoes. Specialized PPEs shall be provide to workers in addition to or in lieu of the corresponding basic PPE as the work or activity requires. Which of the following specialized PPE should be given for workers involved of pouring of concrete, if workers hands may have contact with fresh concrete?

a)

Chemical Resistant Gloves

b)

Heat Resistant Gloves

c)

Occupational safety

d)

High visibility gloves

24.

The refers to a set of detailed rules to cover processes and practices that should be utilized in a specific construction site including the personnel responsible and the penalties for the violation thereof,

a)

Occupational Safety and Health Standard

b)

Construction Safety and Health Standard

c)

Occupational Safety and Health Program

d)

Construction Safety and Health Program

25.

This Department Order set the guidelines, rules and procedure to be followed by all concerned in the implementation of DOLE D.O. No. 13 series of 1998 otherwise known as the Guidelines Governing Occupational Safety and Health in the Construction Industry, with emphasis in the methodology to be used in estimating the cost of construction safety and health program as required in this section 17.

a)

D.O. 56, series of 2003

b)

D.O. 56 series of 2004

c)

D. O. 56 series of 2005

d)

D.O. 56 series of 2006

26.

Road work signs shall be installed before work starts in the following sequence.

a)

Advance Warning, Driver Instruction Signs, Other Warning Signs

b)

Advance Warning, Other Warning Signs, Driver Instruction Signs

c)

Driver Instruction Signs, Advance Warning, Other Warning Signs

d)

Other Warning Signs,, Advance Warning, Driver Instruction Signs

27.

A shifts a line traffic sideways where the traffic must join with another line of traffic travelling in the same direction.

a)

Merge Taper

b)

Lateral Merge Taper

c)

Lateral Shift Taper

d)

Merge Shift Taper

28.

Which of the following road classification is proposed for road corridor connecting several highway urbanized centers with ribbon-type of development of commercial business and industrial establishment?

a)

national road

b)

arterial road

c)

expressway

d)

Provincial road

29.

The following are important elements to consider for barangay roads except;

a)

Vehicle flows to be kept minimum

b)

All through traffic eliminated

c)

Pedestrians and vehicles can share space

d)

Parking and stopping within streets are prohibited

30.

An acacia tree was found protruding the carriageway of a newly widened national road. Frequent night-time road crashes were noticed to be associated by the presence of this tree. What is the best solution for this problem?

a)

Install hazard markers on the tree to make it visible at night

b)

Install bollards

c)

Install light poles

d)

Remove tree

31.

The following are the communication principles for a good signage and markings except;

a)

Conspicuous

b)

Clear

c)

Concise

d)

Comprehensible

32.

The is an area where drivers are redirected out of their normal path of travel if a roadway needs to be partially closed due to road works.

a)

Transition area

b)

Approach clearance area

c)

Advanced road work area

d)

Transitory area

33.

The depth of weakened plane joints should not less than:

a)

45mm

b)

50mm

c)

60mm

d)

75mm

34.

Unless otherwise specified, all materials below subgrade level in earth should be cut to a depth of:

a)

100mm

b)

150mm

c)

200mm

d)

250mm

35.

In the DPWH Standard Specifications, What is the item no. of excavation?

a)

100

b)

102

c)

104

d)

105

36.

When a project is delayed, and the contractor desired to complete the project on time, he may submit to approval;

a)

Request for time extension

b)

Catch-up schedule

c)

Request for variation order

d)

Revised S-curve

37.

Which of the following is not a result of poor materials control in a project?

a)

Wastage and breakages

b)

Inflation

c)

Theft and loss

d)

Short delivers

38.

What do you call the complementary drawings prepared by a contractor or supplier which show how specific structural elements or items of equipment are to be fabricated and installed?

a)

Method specification

b)

Supplemental plans

c)

Shop drawing

d)

Catalog drawing

39.

When will the certificate of Final Inspection be issued?

a)

after the supervision team has conducted final inspection

b)

after the inter-bureau committee has conducted inspection

c)

after the contractor has submitted the final inspection

d)

after the one-year warranty period

40.

Unbalanced bid items should be paid in full when subject major item has been completed and the entire project is:

a)

20% completed

b)

70% completed

c)

50% completed

d)

80% completed

41.

If the minimum compressive strength for concrete class A concrete is 20.7 mpa, what is the minimum compressive strength for concrete class C?

a)

16.5MPA

b)

28.5MPA

c)

20.7 MPA

d)

37.7 MPA

42.

Pile cap dimension from sheet pile

a)

100mm

b)

150mm

c)

250mm

d)

300mm

43.

200mm thk. aggregate sub base course to compact each layer

a)

1 layer

b)

2 layer

c)

3 layer

d)

4 layer

44.

1098.CHB rebar horizontal location at every?

a)

1 layer

b)

2 layer

c)

3 layer

d)

4layer

45.

When you poured at single lane of concrete pavement

a)

500 Ln.m

b)

1000 In.m

c)

400 In.mp

d)

900 Ln.m

46.

Deficiency of asphalt

a)

1%

b)

3%

c)

2%

d)

4%