FAB-101 EPA Week 5 Homework (Type III)

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

What is the maximum test pressure for leak testing a low-pressure centrifugal chiller with nitrogen?

a)

5 psig

b)

10 psig

c)

15 psig

d)

20 psig

2.

How can charged low-pressure refrigeration machines be most effectively leak checked?

a)

By adding refrigerant

b)

By reducing pressure

c)

By adding heat with hot water or heating blankets

d)

By cooling the system

3.

What type of compressors are particularly susceptible to leaks from the shaft seal?

a)

Open-drive type compressors

b)

Closed-drive type compressors

c)

Rotary compressors

d)

Scroll compressors

4.

According to ASHRAE Guideline 3, when should a system be checked for leaks?

a)

If pressure rises from 1 mm Hg to 2.5 mm Hg

b)

If pressure drops from 2.5 mm Hg to 1 mm Hg

c)

If temperature increases

d)

If refrigerant levels decrease

5.

What happens once the threshold leak rate has been exceeded on a system using a regulated refrigerant?

a)

The system must be replaced

b)

The system must be repaired

c)

The refrigerant must be removed

d)

The refrigerant must be increased

6.

As of January 1, 2019, what is the maximum leak rate for comfort cooling?

a)

10% of the charge per year

b)

20% of the charge per year

c)

30% of the charge per year

d)

40% of the charge per year

7.

How long does an owner have to repair an appliance that has 50 pounds or more of refrigerant and has exceeded the threshold leak rate?

a)

10 days

b)

18 months

c)

30 days

d)

3 years

8.

What is the typical high-pressure cut-out control setting for a low-pressure chiller?

a)

0 psig

b)

5 psig

c)

10 psig

d)

15 psig

9.

What is the deadline for conducting an initial verification test after a chiller with 200 pounds of refrigerant passes the initial leak test?

a)

5 days

b)

10 days

c)

15 days

d)

20 days

10.

What should be done to refrigerant oil before removal to ensure less refrigerant is contained in the oil?

a)

Cool it to 32°F

b)

Heat it to 130°F

c)

Freeze it to 0°F

d)

Boil it to 212°F

11.

What is the required recovery vacuum for a low-pressure appliance to be disposed?

a)

10 mm of Hg absolute

b)

15 mm of Hg absolute

c)

20 mm of Hg absolute

d)

25 mm of Hg absolute

12.

What is the effect of warming the liquid refrigerant in the system with hot water?

a)

It increases system pressure

b)

It brings the system pressure out of a vacuum

c)

It decreases system pressure

d)

It freezes the refrigerant

13.

How should all pressure relief valves be installed in machine rooms?

a)

In series

b)

In parallel

c)

Randomly

d)

Vertically

14.

What safety equipment should be worn when working with liquid refrigerant for low-pressure systems?

a)

Hard hat and boots

b)

Gloves and safety goggles

c)

Ear plugs and mask

d)

Apron and face shield

15.

When the TLV-TWA is exceeded what is required?

a)

An evacuation of the building and Emergency First Responders notified.

b)

Each machinery room activate an alarm and a mechanical ventilation system.

c)

To pull the fire alarm to safely evacuate the building.

d)

To notify the Safety Commissioner on staff.