Project Delivery Methods and Contracts

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

Which of the following is NOT a typical role of the owner in a construction project?

a)

Paying for the facility

b)

Designing the structure

c)

Setting project requirements

d)

Hiring contractors

2.

In a traditional Design-Bid-Build (DBB) project delivery method, which sequence is correct?

a)

Construction → Design → Bidding

b)

Design → Bidding → Construction

c)

Bidding → Design → Construction

d)

Bidding → Construction → Design

3.

What is the primary role of the Consultant (Construction Manager) in a project?

a)

Representing the owner on-site

b)

Signing contracts with designers

c)

Acting as a subcontractor

d)

Designing the structure

4.

Which project delivery method combines the design and construction phases under a single contract?

a)

Design-Bid-Build

b)

Design-Build

c)

Construction Management

d)

Lump Sum

5.

Which of the following is a key disadvantage of the Lump Sum contract type?

a)

High risk for the owner

b)

Low risk for the contractor

c)

Limited flexibility for design changes

d)

Owner must estimate uncertain quantities

6.

In a Guaranteed Maximum Price (GMP) contract, who bears the cost if the project exceeds the agreed maximum price?

a)

The owner

b)

The contractor

c)

The subcontractor

d)

The consultant

7.

What is a key feature of Unit Price contracts?

a)

The total price is fixed before construction

b)

The contractor submits prices per unit of work

c)

The contractor bears all financial risk

d)

Design and construction are done by the same entity

8.

Which project delivery method typically results in reduced project duration by allowing construction and design phases to overlap?

a)

Traditional Design-Bid-Build

b)

Lump Sum

c)

Fast Track Construction

d)

Unit Price

9.

In a Cost-Plus contract with a fixed fee, what motivates the contractor to complete the project quickly?

a)

Increased cost leads to increased profit

b)

They receive a percentage of the total cost

c)

A fixed fee ensures that longer durations do not increase profit

d)

There is no motivation to finish early

10.

Which of the following is NOT a contractual relationship in a construction project?

a)

Contractual relationship

b)

Communicational relationship

c)

Internal relationship

d)

Financial relationship