Total questions: 88
Worksheet time: 44mins
What is a deliverable?
A unique output of a project
A resource allocated to the project
A checkpoint in the project timeline
A team member working on a project
Your customer states that the packaging for the new product being developed must be easy for everyone to open. During product testing, only 60% of the people were able to open the packaging easily. As the project manager, what should you do?
Request a team meeting to decide on corrective action.
Inform the project sponsor that the project has failed.
Meet with the product testers to change the results.
Inform the customer that more than 50% is an acceptable result
What is a project life cycle?
The sequence of activities that determines the shortest possible duration of a project
The tasks performed to deliver a product, service, or result with specified features and functions
The series of phases that a project passes through from its start to its completion
The steps used to identify the best possible solution to a problem
What is a benefit of creating a lessons learned document?
Sharing best practice approaches among the team members
Creating marketing materials that can be used to promote the product
Meeting with the client to provide closure to the project
Ensuring team members are held responsible for their mistakes
What is a key characteristic of the adaptive project management approach?
Continuous refinement of the product based upon stakeholder feedback
Minimal changes due to familiarity with project requirements
Sequential completion of tasks with no change in scope
Delivery of the product after the final phase has been completed
You are part of a project team that is working on developing a new app. A team member suggests that you add a feature to the app. The project manager says that the feature is out of scope. What should you do if a product feature is out of scope?
You should decline the development of the feature.
You should develop the feature as part of the project.
You should consider the feature a project dependency.
You should add the feature to the scope statement.
What role does quality assurance play in the project development process?
It ensures the project is delivered within budget.
It ensures procedures are followed to meet standards for performance.
It ensures employees are qualified to complete their assigned tasks.
It ensures the project is delivered on time.
Which scenario demonstrates a schedule dependency?
Team members must schedule activities during business hours.
Team members must wait to start a task until after another task is completed.
Team members must work independently on tasks.
Team members must determine the minimum time necessary to complete a project.
You are an event coordinator for an upcoming party. The customer changes the party date. You know that this change will result in an increase in the cost of the venue. What should you do to resolve the budget variance?
Determine the cost difference and discuss options with the customer.
Cancel the venue contract and then find a new venue.
Stay at the same venue and tell the caterers to remove menu items to save money.
Approve the date change and invoice the customer for more money.
Which action signifies the formal acceptance of the final product?
Closing of vendor contracts by the project team
Final budget approval by the project manager
Completion of all paperwork by the project manager
Approval by the project sponsor and customer
You are the project manager for a small construction project. You receive an updated quote from one of the material suppliers and the cost has increased by $2000. You request a meeting with your project sponsor to discuss what to do next. Which stage of the change management process are you beginning?
Identify the change
Approve the change
Assess the change impact
Implement the approved change
Recent feedback from a client requires adjusting the scope of a project as well as some additional funding. Who needs to provide the approval to move forward with the changes?
Business analyst
Project manager
Project sponsor
Resource manager
You need to select a project management approach for your team. Key considerations include:
• The team has worked on similar projects
• The deliverable must comply with standards and regulations.
• The project tasks are well-defined
• The project deliverable is clearly defined.
What project management approach should you choose?
Scrum
Adaptive
Predictive
Incremental
Which project document authorizes the project manager to begin working on a project?
Project management plan
Project scope statement
Project charter
Project communication plan
You are one of the team members planning a small community event. The project manager assigns you the task of planning for the event at a specific location. You find a better location and want to alert your team to the change in location. What responsibility and authority do you have regarding your assigned task?
You need to speak with the project manager about changing the location and wait for approval.
You can change the location without approval and set up for the community event.
You cannot approve the location change until all team members have voted on the decision.
You need to inform the sponsor directly about the change and then move the event to the new location.
What impact does gold plating have on a project?
The scope increases and the cost to the customer remains the same.
The scope increases and the cost to the customer increases.
The scope remains the same and the cost to the customer decreases.
The scope remains the same and the cost to the customer increases.
You are evaluating the skills needed in your project team to successfully complete a project. Which component of the project management plan are you working on?
Cost management plan
Scope management plan
Schedule management plan
Resource management plan
Which component of the project management plan outlines the work needed to meet project objectives and deliverables?
Cost management plan
Scope management plan
Resource management plan
Schedule management plan
Which project characteristic suggests that a predictive project management approach should be used?
High levels of change and risk
Defined deliverables and deadlines
Evolving goals and requirements
Multiple releases of product features
What is project procurement?
The purchasing of external goods and services needed to complete a project
The analysis of the business requirements needed to complete a project
The identification of all the funding requirements needed to complete a project
The planning of all communication methods needed to complete a project
In a project, what describes work that should be included and work that should be excluded?
Project baseline
Scope statement
Business case
Work breakdown structure (WBS)
You are estimating the cost of a project by using the budget from a similar project last month. Which type of budget estimation technique are you using?
Expert judgment estimation
Three-point estimation
Bottom-up estimation
Analogous/historical estimation
Why should you archive project documents and processes?
To complete the project management plan
To store all project documents on the project manager's personal computer
To keep a historical record of project activities
To redistribute remaining resources to other projects
You are estimating the cost of a project by using the budget from a similar project last month. Which type of budget estimation technique are you using?
Expert judgment estimation
Three-point estimation
Bottom-up estimation
Analogous/historical estimation
You are managing a project that is experiencing significant scope creep. What is the impact on the project?
The project will require fewer resources to develop.
The project will take additional time to complete.
The project will be assigned a new project manager.
The project will include fewer deliverables.
What is a vendor?
A business analyst who works with the finance team for a project
An external supplier who provides goods or services to a project
A procurement team member who negotiates contracts for a project
An experienced business professional who can sell the final product
As a project manager, what information do you need to include in a status update to your boss?
Project work that has been completed
A list of project stakeholders
Project goals and objectives
A description of the project scope
Your project team is using an agile project delivery method. In preparation for an upcoming meeting, your manager asks you to review the prioritized list of deliverables. What should you review?
Kanban board
Backlog
User story
Work breakdown structure (WBS)
As a project manager, how should you encourage your team to be focused, energized, and positive for the duration of a project?
Discover what personally motivates each team member.
Report poor behavior to upper management.
Give each team member the authority to change project deadlines.
Rank team members' performance during team meetings.
What is the primary goal of creating a work breakdown structure (WBS)?
To prepare an organizational chart for the project team members
To describe the key stakeholders and their roles in the project
To decompose the project work into assignable work activities
To determine which team members will be responsible for each project activity
Who is responsible for overseeing the daily activities of a project from start to finish?
Project manager
Client
Vendor
Sponsor
A project team is arguing about the start date for an important task in the project. The project sponsor intervenes and sets the start date. Which type of conflict resolution technique is the project sponsor using?
Avoiding
Smoothing
Forcing
Collaborating
You are one of the event planners for a large town festival. You are reviewing a list of potential bakeries that will supply the desserts at the festival. When you review the list, you notice that your favorite aunt owns one of the bakeries, but no one else on your team knows this information. According to project management ethical guidelines, what should you do?
Tell your aunt to lower her prices so that she can be easily selected for the event.
Inform your aunt that she will need to remove her bakery from the selection list.
Proceed with the selection process, confident that you will act fairly.
Notify your supervisor that your aunt's bakery is on the list.
What is the purpose of following a change management process?
To document a change in scope and any impact to the project
To delay a new feature request so the customer will reconsider any changes
To inform the customer that your team takes their suggested product changes seriously
To show the project sponsor that you follow correct procedures
As a project manager, which activity should you perform when using a predictive project management approach?
Create a detailed project plan that includes all of the project activities.
Begin the current sprint before planning for the next one.
View the backlog to determine the next planning activity required.
Review deliverables after each iteration with the customer
A community center director hires your project team to build a playground for the families in the community. Upon completion of the playground, who is responsible for the final acceptance of the project?
The director (your client)
The project team
The families in the community
The project manager (you)
You have contracted an external supplier to provide a tool needed for the development phase in a project. The tool has been delivered and the project team finds the tool acceptable and they are using it. Why should you now close the contract with the supplier?
To inform the procurement team that the new tool has been delivered
To prevent the supplier from contacting team members for payment
To request that the supplier be paid for the delivery of the tool
To thank the supplier for delivering the tool according to the contract
Your manager explains that the project team starts every new project with a design stage where they create a design, test the design, make updates to the design, retest, and then create a final design. After this design stage, they create and follow a detailed project plan for all the remaining project deliverables. Which project management approach are they using?
Hybrid
Predictive
Scrum
Adaptive
Who has the authority to choose a new style for the replacement tiles?
The project team
The business analyst
The project manager
The customer
How does an adaptive project management approach engage customers?
It encourages customers to contribute to the lessons learned process.
It encourages customers to complete sections of the project management plan.
It encourages customers to provide continuous feedback.
It encourages customers to complete tasks on the project backlog.
Why is quality assurance included in the project development process?
To evaluate the performance of new employees
To motivate project team members to complete project milestones on time
To ensure products meet specifications and requirements
To provide training for project team members
You need to select a project management approach for an upcoming project. Key considerations include:
• You are working with new technologies and processes.
• The scope of the project is unclear.
• The client wants to be informed and involved in all phases of the project.
• You have a highly qualified and motivated team.
• The project requires a significant amount of testing and retesting.
Which project management approach should you choose?
Adaptive
Predictive
Hybrid
Critical path
While working on your current project, the team learned a new, creative approach to managing project resources. What is a benefit of reporting this new approach in the lessons learned documentation?
To inform other teams of the new approach
To inform the legal team of the new approach
To inform competitors of the new approach
To inform the client of the new approach
What is a vendor?
A procurement team member who negotiates contracts for a project
An experienced business professional who can sell the final product
An external supplier who provides goods or services to a project
A business analyst who works with the finance team for a project
At a team meeting, your project sponsor states the customer is concerned that the software being developed will not perform reliably. As the project manager, how should you respond?
Ask the engineering team to increase software reliability.
Email the customer to inform them reliability will be addressed at the end of the project.
Meet with the customer to understand the basis of their concerns.
Inform the project sponsor that the customer is using old performance data.
In a project, who has the highest level of authority to make project decisions such as changes to the project scope, schedule, or budget?
The business analyst
The sponsor
The quality assurance manager
The project manager
You are creating a budget for your project by calculating the accurate cost of each activity in the project. Which method of budget development are you using?
Three-point estimate
Analogous/historical comparison
Top-down
Bottom-up
During a project, your team develops new procedures to create certain product features more efficiently. Why should the team archive the project documents and new procedures?
To show the sponsor the efficiency of the team
To provide reference material for teams working on similar projects
To identify the employees that discovered the new procedures
To receive recognition for developing new procedures
What describes a project's requirements, including major deliverables and exclusions of the project?
Scope statement
Status report
Work breakdown structure
Business case
You are managing a project that is experiencing significant scope creep. What is the impact on the project?
The project will require fewer resources to develop.
The project will be assigned a new project manager.
The project will include fewer deliverables.
The project will take additional time to complete.
You are a team member working on a project. All the team members signed a non-disclosure agreement (NDA) and promised not to share information with other people outside of the project team. You witness a team member talking about the project to someone outside the According to project management ethical guidelines, what should you do?
Send an email to all employees with the definition of non-disclosure.
Let the project manager discover and take care of the issue.
Bring the situation to the attention of the project manager.
Remind the team about the importance of keeping project details confidential.
Which action signifies the formal acceptance of the final product?
Closing of vendor contracts by the project team
Approval by the project sponsor and customer
Final budget approval by the project manager
Completion of all paperwork by the project manager
You are part of a project team that is working on developing a new app. A team member suggests that you add a feature to the app. They says that the feature is out of scope. What should you do if a product feature is out of scope?
You should develop the feature as part of the project.
You should add the feature to the scope statement.
You should consider the feature a project dependency.
You should decline the development of the feature.
Which document is issued by the project sponsors to formally authorize the existence of a project and is the starting point for initial project planning?
Procurement contract
Scope statement
Project charter
Project management plan
What is a dependency?
The difference between the estimated and the actual length of a task
An accidental change in project requirements
A relationship between two or more tasks
The work needed to complete the project
You are an event planner for an upcoming wedding. In your meetings with the couple, they often disagree about colors and styles for the wedding decorations. When you try to get involved, it tends to make the disagreement worse so you decide to give them time to talk about their choices. Eventually the couple agrees on a joint decision. Which conflict resolution technique are you using?
Withdrawal
Collaborating
Compromising
Forcing
You are a project team member working on a community festival. Your project manager assigns you the task of creating a map of all the games, rides, and vendors at the festival. You want to take another team member off their assigned task to help you, which will save you half the time. What responsibility and authority do you have regarding your assigned task?
You need to promise your team member that you will help them after they help you.
You need to get approval from the project manager before asking for help.
You can reassign tasks as long as both tasks are completed on time.
You can use your team member's help as long as you complete your assigned task faster.
You are an event coordinator and meet with the customer to review the current status of the project. When reviewing the event invitations, your customer requests a change in the design work. Which stage of the change management process does this represent?
Implement the approved change
Identify the change
Assess the change impact
Approve the change
What is a deliverable?
A result created as an outcome of a project
A task that leads to a larger outcome
An organized list of activities
A set of resources needed to accomplish an activity
Which project characteristic suggests that a predictive project management approach should be used?
Multiple releases of product features
High levels of change and risk
Defined deliverables and deadlines
Evolving goals and requirements
A project team is having difficulty meeting deadlines and focusing on the tasks that need to be completed. After meeting with each team member, the project manager decides to offer a paid bonus to three of them, extra time off to two of them, and the ability to work remotely to the remaining two members if they complete the project on time. Why did the project manager decide to provide the team members with different perks?
The project manager wanted to reward the team with something fun.
The project manager discovered how to motivate each team member individually.
The project manager had additional budget that needed to be spent.
The project manager hoped that random perks would inspire the team to work harder.
What impact does gold plating have on a project?
The scope increases and the cost to the customer remains the same.
The scope increases and the cost to the customer increases.
The scope remains the same and the cost to the customer decreases.
The scope remains the same and the cost to the customer increases.
What is a purpose of including a schedule in the project management plan?
To communicate project deliverable deadlines
To obtain management support for the project
To evaluate the work performance of the team
To assign team members to different activities
Who is responsible for completing project deliverables?
Sponsors
Product managers
Business analysts
Team members
What is project procurement?
The planning of all communication methods needed to complete a project
The identification of all the funding requirements needed to complete a project
The analysis of the business requirements needed to complete a project
The purchasing of external goods and services needed to complete a project
What should you include in the project purpose section of the project charter?
A description of the business need
An outline of the key points in time in the project
A list of key milestones
A statement describing the expected deliverables
You provide the following information to your boss.
• Work planned vs. work completed
• Budget planned vs. budget spent
• Issues or roadblocks
Which type of communication are you providing?
A contingency plan
A business plan
A project charter
A status update
Which statement describes the main purpose of using a change management process?
To list project scope requirements and create an initial scope baseline
To discuss new requirements and have customers add them to the work breakdown structure (WBS)
To document all modifications and formalize their approval
To identify new stakeholders and add them to the stakeholder register
You are the project manager for an upcoming bicycle race. You discover that road construction nearby may interfere with the path of the race. Which part of the project management plan should you update?
Schedule
Risk
Cost
Resource
Which statement describes a characteristic of a predictive project management approach?
Planning is completed for the entire scope of the project at the beginning.
Planning is completed for deliverables needed in the next two weeks.
Planning is completed in short increments as part of a cycle.
Planning is completed annually as part of a company finance cycle.
Why is contract closure an important element of project closing?
It ensures that the work described in the contract was completed as specified
It ensures that workers can no longer access project materials.
It ensures that the project management plan is updated with contract completion status.
It ensures that the project budget has enough money to cover the expenses.
The hardware prototype will be developed according to product specifications in the project management plan with minimal customer feedback. Which type of project management approach does this scenario describe?
Hybrid
Incremental
Adaptive
Predictive
You are a project coordinator working to build a new house. You are meeting with the customer to review progress when they notice that the kitchen cabinets that were installed do not match the kitchen cabinets that they selected as part of the scope. What should you do to resolve the scope variance?
Contact the cabinet maker to order the right cabinets, regardless of the impact on the schedule and cost.
Require the customer to accept the house as-is and give them a discount on the house price.
Discuss options with the customer to correct the issue and gain their approval on the course of action.
Communicate with the customer that the project will be over budget with any additional changes and their house price will increase.
Why is contract closure an important element of project closing?
It ensures that the project budget has enough money to cover the expenses.
It ensures that workers can no longer access project materials.
It ensures that the work described in the contract was completed as specified.
It ensures that the project management plan is updated with contract completion status.
What is the purpose of a work breakdown structure (WBS)?
To identify all the stakeholders impacted by a project
To identify all the activities needed to complete a project
To identify all the communication methods needed for a project
To identify all the roles and responsibilities in a project
Which project characteristic suggests that a predictive project management approach should be used?
High levels of change and risk
Evolving goals and requirements
Defined deliverables and deadlines
Multiple releases of product features
In a project, who has the highest level of authority to make project decisions such as changes to the project scope, schedule, or budget?
The project manager
The business analyst
The quality assurance manager
The sponsor
In an adaptive project management approach; which statement describes the actions of team members?
They work on the highest priority items in the product backlog.
They work through all the tasks sequentially to complete the final product.
They gather all customer requirements at the beginning of the project.
They take turns leading the project so they can each gain experience in leadership.
Which document is issued by the project sponsors to formally authorize the existence of a project and is the starting point for initial project planning?
Project charter
Procurement contract
Project management plan
Scope statement
Predictive and adaptive project management approaches have different key characteristics. For each key characteristic, select Predictive or Adaptive.
Reliance on customer input throughout the project.
Predictive
Adaptive
Predictive and adaptive project management approaches have different key characteristics. For each key characteristic, select Predictive or Adaptive.
Increased flexibility to make project adjustments
Predictive
Adaptive
Predictive and adaptive project management approaches have different key characteristics. For each key characteristic, select Predictive or Adaptive.
Completion of project according to the project management plan created at the beginning of the project
Predictive
Adaptive
You have received a request to add a new scope item to your project and need to follow the change management process. Move the four actions to the answer area and place them in the correct order.
Assess the change impact
Identify the change
Approve or deny the change
Implement the approved change
Identify the change
Assess the change impact
Approve or deny the change
Implement the approved change
Assess the change impact
Approve or deny the change
Implement the approved change
Identify the change
Predictive and adaptive project management approaches have different key characteristics. For each project description, select Adaptive or Predictive.
The project is executed in sprints.
Predictive
Adaptive
Predictive and adaptive project management approaches have different key characteristics. For each project description, select Adaptive or Predictive.
The client is flexible to what the end deliverable will look like.
Predictive
Adaptive
Predictive and adaptive project management approaches have different key characteristics. For each project description, select Adaptive or Predictive.
The project has clear deliverables, specific deadlines, and follows the project management plan closely.
Predictive
Adaptive
Move all the project life cycle phases to the answer area and place them in the correct order.
Initiating the project
Organizing and preparing
Carrying out the work
Ending the project
Organizing and preparing
Initiating the project
Carrying out the work
Ending the project
Organizing and preparing
Carrying out the work
Initiating the project
Ending the project
You are managing a house painting project. Move each change management process step from the list on the left to the scenario that describes it on the right.
1. You request a cost estimate for 15 gallons of paint. (Assess the change impact)
2. 15 gallons of paint are delivered to the construction site. (Implement the approved change)
3. The sponsor tells the purchasing manager to buy 15 gallons of additional paint. (Approve the change)
4. The construction manager informs you that the team will need an additional 15 gallons of paint. (Identify the change)
1. You request a cost estimate for 15 gallons of paint. (Implement the approved change)
2. 15 gallons of paint are delivered to the construction site. (Approve the change)
3. The sponsor tells the purchasing manager to buy 15 gallons of additional paint. (Assess the change impact)
4. The construction manager informs you that the team will need an additional 15 gallons of paint. (Identify the change)
1. You request a cost estimate for 15 gallons of paint. (Identify the change)
2. 15 gallons of paint are delivered to the construction site. (Implement the approved change)
3. The sponsor tells the purchasing manager to buy 15 gallons of additional paint. (Approve the change)
4. The construction manager informs you that the team will need an additional 15 gallons of paint. (Assess the change impact)