Quiz 5 Training Project Management [17/04/25]

Total questions: 5

Worksheet time: 10mins

Name
Class
Date
1.

Kumar, the project manager of the Antom project, is reviewing his project schedule network diagram, which is shown on the screen.

What is the free float of Activity AC?

a)

Activity AC has a free float of 2 days

b)

Activity AC has a free float of 6 days

c)

Activity AC has a free float of zero days

d)

Activity AC has a free float of 4 days

2.

You are currently executing some activities in the Monitor and Control Project Work process. Which of the following may be part of these activities?

a)

Providing forecasts to update current cost

b)

Ensuring that the project stays aligned with the business needs

c)

Determining whether the corrective actions are effective

d)

All the above

3.

You are taking over a project in your organization because of its schedule delay and you are requested to control this schedule. The first step you took was collecting information.

If the planned value was $132 K, which of the following will be your SPI?

a)

0.9

b)

1.1

c)

1.0

d)

1

4.

After executing the Validate Scope process, which of the following describes the best way to deal with the resulted work performance information?

a)

The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and added to the lessons learned register

b)

The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and communicated to the stakeholders

c)

The information about the deliverables that have been accepted is documented and communicated to the stakeholders

d)

The information about the deliverables that have not been accepted and the reasons why are documented and communicated to the stakeholders

5.

You are managing a project for the first time in your organization. You are executing the earned value analysis from time to time to review the project performance.

Today when executing the same analysis, you got a planned value of 450, actual cost of 480, and the CPI was 0.95. What is the status of your project work?

a)

More project work was completed than planned

b)

Less project work was completed than planned

c)

Project work was completed as planned

d)

None of the above