Post-Test Training Project Management [17/04/25]

Total questions: 50

Worksheet time: 57mins

Name
Class
Date
1.

What are five integrated elements of PRINCE2?

a)

Principles, Processes, Practices, People, and Project Environment

b)

Principles, Processes, Themes, People, and Tailoring

c)

Process, Principles, Practices, People, and Project Context

d)

Process, Principles, Themes, People, and Project Context

2.

How many Principles are implemented in PRINCE2 Project?

a)

5

b)

7

c)

10

d)

9

3.

In PRINCE2, how many layer of structure in defining the boundary of the project management team?

a)

5 layers

b)

2 layers

c)

4 layers

d)

3 layers

4.

Which process defines the work to deliver the

major products ensuring that an organization uses

its resources effectively?

a)

Initiating a project

b)

Starting up a project

c)

Controlling a stage

d)

Managing product delivery

5.

As a project manager, when do you use the Tuckman ladder?

a)

Measuring the team performance

b)

Describing team development

c)

Managing the team behaviors

d)

Empowering the team

6.

What is the most common project organization in EPC/EPCI Contractor?

a)

Matrix Organization

b)

Projectized Organization

c)

Semi-Matrix Organization

d)

Project Team Organization

7.

Which PRINCE2 practice focuses on identifying and addressing uncertainties in the project?

a)

Plans

b)

Quality

c)

Risk

d)

Change

8.

Which process should be used to confirm that the project continues to deliver against the strategic objectives?

a)

Closing a project

b)

Initiating a project

c)

Managing a stage boundary

d)

Managing product delivery

9.

How many project development types according to PUDW?

a)

10

b)

9

c)

11

d)

8

10.

Which TWO are objectives of the 'starting up a project' process?

1. To create a common view of how the required quality will be achieved

2. To give authority to initiate the project

3. To appoint the resources needed to do the work to initiate the project

4. To ensure that projects are initiated based on agreed acceptance criteria for the project product

a)

1 and 2

b)

2 and 3

c)

3 and 4

d)

1 and 4

11.

Kristin has a schedule delay in her project. As part of controlling her schedule, she added more resources to the project to shorten the schedule period.

Which tool did she use?

a)

Crashing

b)

Resource smoothing

c)

Fast tracking

d)

Resource leveling

12.

Which of the following contents are expected to be in the stakeholder register?

a)

Potential for influencing project outcomes

b)

Stakeholders raised issues

c)

Stakeholders identified risks

d)

All the above

13.

PUDW can be applied to projects in which category?

a)

Organic for both BD & NBD

b)

Organic and Inorganic

c)

Inorganic for both BD & NBD

d)

Exploration and Inorganic

14.

Due to market changes, you are requested by the customer to shorten the project duration by 15% to get the project benefits earlier and to have a good chance to compete in the new market conditions. Your project has scarce resources, so it is hard to add more resources. Your customer shows some tolerances for quality risk.

What is the technique that will best fit you in decreasing your project duration?

a)

Resource smoothing

b)

Crashing

c)

Variance analysis

d)

Fast tracking

15.

The salience model describes classes of stakeholders based on

a)

Assessments of their power

b)

Need for immediate attention

c)

Ability to influence the outcomes of the project

d)

All the above

16.

Which of the following processes decomposes work packages into schedule activities to provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work?

a)

Sequence Activities

b)

Develop Schedule

c)

Estimate Activity Durations

d)

Define Activities

17.

Which term is defined as a product that will not

meet its quality specifications?

a)

Off-specification

b)

Request for change

c)

Concern

d)

Problem

18.

Sam is defining his project scope with the project team and the subject matter experts. He found some items outside the scope and he needs to point out clearly to his customer that they are not part of his deliverables to avoid future disputes.

Where should Sam add these scope exclusions?

a)

In the scope statement

b)

In the scope register

c)

In the scope management plan

d)

In the exclusion register

19.

Which of the following roles is NOT part of the PRINCE2

project management team structure?

a)

Project Executive

b)

Project Manager

c)

Senior Supplier

d)

Senior Manager

20.

What is most common delivery method in Oil & Gas Upstream Project?

a)

Hybrid

b)

Agile

c)

Iterative-Incremental

d)

Linear-Sequential

21.

The Power/interest grid technique is used by Allan to categorize the stakeholders in his project. Which of the following is considered classification of the stakeholders using this technique?

a)

Stakeholders' level of authority

b)

Stakeholders' level of concern about the project’s outcomes

c)

Stakeholders' ability to influence the outcomes of the project

d)

All the above

22.

Who owns the business case in a PRINCE2 project?

a)

Project Manager

b)

Project Executive

c)

Team Manager

d)

Project Support

23.

Kumar, the project manager of the Antom project, is reviewing his project schedule network diagram, which is shown on the screen.

What is the free float of Activity AC?

a)

Activity AC has a free float of 2 days

b)

Activity AC has a free float of 6 days

c)

Activity AC has a free float of zero days

d)

Activity AC has a free float of 4 days

24.

What is PUDW stands for?

a)

Project Upstream Drilling Way

b)

Pertamina Upstream Development Way

c)

Project Upstream Development Way

d)

Proposal Upstream Development Way

25.

"If a project does not align anymore with the benefits then the project should be stopped".

This principle is known as?

a)

Project Context

b)

Ensure Business Justification

c)

Manage by Stages

d)

Sustainability

26.

Project Review in Eksekusi consist of:

a)

TRM, PRR-2, PRR-3 and GR-4

b)

PRR-2, PRR-3, Assessment and GR-4

c)

PRR-2 and PRR-3

d)

PRR-2, PRR-3 and Post-Mortem

27.

How many process groups and Knowledge Areas in Project Management accoording to PMBOK 6th Edition?

a)

4 process groups & 15 Knowledge Areas

b)

49 process groups & 8 Knowledge Areas

c)

45 process groups & & 10 Knowledge Areas

d)

5 process groups & 10 Knowledge Areas

28.

When is "Tahap Eksekusi" in PUDW started?

a)

After gaining FID approval

b)

After gaining FID approval and budgeted in RKAP

c)

After budgeted in RKAP and gaining AFE approval

d)

After awarding the EPCI Contractor

29.

Based on a review of lessons reports from previous projects, some proposals have been made on how to apply PRINCE2 to a project. Which role should be accountable for approving these proposals?

a)

Project board

b)

Project manager

c)

Project assurance

d)

Business layer

30.

What is a characteristic of a project that distinguishes it from business as usual?

a)

Projects continue after business a usual resumes

b)

Projects include ongoing management of operations

c)

Every project will be different to previous projects

d)

Project work is generally less risky than business as usual work

31.

Which term is defined as the means by which an organization

transitions from its current state to the target state?

a)

Change management

b)

Change control

c)

Progress management

d)

Risk management

32.

The Investment proposal for threshold > USD 30 M for OPL/OPLL is proposed and approved in Tahap Seleksi respectively by?

a)

Pimpinan Tertinggi Zona dan Direktur/Direktur Utama yang merupakan Pimpinan Tertinggi Entitas Anak Perusahaan

b)

Pimpinan Tertinggi Zona dan Direktur D&P dan Direktur Utama Subholding Upstream

c)

Direktur/Direktur Utama yang merupakan Pimpinan Tertinggi Entitas Anak Perusahaan dan Direktur D&P dan Direktur Utama Subholding Upstream

d)

Direktur/Direktur Utama yang merupakan Pimpinan Tertinggi Entitas Anak Perusahaan dan Direktur D&P Subholding Upstream

33.

In PUDW, Pre-FID mechanism can be used for

a)

FEED & Early Work

b)

Pre-Project & Early Work

c)

Land Acquisition

d)

Land Acquisition & LLI

34.

In "Kebijakan Umum" Pedoman PUDW, there are '6 Pillars (6P) and 6 Enablers (6E). Which one is the CORRECT 6 Enables (6E):

a)

HSE. Organization Capability; Legal, Compliance and Land Matter; Project Cost and Financing Strategy; Project Economics and Commercial Strategy; Project Risk Management .

b)

HSSE; Organization Capability; Legal, Compliance, Land Matter and Formalities; Project Cost; Project Economics; Project Risk Management

c)

HSSE; Organization Capability; Legal, Compliance and Formalities; Project Cost and Strategy; Project Economics Strategy; Project Risk Management .

d)

HSSE; Organization Capability; Legal, Compliance, Land Matter and Formalities; Project Cost and Financing Strategy; Project Economics and Commercial Strategy; Project Risk Management .

35.

The project board needs to confirm that there is enough information to initiate the project. What should the project board review?

a)

Business case

b)

Benefits management approach

c)

Project brief

d)

Project plan

36.

You are currently executing some activities in the Monitor and Control Project Work process. Which of the following may be part of these activities?

a)

Providing forecasts to update current cost

b)

Ensuring that the project stays aligned with the business needs

c)

Determining whether the corrective actions are effective

d)

All the above

37.

Stages or Steps in PUDW consist of?

a)

Inisiasi, Seleksi, Kajian Lanjut, Eksekusi

b)

Inisiasi, Seleksi, Kajian Lanjut, Eksekusi, Operasi

c)

Inisiasi, Seleksi, Definisi, Eksekusi

d)

Inisiasi, Seleksi, Definisi, Eksekusi, Operasi

38.

You are taking over a project in your organization because of its schedule delay and you are requested to control this schedule. The first step you took was collecting information.

If the planned value was $132 K, which of the following will be your SPI?

a)

0.9

b)

1.1

c)

1.05

d)

1

39.

Which is a purpose of the ‘plans’ practice?

a)

To provide the standards against which the project products can be

quality controlled

b)

To enable an event that requires project management consideration to

be controlled

c)

To enable control of opportunities and threats, that could impact on

delivery of the business objectives

d)

To provide the basis of control against which a project’s progress can be monitored

40.

You are managing a project and you found a chance to reduce the time and cost of the project. What do you call this chance?

a)

Threat

b)

Opportunity

c)

Issue

d)

Assumption

41.

After executing the Validate Scope process, which of the following describes the best way to deal with the resulted work performance information?

a)

The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and added to the lessons learned register

b)

The information about the deliverables, which have been accepted and which have not been accepted and the reasons why are documented and communicated to the stakeholders

c)

The information about the deliverables that have been accepted is documented and communicated to the stakeholders

d)

The information about the deliverables that have not been accepted and the reasons why are documented and communicated to the stakeholders

42.

The amount of time that a schedule activity can be delayed without delaying the early start date of any successor or violating a schedule constraint is called

a)

The lead time

b)

The lag time

c)

The total float

d)

The free float

43.

You are managing a project for the first time in your organization. You are executing the earned value analysis from time to time to review the project performance.

Today when executing the same analysis, you got a planned value of 450, actual cost of 480, and the CPI was 0.95. What is the status of your project work?

a)

More project work was completed than was planned

b)

Less project work was completed than was planned

c)

Project work was completed as was planned

d)

None of the above

44.

What are the PMBOK and PRINCE2 stands for?

a)

Project Management Book of Knowledge & Project in Closed Environment

b)

Project Management Body of Knowledge & Projects in Controlled Environments

c)

Project Management Body of Knowledge & Projects in Centralized Environments

d)

Project Management Book of Knowledge & Projects in Controlled Environments

45.

In Pertamina Upstream Project, the successful project shall achieved OTOBOSOR. What is OTOBOSOR stands for?

a)

On Time, On Budget, On Scope, On Return

b)

On Target, On Budget, On Scope, On Return/On Regulation

c)

On Time, On Budget, On Scope/On Specification/On Safety, On Return/On Regulation

d)

On Target, On Budget, On Scope/On Specification/On Safety, On Return/On Regulation

46.

What is the percentage of technical maturity and cost estimation accuracy for Kajian Lanjut accoding to PUDW?

a)

70-90% dan ± 10%

b)

70-90% dan ± < 10%

c)

75-90% dan ± 10%

d)

75-90% dan ± < 10%

47.

Which TWO are objectives of the 'controlling a

stage' process?

1. To focus attention on achieving work within the

agreed tolerances

2. To create follow on action recommendations for

all open issues and risks

3. To understand how the quality required will be

achieved

4. To ensure that the stage’s products meet agreed

quality expectations

a)

1 and 2

b)

2 and 3

c)

3 and 4

d)

1 and 4

48.

According to PMBOK, the following are the key benefits of the Close Project or Phase process, except:

a)

The project or phase information is archived

b)

Organizational team resources are released to pursue new endeavors

c)

Having visibility into the future project status with cost and schedule forecasts

d)

The planned work is completed

49.

When does the ‘directing a project’ process

start?

a)

When the project manager submits the project

brief for approval

b)

When the request to authorize a project is

received

c)

After the project has been authorized by business

layer

d)

After the project mandate has been received

50.

What is the main different based on process approach between PRINCE2 and PMBOK?

a)

PMBOK does not include process in pre-project while the PRRINCE2 does

b)

PMBOK has initating process group while the PRINCE2 has initiating process

c)

PMBOK has no detail aspect of knowledge area while the PRINCE2 has

d)

PMBOK has closed procurement process while PRINCE2 has not