wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Week 6 & 7 CA 2025

Total questions: 44

Worksheet time: 24mins

Name
Class
Date
1.

What are variations?

a)

Change to scope

b)

Change to quality

c)

Change to cost

d)

All of these

2.

Choose all of the following that can cause a variation

a)

Change of design

b)

Error in documentation

c)

Inconsistencies in contract documents

d)

None of these

3.

Who may affect a variation to a contract

a)

Superintendent

b)

Contractor

c)

Subcontractor

d)

All of these

4.

What is a contractor required to do when a Superintendent directs a variation?

a)

Provide a price and impacts on time and other aspects of the project

b)

Walk off the job

c)

Wait 14 days to respond to the request

d)

Complete works and include costs in following payment claim

5.

Which of those below are not included in deduction variations 

a)

reasonable profit

b)

Additional overheads

c)

Time extensions

d)

None of these

6.

Under what circumstances might a contractors request a variation for convenience.

a)

Speed up the works

b)

Simplify construction methodology

c)

Safety

d)

All of these

7.

What is a contractor entitled to for a variation for convenience

a)

Time

b)

Money

c)

Bonus

d)

None of these

8.

What is an issue caused by removing the variation clause form a contract.

a)

You can force the contractor to do more work at a discount

b)

You may not be able to direct a variation

c)

Variations will be priced at double

d)

All of these

9.

If a contractor claims that works are impossible to undertake what might be the result in contract

a)

Frustration

b)

Retention

c)

Arbitration

d)

Reconciliation

10.

What is the time for a contractor to submit costs for variations under the MW21 contract?

a)

24hrs

b)

10 weeks

c)

5 days

d)

10 days

11.

If the principal accepts a variation proposal submitted by the contractor how long do they have to respond

a)

48hrs

b)

3 weeks

c)

10 days

d)

1 day

12.

If the principal refuses the variation proposal, when should they respond

a)

36hrs

b)

1 month

c)

2 days

d)

They are not required to respond

e)

None of these

13.

Which of these are not an contractual entitlements to the contractor for a variation

a)

Direct costs

b)

Margin

c)

Time extension

d)

Quality adjustment

14.

What are the implications if a contract does not make provision for pricing variations

a)

A handshake agreement is made

b)

Construction contract act makes provisions

c)

Code of practice is consulted

d)

None of these

15.

How much is a contractor entitled to for voluntarily providing higher quality product

a)

5%

b)

10%

c)

2.5%

d)

0%

16.

How much is a contractor entitled to for work not required by the contract.

a)

5%

b)

10%

c)

2.5%

d)

0%

17.

What can a contractor claim for work not directly stated by the contract but implied by the nature of the works

a)

Extras

b)

Nothing

c)

Congratulations

d)

20% of contract value

18.

What are examples of a delay under AS4000

a)

Client fails to provide site access on date specificied in contract

b)

Principal conducts too many site visits

c)

Failure of client to respond to contractors notice within the prescribed number of days to provide direction

d)

None of these

19.

When should a contractor notify the Principal of a potential delay?

a)

48hrs

b)

5 days

c)

10 days

d)

Promptly

20.

When should a written claim for EOT be provided to the principal for a qualifying circumstance

a)

5 days

b)

10 days

c)

28 days

d)

Not applicable

21.

What can be an issue with concurrent delays.

a)

Contention over EOT and the impact on critical pathway

b)

It doubles the extension time

c)

Can cause site closure

d)

None of these

22.

What is a common practice for contractors when facing delays

a)

Attempt to claim more time than reasonable

b)

Speed up their schedules to mitigate delays

c)

Avoidance of submitting EOT's

d)

Slowing down work to give workers some down time

23.

When assessing the impact of delays and the effect on the completion date which construction program should be used?

a)

The one submitted at tender

b)

Post tender award program

c)

The clients ambitious program

d)

Latest approved program

24.

What could be reasonably expected of contractors when facing delays that may impact project completion date

a)

Engage additional resources

b)

Work additional hours

c)

Tighten construction program

d)

All of these

25.

What are two of the common payment options for construction

a)

End of contract

b)

Beginning of contract

c)

Progress

d)

Mid contract

26.

Where is the relevance of the construction contract act 2004 found

a)

NSW

b)

South Australia

c)

Victoria

d)

WA

e)

All of these

27.

When does the construction contract act 2004 apply

a)

To all new contracts

b)

To all new construction contracts

c)

Construction contracts prior to 2022

d)

Post COVID construction contracts

28.

What act replaces the construction contract act 2004

a)

Security of payment act 2021 (WA)

b)

Security of payment act 2009 (TAS)

c)

Security of payment act 1999 (NSW)

d)

All of these

29.

What is the importance of defining construction work in the construction contracts acts

a)

So the average consumer will understand contract requirements

b)

To inform the legal profession of construction terms

c)

So that both parties to a contract understand the project scope

d)

None of these

30.

What goods are covered by the construction contract acts

a)

Materials used in the works

b)

Fittings in the construction project

c)

Plant for carrying out construction related works

d)

All of these

31.

What services are not covered by the construction contract acts

a)

Professional services directly related to construction work

b)

Construction Feasibility services

c)

Legal services

d)

Services related to provision of labour

32.

Which two legal provisions were prohibited in the 2004 construction contract acts to protect payees in a construction contract

a)

Pay if paid/when paid

b)

Payment after 50 days

c)

Payment after progress claim

d)

None of these

33.

What amount of payment is a contractor entitled to if they have not completed all the work in their payment claim?

a)

50%

b)

70%

c)

Maximum 90%

d)

Reasonable amount for the work completed

34.

Who is entitled to the unfixed/unpaid goods supplied by the contractor in the case of client insolvency under the 2004 WA act

a)

Client

b)

Principal

c)

Project manager

d)

None of these

35.

What two actions can a builder take under a simple contract if the owner does not make a payment post work performed

a)

Charge interest

b)

Suspend works

c)

Demolish works

d)

Remove all valuable fixtures form the works

36.

Who can authorise payments under contracts

a)

Project mangers as authorised persons

b)

Superintendent

c)

Contract administrator

d)

All these three above

37.

Which of the following is required in a payment claim

a)

Value of work completed

b)

Profit margins of subcontractors

c)

Home address of claimant

d)

All of these

38.

Under AS4000 how long does the superintendent have to issue a payment certificate

a)

7 days

b)

14 days

c)

21 days

d)

30 days

39.

What monies can be held back from payment to the Contractor after claim is processed

a)

Retention

b)

Monies due the principal

c)

Beer tax

d)

social engagement levy

40.

How long within payment certificate issue is payment required

a)

7 days

b)

14 days

c)

21 days

d)

30 days

41.

What common strategy is used by contractors to improve cash flow

a)

Borrow money off client

b)

Provide a large deposit in lieu of retention

c)

Overstate works completed on the payment claim

d)

All of these

42.

What is an important exclusion from a payment claims that can stop a payment made to contractors

a)

Declaration of payment of subcontractors and workers

b)

Declaration of good will

c)

Declaration of 4th amendment rights

d)

None of these

43.

When is a contractor entitled to a bonus according to AS4000 clauses

a)

End of year summer break

b)

School holidays

c)

When specificied in contract terms

d)

When the project comes under budget

44.

What interest is paid on non-payment monies due

a)

5%

b)

10%

c)

15%

d)

As per relevant contract item