Project Management Quiz

Total questions: 47

Worksheet time: 26mins

Name
Class
Date
1.

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments. What should the project manager do?

a)

Discuss the lack of dedication with the team member and their functional manager

b)

Allow the most senior team members to decide the time that works for the team

c)

Remove the team member from the project team to be fair to the other members

d)

Reassess the team's hours collaboratively so that the team is not impeded by the issue

2.

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change in project scope. How should the project manager respond to this requirement?

a)

Perform an analysis to assess the Impact on the project.

b)

Proceed with the existing company governance policy.

c)

Escalate the issue to upper management and let them decide.

d)

Directly comply with the financial regulations.

3.

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs. How should the project manager ensure the work continues smoothly?

a)

Postpone the required work on the project until school holidays begin

b)

Continue the work as planned and inform the school when the project team arrives on-site

c)

Advise the school to close for the duration of the project work

d)

Liaise with the school to include nonworking project hours during school start and finish times

4.

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member is crying about the pressures of an upcoming deadline. What should the project manager do?

a)

Review the organization's human resources (HR) policy.

b)

Empathize with the team member and discuss next steps.

c)

Ask the team member to send their concerns in writing.

d)

Schedule a meeting with the team member for the next work day.

5.

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months. In order to help the team, what should the project leader do?

a)

Recommend that the team reviews the length of the iteration with the stakeholders.

b)

Recommend that the product owner reviews the backlog refinement processes.

c)

Recommend limiting the work in progress to improve the team’s focus.

d)

Recommend a review of the team members' individual performances.

6.

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to analyze team performance? (Choose two.)

a)

Burndown chart

b)

Product backlog burnup chart

c)

Cumulative flow diagram of completed features

d)

Work breakdown structure (WBS)

e)

Project schedule

7.

A project manager is working with the team to deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members, causing negative consequences for delivery. How should the project manager avoid this situation in the future?

a)

Agree with the project team on a suitable collaboration and make sure information is shared at all times.

b)

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.

c)

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.

d)

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.

8.

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty. Which life cycle should the project manager use for this project?

a)

A predictive execution strategy

b)

An iterative execution strategy

c)

An agile execution strategy

d)

A hybrid execution strategy

9.

A project manager is managing a project that has a new sponsor who is cutting the budget. As a servant leader, how should the project manager handle the budget cuts with the team?

a)

Notify the project sponsor that the budget reduction will require a schedule slip and scope reduction.

b)

Collaborate with the team to assess the impact of the change on the project and recommend an updated project plan.

c)

Inform each team member that they must release a portion of their budget but must remain on schedule with no change to the scope.

d)

Meet with the schedule coordinator and financial analyst to tell them which budget lines to reduce and where to release slack.

10.

A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks. What should the project manager do?

a)

Create a new standard performance measure based on project requirements

b)

Develop different approaches based on team members' motivation and ability

c)

Develop a standard approach to provide feedback to all team members

d)

Provide intensive oversight to the team members who performed poorly

11.

An agile team has released the second version of its product, but the feedback is that the software has many bugs that compromise the user experience. What should the project manager do?

a)

Hire an external consultancy firm to focus on testing and quality control to avoid the issue in the future

b)

Propose an internal program that offers incentives for the team members who find and fix bugs

c)

Closely evaluate the skill set of the team, looking for technical gaps that need to be filled in order to improve quality

d)

Facilitate the next retrospective meeting, focusing the team on analyzing root causes and proposing solutions

12.

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder. Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two.)

a)

Provide training to the team on emotional intelligence and status reporting techniques

b)

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders

c)

Share weekly status reports with detailed information about the project and team performance

d)

Submit performance reports and task assignments to keep the stakeholder informed

e)

Schedule regular meetings with the key stakeholder to provide updates and receive feedback

13.

A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved. Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three.)

a)

Prioritize stakeholders based on the project phase and need

b)

Perform a stakeholder assessment to align with the project objectives

c)

Classify and rank stakeholders based on their positions in the organization

d)

Include all stakeholders in the stakeholder engagement plan and provide the same level of communication

e)

Develop a stakeholder impact/influence matrix to determine the level of engagement

14.

In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project manager do next?

a)

Produce a value-added product for the customer in each phase of the project.

b)

Produce a value-added product for the customer as continuously as possible.

c)

Produce a value-added product for the customer in the beginning of the project.

d)

Produce a value-added product along with the supporting documentation.

15.

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are afraid of the same issue in this project. Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two.)

a)

Organize a team-bonding activity and invite an external manager to speak to the team.

b)

Set a clear vision for the project and ensure it is visible to all stakeholders.

c)

Focus on the resource management plan and track project progress.

d)

Encourage the team to do a brainstorming session and provide a mitigation plan.

e)

Keep the team engaged and focused on the project's direction.

16.

Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised. What should the project manager do to ensure success of the project?

a)

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

b)

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.

c)

Escalate the issue to the project sponsor and seek support to keep the original requirements.

17.

One phase of a project took much longer than initially anticipated. The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

a)

Request additional contingency from the sponsor

b)

Add more float to the overall project schedule

c)

Expedite the next phase to reduce slippage

d)

Organize a root cause analysis (RCA) workshop

18.

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country's unique requirements. The expected revenue for the product is the same for each country. Which release strategy should the project manager recommend?

a)

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

b)

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

c)

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

d)

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

19.

A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly to ensure that the stakeholder is up to date on the project. However, the project manager has recently resigned and will not be meeting with the new project manager prior to departure. How should the project manager ensure that the new project manager continues to update this particular stakeholder?

a)

Ensure that the project team has been provided guidance on the specific needs of this stakeholder

b)

Update the stakeholder engagement plan with the specific communication needs for the stakeholder

c)

Ensure that the project documents contain specific instructions regarding the stakeholder

d)

Update the communications management plan with specific information on stakeholder engagement

20.

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company. What should the project manager do next?

a)

Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance

b)

Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor

c)

Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track

d)

Review the contract with the vendor to go over the financial penalty that is applicable to this situation

21.

A project manager for a software development company faces a number of financial risks in their project. The project manager needs to frequently check the strength and efficiency of the risk management process. What should the project manager use to accomplish this?

a)

Brainstorming session

b)

Stakeholder register

c)

Assumption log

d)

Audit meeting

22.

Atypically high-performing team member has started to demonstrate a performance drop as well as some aggressive behaviors toward other team members in meetings. The project manager has worked with this individual for many months on this project and has not seen this type of behavior before. What should the project manager do?

a)

Discuss the individual's behavior with the other team members to determine if they have noticed and know what is going on

b)

Attend more team meetings to observe the team more closely to determine the root cause

c)

Discuss the project manager's observations with the individual to determine why they are behaving this way

d)

Discuss their performance with the team member's functional manager as well as human resources (HR) and discuss next steps

23.

In a newly formed project team, one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

a)

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

b)

Set up team-building activities with the project team members to reduce tension

c)

Ask the team member to enter this potential schedule delay in the risk register

d)

Actively listen to the team member and identify ways to support their needs in completing the tasks

24.

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

a)

Report the delay with rectifying actions to the project management office (PMO).

b)

Rebaseline the project schedule to absorb the delay.

c)

Notify the project steering committee about the cause of the delay.

d)

Report the delay with rectifying actions to the change control board (CCB) for review.

25.

An experienced project manager is managing a multi-million dollar agile project. The project manager communicates the ground rules to the team, but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules. What should the project manager do first to ensure team adherence to the ground rules?

a)

Ask the functional manager to replace team members not following the ground rules.

b)

Schedule a meeting with the project team to reinforce the ground rules.

c)

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action.

d)

Contact human resources to request a written warning letter be sent to team members not following the ground rules.

26.

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already. What should the project manager do to support the team?

a)

Provide feedback to the team using project performance evaluations.

b)

Include buffer time in the schedule to absorb future delays.

c)

Escalate the impact on the schedule to the project sponsor.

d)

Create a change request to extend the project's duration and costs.

27.

A customer has provided excellent feedback on the project. However, a key project resource is leaving the company. Which measure should mitigate the impact of this key resource's departure?

a)

Establish a proactive knowledge-sharing plan

b)

Offer a new contract to the resource who is leaving

c)

Develop a contingency budget to replace the key resource

d)

Update the risk register and inform the customer

28.

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins to identify, evaluate, and categorize the stakeholder relationships to the program. What is the purpose of this process?

a)

Identify all stakeholders who can positively affect the project

b)

Identify all stakeholders who can negatively affect the project.

c)

Incorporate the needs of all stakeholders into the communications management plan

d)

Incorporate only primary stakeholders into the communications management plan

29.

A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects. What should the project manager do to ensure the project scope is completely defined?

a)

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

b)

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

c)

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

d)

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

30.

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds. What should the project manager do?

a)

Continue executing the project as planned and add more resources if they are required.

b)

Evaluate the project risk and add external experts to address the potential risks.

c)

Review the lessons learned on similar projects so that they do not fall back into the same pattern.

d)

Inform the project sponsor about the risk and try to convince them to withdraw from the project.

31.

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another. What should the project manager do?

a)

Ask the experienced members to lead the junior members to facilitate skill transfer

b)

Organize networking sessions to allow the team members to get to know one another

c)

Encourage team members to focus on delivering results with their specialized skills

d)

Ask the team to self-organize and escalate any issues to the project manager

32.

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government. Which action should the project manager take to address the sponsor's request?

a)

Work with the organization's legal department to identify local regulations to ensure project compliance

b)

Work with the organization's project management office (PMO) to build a project team of residents located in the city

c)

Work with the organization's real estate department and reach out to the local government to identify the best location for the store

d)

Work with the local government to build the profiles of employees that will be working in the store

33.

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience. How should the project manager ensure that the client is effectively represented in the daily meetings?

a)

Recommend agile training programs that best suit the client project manager’s schedule.

b)

Propose a session for essential agile knowledge transfer for the client team to align with the daily meeting goals.

c)

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

d)

Provide the client project manager with agile best practice documents and web resources.

34.

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents. What should the project manager do to ensure a successful project execution?

a)

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

b)

Send emails with information about the project deliverables on the first day of the project.

c)

Connect with every location and check their preferred methods of communication.

d)

Invite all resources to the project manager's location to form a cohesive team until all deliverables are completed.

35.

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

a)

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

b)

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

c)

Document the request and escalate to upper management to consider a modification of the project charter.

d)

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

36.

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate. What should the project manager do next?

a)

Hire a company in country B to perform a quality check before shipment

b)

Evaluate the procurement contract to determine the agreed-upon specifications

c)

Escalate the issue to the purchasing department for review

d)

Add an additional task to cut the received part according to the specifications

37.

A project manager has team members around the world in many different time zones. Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered. What should the project manager have done to avoid this?

a)

Ensured that the project would be the highest priority for all team members

b)

Planned and scheduled tasks and work packages to overcome geographical and time zone challenges

c)

Learned more about how each team member prefers to communicate before assigning project work

d)

Used communication tools, such as video conferencing, so different offices could communicate

38.

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

a)

Initiate a change request to obtain additional funds from the management reserve

b)

Meet with the project team and customer to brainstorm about potential solutions

c)

Schedule a high-priority meeting with the project stakeholders to discuss the issue

d)

Collaborate with the relevant stakeholders on implementing the risk response plan

39.

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones. When will the project manager be able to provide the requested information?

a)

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

b)

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

c)

In the initiation process, as it happens concurrently with the project contract and project charter creation

d)

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

40.

After conducting a performance assessment, the project manager identified that some gaps still exist. What should the project manager ensure?

a)

Awards are given to all team members for playing a role in the project and undertaking the assessment.

b)

Performance improvement programs are organized for all team members who were assessed.

c)

All team members rotate their job schedules immediately to make them versatile.

d)

Assessment results are kept private and not shared among team members.

41.

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have recently been requested. What should the project manager do next?

a)

Discuss the changes with the client and jointly make the decision on how to proceed.

b)

Reject the changes and stay the original course as initially agreed with the client.

c)

Review the risk register to see if mitigations have already been outlined for this scenario.

d)

Review the changes and make the decision based on the project team's recommendations.

42.

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days. What does the project manager need to do now?

a)

Inform the product owner

b)

Inform the project sponsor

c)

Inform the relevant stakeholders

d)

Inform the project team only

43.

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team. What should the project manager do?

a)

Ask the team member to bring up the concern in the next daily meeting

b)

Send an email explaining the issue to all team members

c)

Reassign the task to another team member

d)

Move the task to the next sprint

44.

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing. What should the project manager do to create a positive environment?

a)

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals

b)

Copy the ground rules established by another project and provide them to the teams

c)

Establish the team ground rules and share them with the team for strict adherence

d)

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to

45.

An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for them. How does the project lead ensure adherence to agile practices?

a)

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend

b)

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach

c)

Have a discussion with the team on the approach and come to a decision on when the daily standups should be

d)

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team

46.

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?

a)

Reject the suggestion and ask the team member to focus on executing the plan

b)

Ask the team member to submit a formal change request

c)

Accept the suggestion as it has no impact on the project

d)

Ask another team member to validate the impacts of the suggestion

47.

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team. What should the project manager do?