DAY 23 ITI WORKSHEET (Formwork and Timbering)(10/10) Quiz

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

The primary purpose of formwork in construction is to:

a)

Strengthen steel reinforcement

b)

Support fresh concrete until it hardens

c)

Form a base for plastering

d)

Hold masonry walls

2.

Which of the following materials is commonly used for modern formwork?

a)

Straw mat

b)

Timber only

c)

Plywood and steel

d)

Mud blocks

3.

A good formwork should be:

a)

Weak but watertight

b)

Easily removable and water-tight

c)

Permanent and heavy

d)

Only made of wood

4.

The vertical formwork for columns can be removed after approximately:

a)

16-24 hours

b)

24 – 48 hours

c)

5 days

d)

10 days

5.

Beam soffits (with props left under) can be removed after:

a)

3 days

b)

7 days

c)

10 days

d)

21 days

6.

Timbering of trenches is used to:

a)

Increase excavation depth

b)

Prevent side walls from collapsing

c)

Improve drainage

d)

Support foundation steel

7.

The main plank in contact with the trench wall is called:

a)

Strut

b)

Sheeting

c)

Bracing

d)

Ranger

8.

Box sheeting is suitable for:

a)

Hard rock excavation

b)

Firm ground up to 2 m

c)

Loose soil up to 4 m depth

d)

Deep excavation up to 15 m

9.

Stay bracing is adopted for:

a)

Loose soil up to 10 m

b)

Firm soil up to 2 m

c)

Very soft soil

d)

Sandy soil over 5 m

10.

The _______ method is similar to box sheeting except that the work is carried out in stages and at each stage, and offset is provided.

a)

Sheet piling

b)

stay bracing

c)

Box sheeting

d)

vertical sheeting

11.

Sheet piling is adopted for:

a)

Small pits only

b)

Large deep excavations

c)

Rock foundations

d)

Pavement work

12.

Centering for arches is removed only after:

a)

1 day

b)

Concrete gains strength

c)

Arch form set is dry

d)

Laggings fixed

13.

Plywood formwork can be reused about:

a)

3 – 5 times

b)

7 – 10 times

c)

15 – 20 times

d)

25 – 30 times

14.

Match the components of formwork with their functions:

a)

A–4, B–2, C–3, D–1

b)

A–1, B–2, C–3, D–4

c)

A–2, B–1, C–3, D–4

d)

A–3, B–2, C–1, D–4

15.

Write down the stripping time for different types of formwork, as per IS 456

(a)