Intro to Preliminaries, Prime Cost Sum & Prov Sum

Total questions: 16

Worksheet time: 11mins

Name
Class
Date
1.

Items that cover the general requirements of the project — not physical construction works, but conditions, obligations, and facilities necessary to execute the project.

a)

Preliminaries

b)

Prime Cost Sum

c)

Provisional Sum

2.

An estimated allowance for work that cannot be precisely defined at tender stage.

a)

Preliminaries

b)

Prime Cost Sum

c)

Provisional Sum

3.

Sum provided for work or services to be executed by a NSC, statutory authority or a public undertaking or for materials or goods to be obtained from a NS.

a)

Preliminaries

b)

Prime Cost Sum

c)

Provisional Sum

4.

Which of the following best describes Preliminaries?

a)

Work that is not yet defined but may be required later

b)

Materials selected by the client after tender

c)

General requirements and obligations for managing the project

d)

Extra work instructed during construction

5.

Provisional Sum is included in the BOQ to cover:

a)

Work that is fully detailed at tender stage

b)

Works or quantities that cannot be determined at tender stage

c)

Supply-only items selected by the client

d)

The contractor’s attendance on site

6.

Which item is most likely found under Preliminaries?

a)

Tile supply at RM40/m²

b)

Rock excavation

c)

Landscaping works

d)

Temporary site office

7.

Preliminaries generally include temporary works, insurances, and project management requirements.

a)

TRUE

b)

FALSE

8.

Match the following

Categorize the following

Hoarding

Water and Electricity

PPE

Fire Fighting Installations

Lift System Installation

Drainage Diversion

Interior Design Works

Rock Excavation

Landscaping

Piling Works

Insurance

Preliminaries
Prime Cost Sum
Provisional Sum
9.

Provisional sum is used in the conditions below:

a)

Construction work that is not completely defined at the time the

tender documents are issued

b)

Cost of a construction work that entirely cannot be foreseen

c)

Cost of construction work involving initial power and water supply

d)

Cost of construction work carried out by a nominated sub-contractor

10.

Which of the following's construction works are categorized as Prime Cost (PC)?

a)

Electrical Installation

b)

Fire Fighting System

c)

Air-conditioning System

d)

Lift and Escalator System

e)

Load Bearing Wall System

11.

Which of the followings are included in Preliminaries cost?

a)

Tower crane

b)

Scaffolding

c)

Temporary road

d)

Portland cement

12.

Sum provided for work or services to be executed by a Nominated Sub Contractor.

The statement above is

a)

Provisional Sum

b)

Prime Cost Sum

c)

Preliminaries Sum

d)

Drain Sump

13.

When there is Nominated Supplier, the Main Contractor may received

a)

Profit and Attendance

b)

Profit Only

c)

Attendance Only

d)

None of the above

14.

When there is Provisional Sum, the Main Contractor may received

a)

Profit and Attendance

b)

Profit Only

c)

Attendance Only

d)

None of the above

15.

Prime Cost sum is the money allocated for

a)

Main Contractor

b)

Nominated Sub Contractor

c)

Sub Conctractor

d)

Consultant

16.

Below are example of items under Preliminaries Sum EXCEPT

a)

hoarding

b)

site office

c)

insurance

d)

site transportation

e)

fire fighting installation