wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

PERT Pretest

Total questions: 10

Worksheet time: 4mins

Name
Class
Date
1.

Graph or bar chart with a bar for each project activity that shows  passage of time which provides visual display of project schedule

a)

PERT/CPM

b)

GANTT CHART

c)

PRIMAVERA

d)

BAR SCHEDULE

2.

Indicates only precedence relationships and does not require any time of effort

a)

Dummy

b)

Slacks

c)

Float

d)

Event

3.

Latest time an activity can be completed without delaying critical path time

a)

Early Start

b)

Early Finish

c)

Late Start

d)

Late Finish

4.

It refers to the amount of extra time that exists for an activity when all activities preceding it start at their Early Start (ES) date.

a)

Float

b)

Slacks

c)

Total Float

d)

Free Float

5.

The longest path (time) in a network diagram and it determines the project duration.

a)

Critical Activities

b)

Critical Path

c)

Activity on Node

d)

Activity on Arrow

6.

A perimeter fence required 11,200 units of 6” CHB to complete. If a mason has an average daily installation productivity of 320 units, what is its estimated duration for a crew of 5 mason/day

a)

6 days

b)

7 days

c)

3 days

d)

4 days

7.

Draw the Network diagram given the ff:

A, B and C are starting activities and may begin at the same time.

 D and E follows A and E is an ending activity

 G follows and depends on C.

 F is dependent on the completion of B and D.

 G and F must be done before H, an ending activity, can start.

What is the Critical Path?

A=5, B=4, C=5, D=3, E=8, F=2, G=6 and H = 5 (all in days)

a)

A-E

b)

A-D-F-H

c)

B-F=H

d)

C-G-H

8.

From the Network Diagram Shown,

What is the project duration?

a)

16 days

b)

15 days

c)

14 days

d)

13 days

9.

From the same Network Diagram

What is the duration of the shortest path?

a)

13 days

b)

14 days

c)

15 days

d)

16 days

10.

From the same Network Diagram

What is the late start of Activity B but still

project can still be completed on its target duration?

a)

6 days

b)

5 days

c)

9 days

d)

7 days