WorksheetsPERT Pretest
Total questions: 10
Worksheet time: 4mins
Graph or bar chart with a bar for each project activity that shows passage of time which provides visual display of project schedule
PERT/CPM
GANTT CHART
PRIMAVERA
BAR SCHEDULE
Indicates only precedence relationships and does not require any time of effort
Dummy
Slacks
Float
Event
Latest time an activity can be completed without delaying critical path time
Early Start
Early Finish
Late Start
Late Finish
It refers to the amount of extra time that exists for an activity when all activities preceding it start at their Early Start (ES) date.
Float
Slacks
Total Float
Free Float
The longest path (time) in a network diagram and it determines the project duration.
Critical Activities
Critical Path
Activity on Node
Activity on Arrow
A perimeter fence required 11,200 units of 6” CHB to complete. If a mason has an average daily installation productivity of 320 units, what is its estimated duration for a crew of 5 mason/day
6 days
7 days
3 days
4 days
Draw the Network diagram given the ff:
A, B and C are starting activities and may begin at the same time.
D and E follows A and E is an ending activity
G follows and depends on C.
F is dependent on the completion of B and D.
G and F must be done before H, an ending activity, can start.
What is the Critical Path?
A=5, B=4, C=5, D=3, E=8, F=2, G=6 and H = 5 (all in days)
A-E
A-D-F-H
B-F=H
C-G-H
From the Network Diagram Shown,
What is the project duration?
16 days
15 days
14 days
13 days
From the same Network Diagram
What is the duration of the shortest path?
13 days
14 days
15 days
16 days
From the same Network Diagram
What is the late start of Activity B but still
project can still be completed on its target duration?
6 days
5 days
9 days
7 days