wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Day 87-Dec 23-worksheet-Btech-CM-Contracts & Tenders

Total questions: 15

Worksheet time: 10mins

Name
Class
Date
1.

In network crashing, the cost slope of an activity represents:

a)

Increase in indirect cost per unit time

b)

Increase in total project cost per unit reduction in duration

c)

Increase in direct cost per unit reduction in activity duration

d)

Ratio of normal cost to crash cost

2.

Which activity should be crashed first to reduce project duration economically?

a)

Activity with maximum float

b)

Activity on non-critical path

c)

Critical activity with minimum cost slope

d)

Activity with maximum duration

3.

Resource allocation in CPM primarily aims at:

a)

Reducing project duration

b)

Minimizing total project cost

c)

Eliminating dummy activities

d)

Adjusting start times without changing project duration

4.

Resource leveling differs from resource allocation because leveling:

a)

Reduces total cost

b)

Maintains project duration constant

c)

Shortens critical path

d)

Requires crashing

5.

Which of the following is NOT a type of tender?

a)

Open tender

b)

Limited tender

c)

Negotiated tender

d)

Indexed tender

6.

Earnest Money Deposit (EMD) in tendering is mainly intended to:

a)

Cover construction cost

b)

Ensure contractor’s financial capacity

c)

Prevent frivolous bidding

d)

Pay labour wages

7.

In a lump sum contract, the contractor’s risk is generally:

a)

Nil

b)

Shared equally

c)

Higher

d)

Lower than item rate contract

8.

: Crashing an activity always reduces the total project cost.

a)

True

b)

False

9.

Resource smoothing allows variation of project completion time.

a)

True

b)

False

10.

The shortest possible duration of an activity is called (a)   time.

11.

Cost slope is calculated as (Crash Cost − Normal Cost) / (a)   .

12.

Resource allocation does not alter the duration of the project.

a)

True

b)

False

13.

The process of distributing limited resources over time is called (a)   .

14.

Tender invited from all eligible contractors is known as (a)   tender.

15.

The agreement document between owner and contractor is called (a)   .