5. Terminations, Conductors and Stringing Methodology

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

Which project used pre-stretching method for conductor stringing?

a)

EPC/IR

b)

Metro

c)

High-speed

d)

DFCC

2.

For a full tension length, 2 numbers of BWA locations are required.

a)

True

b)

False

3.

What is the time duration of High-speed Contact wire pre-stretching?

a)

60minutes

b)

2 Hour

c)

30 minutes

d)

5 minutes

4.

Normally, catenary wire is made up of

a)

Thin copper wire

b)

Cadmium copper

c)

Hard drawn copper

d)

Flexible copper

5.

What is the maximum length of a contact wire in a single drum?

a)

3000 m

b)

1500 m

c)

1000 m

d)

2000 m

6.

Tension applied to OHE in EPC Project is

a)

1100 kgf

b)

1000 kgf

c)

2400 kgf

d)

2000 kgf

7.

A dynamometer is required for checking the tension in conductors.

a)

False

b)

True

8.

Conductor weight is not required for billing purposes.

a)

True

b)

False

9.

DFCC catenary wire cross-sectional area is 129 sq.mm.

a)

False

b)

True

10.

BEC conductors are normally provided for earthing purpose in EPC / IR OHE.

a)

True

b)

False

11.

Cross section of Messenger wire in CMRL Metro is

a)

150 sq.mm

b)

129 sq.mm

c)

65 sq.mm

d)

107 sq.mm

12.

Abbreviations of FTA is

a)

Final Task Anchor

b)

Finished Terminal Anchor

c)

Fixed Termination Anchor

d)

Fixed Tension Anticreep

13.

In the High-Speed OHE project, what is the cross-sectional area of the contact wires?

a)

120 sq.mm

b)

150 sq.mm

c)

170 sq.mm

d)

200 sq.mm

14.

Which component joins two conductor rails together in ROCS?

a)

Anchor Bar

b)

Interlocking Joint

c)

Swivel Head

d)

Drop Tube

15.

In the Third Rail System, the conductor rail is made of

a)

Pure copper

b)

Aluminium with stainless steel

c)

Mild steel

d)

Aluminium and zinc