5. Terminations, Conductors and Stringing Methodology

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

Which project used pre-stretching method for conductor stringing?

a)

EPC/IR

b)

Metro

c)

High-speed

d)

DFCC

2.

How many BWA terminations will be there in Full tension length?

a)

0

b)

1

c)

2

d)

3

3.

What is the time duration of High-speed Contact wire pre-stretching?

a)

60minutes

b)

50minutes

c)

30minutes

d)

40minutes

4.

Normally, Contact wire is made up of

a)

Thin copper wire

b)

Cadmium copper

c)

Hard drawn grooved copper

d)

Flexible copper

5.

Full form of AWT

a)

Automatic Wiring Train

b)

Alumino Wiring Technology

c)

Automatic Welding Technology

d)

Anchor Wire Termination

6.

Tension applied to OHE in High-speed project is

a)

1200 kgf

b)

5500 kgf

c)

2400 kgf

d)

2000 kgf

7.

A dynamometer is required for checking the tension in conductors.

a)

False

b)

True

8.

Conductor weight is not required for billing purposes.

a)

True

b)

False

9.

DFCC Contact wire cross-sectional area is 129 sq.mm.

a)

False

b)

True

10.

BEC are normally provided for earthing purpose

a)

True

b)

False

11.

Cross section of Messenger wire in CMRL Metro is

a)

150 sq.mm

b)

129 sq.mm

c)

65 sq.mm

d)

107 sq.mm

12.

Abbreviations of FTA is

a)

Final Task Anchor

b)

Finished Terminal Anchor

c)

Fixed Termination Anchor

d)

Fixed Tension Anticreep

13.

Messenger wire is also known as Catenary wire

a)

False

b)

True

14.

Which component joins two conductor rails together in ROCS?

a)

Anchor Bar

b)

Interlocking Joint

c)

Swivel Head

d)

Drop Tube

15.

In the Third Rail System, the conductor rail is made of

a)

Pure copper

b)

Aluminium with stainless steel

c)

Mild steel

d)

Aluminium and zinc