wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Civil war-Day 41-LSGD-Rate analysis,Simpson’s & trapezoidal rule

Total questions: 10

Worksheet time: 9mins

Name
Class
Date
1.
What is the minimum number of cross-sections required to find the quantity of earth work using trapezoidal formula?
a)
1
b)
2
c)
3
d)
4
2.
If B is the width of formation, D is the height of formation, and side slope is S:1, the area of cross section for a highway embankment (no transverse slope) is:
a)
B + D + SD
b)
BD + SD²
c)
BD − SD²
d)
1/2(BD + SD²)
3.
Rate analysis is required before preparing —
a)
Abstract of cost
b)
Soil report
c)
DPR
d)
Map
4.
Lift is measured in —
a)
Horizontal plane
b)
Vertical direction
c)
Arc length
d)
Slope
5.
Which of the following is NOT overhead expense?
a)
Watch & ward
b)
Office staff
c)
Site rent
d)
Brickwork quantity
6.
Profit to contractor is added —
a)
Before labour
b)
After all expenses
c)
Before material
d)
In BOQ preparation
7.
If material + labour = ₹20,000, add 1.5% water charges and 10% contractor’s profit (profit added last). Final cost is —
a)
₹22,000
b)
₹22,150
c)
₹22,330
d)
₹23,150
8.

Wages paid to mason are part of —

a)
Overhead
b)
Labour cost
c)
Contractor profit
d)
Tools cost
9.

The Simpson’s rule for determination of areas is used when the number of offsets are:

a)

2

b)

even

c)

3

d)

Odd

10.

In Simpson’s rule the line joining the top of the ordinates is assumed

a)

Parabolic

b)

Straight

c)

Circular

d)

Elliptical