Worksheetspost-contract
Total questions: 10
Worksheet time: 5mins
Under PWD 203A Clause 39.2, the Contractor must notify the S.O. in writing when they believe the works have reached Practical Completion.
True
False
Under PWD 203A, the S.O. has 30 days to inspect the works after receiving notice of Practical Completion.
True
False
Under PAM 2018 Clause 15.1, minor defects are allowed as long as the Contractor provides a written undertaking to rectify them within a reasonable time.
True
False
A Certificate of Non-Completion (CNC) under PAM 2018 must be issued before the Employer can impose Liquidated Damages.
False
True
Under PWD 203A Clause 40.3, the Government must prove the actual loss suffered in order to charge Liquidated and Ascertained Damages.
False
True
Under PWD 203A Clause 42, when the Government takes partial occupation of a part of the works, the Defects Liability Period for that part begins immediately.
True
False
Under PAM 2018 Clause 16.1, partial possession by the Employer automatically reduces the Liquidated Damages proportionally.
True
False
Under PWD 203A, sectional completion allows each section to have separate Practical Completion and its own defects liability period.
False
True
Under PWD 203A Clause 48.2, if the Contractor fails to remedy defects, the S.O. may arrange for others to fix them and recover the cost from the Contractor.
True
False
Under PAM 2018 Clause 15.6, the Architect must issue the Certificate of Making Good Defects within 14 days if all defects have been rectified.
True
False