Solid Wall assessment questionaire

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

A specification states that blue engineering bricks are to be used for a brick on edge feature. If there are only red engineering bricks available, what action should be taken?

a)

Stop work and ask the foreman.

b)

Carry on working using the material you have available.

c)

Build it in the Red bricks and come back when the Blue ones are delivered.

d)

Stop work and go home.

2.

How can a bricklayer’s line be supported on long lengths of a wall?

a)

Single Plate

b)

Tingle Spoon

c)

Tingle Plate

d)

Fingle Cup

3.

How many bricks are required to construct a brick on edge fora 1.5m long wall?

a)

5 Bricks

b)

22 Bricks

c)

21 Bricks

d)

20 Bricks

4.

Which type of brick should be used for brick on edge?

a)

Any Brick

b)

A less porous / Dense Engineering Brick

c)

A less Porous / Common Facing Brick

d)

A More porous / Common Facing Brick

5.

Which regulations cover the tools and equipment used on a construction site?

a)

PUWER (Provision & Use of Work Equipment Regulation 1998)

b)

COSHH (Control of substances Hazardous to health)

c)

HASAWA (Health & Safety at Work Act 1974)

d)

HSE (Health & Safety Excecutive)

6.

What is the purpose of an over sailing course?

a)

To look pretty.

b)

To divert rain away from the face of the wall and act as a drip.

c)

To direct rain into the wall and act as a water collection.

d)

To divert rain into the cavity and soak the insulation.

7.

Which brickwork bond is made up of alternate courses of headers and stretchers?

a)

English Bond

b)

Flemish Bond

c)

Stretcher Bond

d)

Stack Bond

8.

How many bricks are there per meter squared on a 1 & 1/2 brick solid wall?

a)

60 Bricks

b)

100 Bricks

c)

120 Bricks

d)

180 Bricks

9.

Why would a weep hole be used in a retaining wall?

a)

To release moisture or rain water from the soil that's behind the wall

b)

To keep the moisture from the soil behind the wall

c)

To enable the plants to root better

d)

To release the water from the mains water supply

10.

How should completed work be protected from heavy rainfall?

a)

Use a dust Sheet to cover the new wall.

b)

Use Hessian to cover the new wall.

c)

Use a Tarpaulin to cover the new wall.

d)

Leave it exposed as masonry doesn't need protecting from rain.