EOT & CLAIMS FOR LOSS AND EXPENSES

Total questions: 10

Worksheet time: 20mins

Name
Class
Date
1.

What is the main purpose of an Extension of Time (EOT) in a construction contract?

a)

To increase the contractor’s profit

b)

To reduce project quality

c)

To protect the contractor from Liquidated Damages when delays are not their fault

d)

To speed up construction work

2.

Why is it important for a contractor to keep records when submitting a Loss and Expense claim under PAM 2018?

a)

For site decoration

b)

For marketing purposes

c)

To impress the client

d)

As evidence to support and justify the claim

3.

Under PWD 203A, the contractor must give written notice within 30 days to claim for EOT.

a)

TRUE

b)

FALSE

4.

Which of the following is a valid cause for Loss and Expense under PAM 2018 Clause 24.3?

a)

Contractor’s negligence

b)

Poor site management

c)

Late arrival of workers

d)

Late Architect’s Instructions (AI)

5.

Under PWD 203A Clause 43.0, within how many days must the contractor give notice for EOT?

a)

14 days

b)

21 days

c)

30 days

d)

60 days

6.

In PAM 2018, who assesses and verifies the Loss & Expense claim amount?

a)

Superintending Officer only

b)

Employer

c)

Architect and Quantity Surveyor

d)

Main Contractor

7.

Loss and Expense only covers the cost of materials used on site.

a)

TRUE

b)

FALSE

8.

In PAM 2018, a contractor does not need to keep any records when making a claim for loss and expense.

a)

FALSE

b)

TRUE

9.

5. Which of the following BEST defines a “Loss and Expense” claim?

a)

Cost of repairing defective works

b)

Contractor’s normal operating cost

c)

Late payment by the contractor

d)

Extra costs incurred due to delays or disruptions beyond the contractor’s control

10.

The Superintending Officer is responsible for assessing claims under PAM 2018.

a)

FALSE

b)

TRUE