WorksheetsProject Scheduling
Total questions: 12
Worksheet time: 6mins
Project Scheduling mainly helps in:
Reducing project scope
Allocating resources and setting deadlines
Removing project risks
Closing the project
Crashing a project means:
Increasing project duration
Reducing costs
Adding resources to speed up project tasks
Stopping the project
A predecessor activity is an activity that:
Can start anytime
Comes before another activity
Comes after another activity
Has no dependency
A milestone in project Scheduling represents:
A delay
A key event or checkpoint
A resource need
A task with float
Which scheduling technique identifies the longest path in a project?
PERT
Gantt chart
CPM
Resource leveling
Full form of PERT is ?
Project Evaluation and Review Technique
Program Evaluation and Review Technique
Program Estimation and Review Technique
Process Estimation and Resource Technology
Which technique used three time estimates: optimistic, pessimistic,and most likely?
CPM
PERT
WBS
Crashing
In a network diagram,the longest path from start to end is called:
Slack path
Float path
Critical path
Free float
In a network,ES+Duration=?
LS
EF
Float
Crash time
Which of the following is not a technique of Project scheduling?
CPM
ASD
PERT
EVM
Gantt chart is also known as :
Line chart
Bar chart
Network chart
Pie chart
Which scheduling method handles uncertainty?
CPM
PERT
Gantt
Histogram