Excavation Hazards

Total questions: 15

Worksheet time: 1hrs 15mins

Name
Class
Date
1.

The role of Competent Person in excavation safety is: (select all that apply)

a)

Having required training and knowledge of soil classification

b)

Having required training and knowledge on use of protective systems

c)

Being able to identify hazards

d)

Having the authority to eliminate hazards

e)

Having the ability to terminate employees that haven't been properly trained on excavation safety

2.

The greatest hazard to excavations is the natural ability for a trench to try to ________ itself. One cubic foot of soil weighs between ________. It will entrap, ________, or otherwise injure you.

a)

implode, 15 - 25 pounds, suffocate

b)

deflate, 35 - 75 pounds, pulverize

c)

fill, 90 - 130 pounds, bury

d)

stay open on, 300 - 450 pounds, engulf

e)

move, 150 - 200 pounds, conceal

3.

Never enter an unprotected trench that is ________ feet or more in depth. The competent person must first choose and implement a ________ system. Even excavations less than the minimum depth required for trench protection may need to be deemed ________ by the competent person. ________ can happen without warning.

a)

five (5), protective, safe, Cave-ins

b)

four (4), preventative, unsafe, Anything

c)

six (6), provocative, worthy, Everything

d)

ten (10), warning, available, Things

e)

eight (8), weapons, catastrophic, Logic

4.

What is The Theory of Shoring: (select all that apply)

a)

Shoring prevents cave-ins

b)

Shoring, if designed and installed correctly, prevents movement of the excavated wall.

c)

You must stay within the protection of the shoring even when entering, working in, and exiting the trench.

d)

Shoring is safer than not working in a trench.

e)

It is best to use malleable metals, so that the earth impregnates its burden upon the shoring.

5.

Make-shift, improperly designed shoring does little other than provide a false sense of security!

a)

True

b)

False

6.

Type B soil or rock, shall have a maximum allowable slope, for excavations less than 20-feet, of ________?

a)

Vertical, 90 Degree Slope

b)

3/4 : 1 (53 Degree Slope)

c)

1 : 1 (45 Degree Slope)

d)

1 1/2 : 1 (34 Degree Slope)

e)

2 : 1 (26.5 Degree Slope)

7.

Stable rock, shall have a maximum allowable slope, for excavations less than 20-feet, of ________?

a)

Vertical, 90 Degree Slope

b)

3/4 : 1 (53 Degree Slope)

c)

1 : 1 (45 Degree Slope)

d)

1 1/2 : 1 (34 Degree Slope)

e)

2 : 1 (26.5 Degree Slope)

8.

Structures become ________ when earth next to them is removed. For your safety, these must be ________. A competent person must ensure precautions are ________.

a)

saturated, drained, known

b)

old, looked at, overlooked

c)

stable, disturbed, handled correctly

d)

solid, admired, preliminary

e)

unstable, supported, implemented

9.

As required, you should give notice to your State’s one call system, to locate any underground utilities before breaking ground. Once utility providers located known utilities, you should hand dig to find the exact location. Who do you call to notify your intentions to dig?

a)

888

b)

411

c)

811

d)

911

e)

988

10.

A soil pile should be a minimum of ________ feet away from the side of a trench.

a)

one

b)

two

c)

three

d)

four

e)

five

11.

When working below grade, ________ hazards exist. ________ must be worn in ________ due to this hazard.

a)

electrical, Silicone gloves, mud

b)

overhead, Hard hats, excavations

c)

dusty, Eye protection, comfort

d)

water, Waders, confidence

e)

fall, Fall Arrest gear, trench boxes

12.

Responsibilities of Employers at trench excavations must: (select all that apply)

a)

Make sure a ladder is within 25’ of your work area when deeper than four feet.

b)

Keep excavated dirt, rocks and other materials back two feet from the excavation’s edge.

c)

Test and monitor the air within the trench in areas suspect to atmospheric hazards.

d)

Must adequately train employees on the hazards of trenching excavations.

e)

Take prompt corrective action when a hazard is identified.

13.

Responsibilities of Employees at trench excavations must: (select all that apply)

a)

Work defensively

b)

Follow your company’s excavation and trenching safety rules.

c)

Correct the hazards you are able to correct safely.

d)

Work offensively, with wreckless abandon.

e)

Report to your supervisor the hazards you are unable to correct.

14.

At what depth must a ladder, ramp, steps, or runway be present for quick worker exit?

a)

Four (4) feet

b)

Five (5) feet

c)

Ten (10) feet

d)

When available to use

e)

It is never required

15.

Unless made in entirely stable rock, at what depth is a protective system required for a trench: (select all that apply)

a)

Any depth if the competent person says so.

b)

Five (5) feet deep and greater.

c)

A protective system is never required in trenches.

d)

When you have a canoe to paddle downstream the trench.

e)

When type M soils are present.