Control Valve – What is the main purpose of this experiment? (Select all that apply)

a)

To study heat transfer in fluids

b)

To understand I/P and control valve operation

c)

To compare signal trends for Air-to-Open (ATO) and Air-to-Close (ATC) control valves

d)

To test pump discharge performance

2.

Control valve - The I/P converter receives a current signal of ___ mA and converts it into a pneumatic output pressure of ___ psig.

a)

4–20 mA and 3–15 psig

b)

0–20 mA and 0–10 psig

c)

10–30 mA and 5–25 psig

d)

4–12 mA and 3–9 psig

3.

True or False for control valve - The Instrument Air Supply (IAS) for the I/P converter should be set to 1.4 bar during the experiment.

a)

True

b)

False

4.

Control valve - Explain the purpose of performing a five-point calibration on the I/P converter.

a)

To verify the linear relationship between input current and output pressure and identify any zero drift or span error

b)

To increase the instrument air supply pressure to its maximum rating

c)

To determine the valve body material and actuator type

d)

To select the appropriate piping schedule for the control loop

5.

Control valve - Which terminals are used for adjusting the zero and span of the I/P converter?

a)

'—○—' and '<– –>'

b)

'Zero+' and 'Span-'

c)

'mA+' and 'mA-'

d)

'SUP' and 'OUT'

6.

Control valve - In an Air-to-Open (ATO) control valve, the valve is ___ when the input current is 4 mA and ___ when the current is 20 mA.

a)

fully open, fully closed

b)

fully closed, fully open

c)

partially open, partially closed

d)

fully open, fully open

7.

Control valve - In an Air-to-Close (ATC) control valve, the valve is ___ when the input current is 4 mA and ___ when the current is 20 mA.

a)

fully open, fully closed

b)

fully closed, fully open

c)

partially closed, partially open

d)

fully closed, fully closed

8.

Control valve - If the input current is 8 mA, calculate the theoretical output pressure for a 3–15 psig range.

a)

3 psig

b)

6 psig

c)

9 psig

d)

12 psig

9.

Control valve - During calibration, if the measured output pressure is higher than the theoretical value, what adjustment should be made?

a)

Reduce the span using the '<– –>' terminal on the I/P converter

b)

Increase the zero using the '—○—' terminal on the I/P converter

c)

Increase the instrument air supply pressure

d)

Reverse the I/P converter input polarity

10.

Level Measurement (DLT 912) – Which of the following level measurement methods are studied in this experiment? (Select all that apply)

a)

DP-diaphragm

b)

DP-bubble tube

c)

Ultrasonic sensor

d)

Millimetres scale

11.

Level Measurement (DLT 912) - The main objective of this experiment is to study the fundamental principles of _____ and compare different level measurement methods.

a)

level/hydrostatic principles

b)

pressure/thermodynamic cycles

c)

electromagnetic induction

d)

optical interference

12.

Level Measurement (DLT 912) - True or False: LT1 measures level using a bubble tube arrangement, and LT2 uses diaphragm seals.

a)

True

b)

False

13.

Level Measurement (DLT 912) - What should be the instrument air supply (IAS) pressure during the experiment setup?

a)

20 psig

b)

25 psig

c)

32 psig

d)

40 psig

14.

Level Measurement (DLT 912) - Why must tank T3 be filled with water up to the marked level before beginning the experiment?

a)

To ensure proper circulation and accurate level measurement across the system

b)

To reduce the pump power consumption

c)

To prevent cavitation in LT1

d)

To calibrate the stirrer speed

15.

Level Measurement (DLT 912) - During the experiment, the pump P1 and the stirrer should be switched _____ before observing the level rise in tank T1.

a)

ON

b)

OFF

c)

Standby

d)

Auto

16.

Level Measurement (DLT 912) - In Experiment 1A, the level in Tank T1 is adjusted to what value before taking readings?

a)

450 mm

b)

500 mm

c)

550 mm

d)

600 mm

17.

Level Measurement (DLT 912) - If the measured pressure difference (DP) at LT1 is 148.6 mmH2O, what is the corresponding level h in mm? Use the calibration formula h = (Measured DP + 557).

a)

696.0 mm

b)

705.6 mm

c)

712.4 mm

d)

734.0 mm

18.

Level Measurement (DLT 912) - According to the hydrostatic principle, the level in a tank can be calculated using which relationship?

a)

h=DPρgh=\frac{DP}{\rho g}

b)

h=ρg/DPh=\rho g/DP

c)

h=DP×ρgh=DP\times\rho g

d)

h=DP2ρh=\frac{DP^2}{\rho}

19.

Water flow measurement - Which of the following flow meters are used in this experiment for volumetric flow measurement? Select all that apply.

a)

Turbine flow meter

b)

Orifice / Differential Pressure flow meter

c)

Variable Area flow meter

d)

Electromagnetic flow meter

20.

Water flow measurement - Fill in the blanks in the main flow path: T32 → P32 → ____ → FT31 (FE31) → ____ → T31 → P31 → APPLY CONDITION 2 → ____ → T32. Choose the correct set of components for the three blanks.

a)

FI31, LCV31, FT32

b)

FI31, LIC31, FT31

c)

FE31, LCV31, FT31

d)

FI31, LCV31, FT31

21.

Water flow measurement - In the WLF 922 setup, the LCV31 acts as the final control element that regulates the flow rate.

a)

True

b)

False

22.

Water flow measurement - What is the function of LIC31 in this experiment?

a)

To indicate and control the water level in T31

b)

To measure the temperature of the water

c)

To control the pump operation

d)

To measure the pressure difference across the orifice plate

23.

Water flow measurement - The instrument air supply (IAS) should be set to ____ psig and must not be disturbed during the experiment.

a)

20 psig

b)

32 psig

c)

40 psig

d)

60 psig

24.

Water flow measurement - In the start-up checklist, why must the tank T32 be filled up to the level of its overflow drain pipe before starting the experiment?

a)

To ensure a continuous water supply and maintain constant head for accurate flow measurement

b)

To prevent air entering FI31 only

c)

To protect P32 from overheating

d)

To minimize turbulence in FT31

25.

Water flow measurement - Which of the following conditions correspond to Condition 2 during the start-up procedure?

a)

P32 suction valve closed, discharge valve closed

b)

P31 suction valve open, both discharge valves open

c)

P32 suction valve open, bypass valve open

d)

T31 gate and globe valves fully shut

26.

Water flow measurement - Using the formula Fv=0.03hF_v = 0.03\sqrt{h} , calculate the flow rate (in m^3/hr) when h=1600h=1600 mmH2O.

a)

0.8 m^3/hr

b)

1.2 m^3/hr

c)

1.6 m^3/hr

d)

3.0 m^3/hr

27.

Water flow measurement - According to the theoretical verification section, what relationship should hold true if the level in the tank is kept constant?

a)

FI31 = FT31 = FT32

b)

FI31 < FT31

c)

FI31 > FT32

d)

FT31 = 0