WorksheetsDay 85-Dec 22-worksheet-Btech-Project management & networking
Total questions: 15
Worksheet time: 10mins
The most important phase of a project, where objectives and resources are clearly defined, is:
Scheduling
Controlling
Execution
Planning
The oldest project scheduling technique developed by Henry Gantt is:
CPM
PERT
Bar chart
Network diagram
In a bar chart, the length of the bar represents:
Cost of activity
Sequence of activities
Duration of activity
Type of resource
In Activity-on-Arrow (AOA) network, activities are represented by:
Nodes
Circles
Arrows
Squares
A dummy activity in a network diagram is represented by:
Thick arrow
Solid arrow
Double line
Dashed arrow
An event consumes time and resources in a project network.
True
False
Parallel activities can be performed simultaneously and are independent of each other.
True
False
Assertion–Reason Assertion (A): Dummy activities do not consume time or resources. Reason (R): Dummy activities are used only to show dependency between activities. Choose the correct option.
Both A and R are true and R explains A
Both A and R are true but R does not explain A
A is true but R is false
A is false but R is true
Controlling involves comparison between what ———progress and actual progress?
(a)
A milestone chart is a modification of ——-chart
(a)
Logical links between activities are shown clearly in what kind of bar charts?
Linked
Simple
Floating
Three-dimensional
Work Breakdown Structure follows topdown approach
True
False
An event represents an ———time
(a)
An event that marks the starting of an activity is called ——-event
(a)
An artificial activity that establishes dependency is called ——-
(a)