Worksheets16/01/2026-overseer grade 3-estimation
Total questions: 10
Worksheet time: 5mins
Name
Class
Date
1.
In professional engineering terminology, a 'Project' is defined as a comprehensive scheme that includes:
a)
Only the architectural floor plans and front elevation.
b)
The physical building structure and the land it stands on.
c)
Designs, Structural Calculations, and Detailed Estimates.
d)
The material list and the labor contract only.
2.
In the Tendering Process, the Bill of Quantities (BOQ) is characterized as an Abstract of Estimate where:
a)
The Quantity and Unit columns are left blank.
b)
The Item Description and Serial Number are left blank.
c)
The Rate and Amount columns are left blank.
d)
All columns are filled by the Department before tendering.
3.
Which type of plan is a small-scale map used for large-scale works to show general topography, such as roads and hospitals?
a)
Site Plan
b)
Index Plan
c)
Layout Plan
d)
Detailed Section
4.
A Layout Plan is specifically prepared to show which of the following details?
a)
The orientation of the building relative to the North.
b)
The precise plot boundaries and neighboring infrastructure.
c)
Site services such as drainage sewer lines and utility networks.
d)
Detailed dimensions of the interior rooms.
5.
Which document is prepared by the Department to show item-wise quantities for tender purposes ensuring uniformity among bidders?
a)
Detailed Estimate
b)
Standard Data Book
c)
Bill of Quantities (BOQ)
d)
Schedule of Rates (SOR)
6.
Which of the Three Pillars of Estimation is considered a legal document used to settle disputes in court regarding work quality?
a)
Detailed Drawings
b)
General Specifications
c)
Detailed Specifications
d)
Schedule of Rates (SOR)
7.
To ensure accurate quantity calculations and avoid errors Detailed Drawings must be drawn to scale and include:
a)
Only the Plan and Elevation.
b)
Plans Elevations and Sections with mandatory dimensions.
c)
General specifications and a Site Map.
d)
The Bill of Quantities and Rate Analysis.
8.
In the standard workflow which form is used specifically to calculate the Quantity of work using dimensions like Length Breadth and Depth?
a)
Abstract of Estimate Form
b)
Bill of Quantities (BOQ)
c)
Details of Measurement Form
d)
Standard Data Book
9.
Assertion A: The Bill of Quantities BOQ allows parity in bidding.
Reason R: All contractors quote for the same items and quantities.
a)
Both A and R are true and R explains A.
b)
Both A and R are true but R does not explain A.
c)
A is true but R is false.
d)
A is false but R is true.
10.
Assertion A: The final rate for an item is always exactly the same as the base price in SOR.
Reason R: Conveyance charges vary with site distance.
a)
Both A and R are true and R explains A.
b)
Both A and R are true but R does not explain A.
c)
A is true but R is false.
d)
A is false but R is true.
100 %