Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Estimation and Costing CA1

Total questions: 30

Worksheet time: 15mins

Name
Class
Date
1.

What is the purpose of an estimate in a construction project?

a)

To determine the exact profit of the project

b)

To calculate the approximate cost of the project

c)

To finalize the contractor’s payment

d)

To supervise construction activities

2.

Which estimate is prepared to accommodate changes in the project scope?

a)

Supplementary Estimate

b)

Sub Estimate

c)

Revised Estimate

d)

Complete Estimate

3.

What type of estimate is used to calculate costs for maintenance of structures?

a)

Repair Estimate

b)

Annual Maintenance Estimate

c)

Sub Estimate

d)

Supplementary Estimate

4.

Which estimate is prepared when additional work is required during progress of work?

a)

Main Estimate

b)

Supplementary Estimate

c)

Revised Estimate

d)

Detailed Estimate

5.

Which method of approximate estimation uses the total built-up area of a building?

a)

Plinth Area Method

b)

Cubical Content Method

c)

Service Unit Method

d)

Typical Bay Method

6.

The Cubical Content Method considers:

a)

Area of the plinth only

b)

Volume of the structure

c)

Length of walls

d)

Service units in the building

7.

In which method of approximate estimation are repetitive structural units like bays used?

a)

Typical Bay Method

b)

Service Unit Method

c)

Plinth Area Method

d)

Cubical Content Method

8.

The Service Unit Method is best suited for which type of project?

a)

Residential buildings

b)

Industrial buildings

c)

Hospitals or schools

d)

Highways

9.

Which estimate provides item-wise expenditure?

a)

Preliminary estimate

b)

Detailed estimate

c)

Plinth area estimate

d)

Rough cost estimate

10.

The Cubical Content Method is more accurate than the Plinth Area Method because:

a)

It considers the total volume of the structure

b)

It excludes the cost of roofing

c)

It uses service units

d)

It ignores height variation

11.

What is the standard unit of measurement for brickwork?

a)

Cubic meter ( m3m^3 )

b)

Square meter ( m2m^2 )

c)

Kilogram (kg)

d)

Number of bricks

12.

For plastering work, deductions are made for openings only if their size exceeds:

a)

0.1 m2m^2

b)

0.5 m2m^2

c)

1.0 m2m^2

d)

No deduction is made

13.

The degree of accuracy in measurement for masonry work is:

a)

Nearest 1 mm

b)

Nearest 1 cm

c)

Nearest 1 m²

d)

Nearest 0.01 m³

14.

Which thumb rule is used to estimate the number of bricks required for 1 m³ of brick masonry?

a)

350 bricks

b)

500 bricks

c)

1000 bricks

d)

1200 bricks

15.

The outturn of work refers to:

a)

Cost of materials per day

b)

Quantity of work done by a worker in a day

c)

Estimated profit

d)

Total material required

16.

Aggregates are primarily required for:

a)

Brick masonry

b)

Concrete work

c)

Plastering

d)

Painting

17.

The Schedule of Rates (SOR) is used for:

a)

Calculating quantities

b)

Estimating cost of works and materials

c)

Preparing lead statements

d)

Lump sum provisions

18.

The Standard Data Book is mainly used to:

a)

Track project profits

b)

Provide standard labor and material data

c)

Prepare drawings

d)

Fix tender value

19.

Lump sum provision in an estimate is made for:

a)

Detailed items

b)

Unspecified or miscellaneous works

c)

Cement and sand

d)

Transport only

20.

Observed data refers to:

a)

Historical cost records

b)

Data collected at site during execution

c)

Schedule of rates

d)

Lump sum data

21.

Specification is essential in construction because it:

a)

Defines quality, materials, and workmanship requirements

b)

Adds decorative details without cost impact

c)

Replaces drawings in all cases

d)

Eliminates need for supervision

22.

The main types of specifications are

a)

Written and verbal

b)

Standard and non-standard

c)

General and detailed

d)

Itemized and lump sum

23.

The purpose of general specifications is to

a)

Give detailed quantities

b)

Provide brief overview of materials and workmanship

c)

Fix project cost

d)

List all construction items

24.

Detailed specifications are necessary for

a)

Feasibility studies

b)

Quality overview

c)

Preparing tenders and execution

d)

Cost comparison

25.

Specifications for cement include

a)

Chemical composition only

b)

Type, grade, and storage conditions

c)

Mixing ratio only

d)

Application method

26.

The primary requirement for sand used in construction is:

a)

Cheap availability

b)

Freedom from organic impurities and silt

c)

Grain color

d)

Transportation cost

27.

Most important property of reinforcement steel is:

a)

Weight per meter

b)

Flexibility

c)

Tensile strength and grade

d)

Length

28.

Water used for construction should conform to:

a)

Neutral pH only

b)

Potable water standards

c)

Hard water standards

d)

Rainwater standards

29.

A construction report is:

a)

List of costs

b)

Written document describing progress or findings

c)

Contract agreement

d)

Work schedule

30.

Which is NOT a key consideration while writing a report?

a)

Clarity and conciseness

b)

Accurate data and evidence

c)

Logical organization with headings

d)

Inclusion of personal bias and unsupported opinions