1.

FLASHCARD QUESTION

Front

When laying out a building, taking two equal measurements of the diagonal corners means that the four corners are: not plumb, not square, square, triangles

Back

square

2.

FLASHCARD QUESTION

Front

To be certain that accurate readings are taken, the bubble in the leveling vial of a farm level should be checked:

Back

before and after each reading

3.

FLASHCARD QUESTION

Front

When one fails to hold the leveling rod up straight, the measurement will be:

Back

inaccurate

4.

FLASHCARD QUESTION

Front

If Steve is using a builder’s level to lay out a building, the degree reading when the telescope is turned to mark a corner should be: 15°, 30°, 45°, 90°

Back

90°

5.

FLASHCARD QUESTION

Front

When setting up a tripod and a builder’s level, the leveling screws should be adjusted until the:

Back

bubble is centered

6.

FLASHCARD QUESTION

Front

If Abby needs to lay out a building using the 3-4-5 method, what measurement is used with 24' and 30' to make a square corner?

Back

18'

7.

FLASHCARD QUESTION

Front

The person using a laser beam level for surveying knows that the receiver is on the same grade when a signal is seen or heard from the: lower sensor, middle sensor, rod person, top sensor

Back

middle sensor

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?