Project Management Concepts Flashcard
Flashcard
•
Business
•
University
•
Practice Problem
•
Hard
Wayground Content
FREE Resource
Student preview

20 questions
Show all answers
1.
FLASHCARD QUESTION
Front
What is a Work Breakdown Structure (WBS)?
Back
A hierarchical decomposition of the total scope of work into manageable sections to ensure project completion.
2.
FLASHCARD QUESTION
Front
What is the purpose of a Requirement Matrix?
Back
To track requirements, their sources, priority, and status throughout the project lifecycle.
3.
FLASHCARD QUESTION
Front
What are some methods of Requirement Gathering?
Back
Interviews, surveys, focus groups, prototyping, observation, and document analysis.
4.
FLASHCARD QUESTION
Front
What are the approaches to developing a Work Breakdown Structure (WBS)?
Back
Top-down, bottom-up, and mind mapping.
5.
FLASHCARD QUESTION
Front
What are the steps in a Project Schedule Management Plan?
Back
Define activities, sequence them, estimate resources and durations, develop the schedule, and monitor it.
6.
FLASHCARD QUESTION
Front
What is the definition of Critical Path?
Back
The longest path of dependent tasks determining the shortest project duration.
7.
FLASHCARD QUESTION
Front
What is the formula for Communication Channels Calculation?
Back
C = \frac{N(N-1)}{2} where N is the number of team members.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
Already have an account?