
Lines/Levels & Gradients
Presentation
•
Professional Development
•
Professional Development
•
Hard
Ice one
Used 115+ times
FREE Resource
25 Slides • 8 Questions
1
Lines/Levels & Gradients
Note: You need 100% in this lesson on the self checks.
2
Establishing line, level, and gradient
At the start of a job, the datum needs to be established
The datum point can be the invert level of a pipe.
The invert level of a pipe is the lowest wetted area at the bottom of
the inside of that pipe
For example, ceramic pipes have walls which are approximately 20 mm thick.
3
Invert level
Invert level shown at bottom of inside of pipe
4
Establishing gradient
A pipe installed with a gradient is not level — it has a slope
or fall.
The term gradient is sometimes referred to as grade.
Gradients are usually specified in NZBC and AS/NZS3500
5
Line and level and gradient
Line is the shortest distance between two points
Level is described as a horizontal line that is parallel to the surface
Gradient is a slope below horizontal. It is usually expressed as a ratio or as a percentage
6
7
Sometimes you need to know how many millimeters per meter your drain has to fall from the gradient you have been given
Use the following method
1:60 means for every 60m you travel the fall is 1m
The calculation is simple > 1000 (mm in 1 m) divided by 60 (grade) = 16.6mm for every meter
8
Setting up a dumpy level
9
Taking readings & levels
10
Check out the folllowing triangle
You will need two values to calculate the third.
See the next slide
11
Calculate the fall for a drain 8m long with a 1:40 grade
F = L divided by G
Therefore
8 / 40 = 0.200
THE FALL = 0.200 m or 200 mm
12
13
14
In the examples we have done, the gradient could have been expressed as a percentage 1.65% at the gradient 1:60 = 1.65%.
Note that the conversions between gradients and percentages are rounded, that is, they are rounded to the nearest 0.05%.
For this reason calculations will vary slightly depending on whether a ratio or percentage is used. The following table shows conversions between percentages, ratios and mm/m.
15
16
17
Drain grades are calculated by engineers to produce
Self cleansing velocities
The correct Fixture Discharge Unit loading to grade
Free ventilation throughout the drainage system
18
Take a look at this video, although American it still has relevance to NZ and gives you an understanding of how FDUs were calculated
19
This is a table from G13 that shows the different gradients for different loadings
Note: You can increase the pipe size and shallow the grade, this may be helpful if you are struggling for fall between to datum points.
20
Some more key points:
When it is necessary to install a drain below a specifed grade, an Alternative Solution might include the provision of flushing tanks and more inspection points.
Drains should also be installed so that under steady flow conditions, the pipe is not completely filled. This will allow for any surge flow and prevent siphonage of any trap seals.
21
Discussion point:
Consider the following scenario below:
What are the falls and grade required?
What can you do to achieve this?
22
NZBC G13/AS2 Drainage requires the use of verifiable levelling devices such as lasers and dumpy levels where drains are laid at gradients of 1:80 or less.
Because, when drains are laid with a very small slope, their gradients should be checked with more accurate equipment.
23
24
Now try these
25
Multiple Choice
Try 1:80 grade, convert to mm per meter
18mm
180mm
125mm
12.5mm
26
Multiple Choice
Try this one: How many mm per mtr fall should a 1:120 drain have?
120mm
12mm
8.3mm
27
Multiple Choice
How much fall is required for a drain 15 m long with a 1:60 grade?
500mm
900mm
250mm
40mm
28
Multiple Choice
You have a FDU loading of 149, what grade should you lay your drain at using a 100mm pipe
1:40
1:60
1:20
1:120
1:80
29
Multiple Choice
What is 1.45% expressed as a grade
1:14.5
1:69
1:1.4
1:45
30
Multiple Choice
You have been asked to lay a drain at 15%, what ratio grade would it be and how much fall in mm is needed per mtr
1:15 and 15mm
1:100 and 15mm
1:6.6 and 151.5mm
1:66 and 15.1mm
31
Multiple Select
Calculate the overall fall from the invert level at your sewer connection of 3.540m to your drain connection at 2.770m
770mm
7.7mm
6.31
7.70
32
Multiple Choice
Using the previous slides calculation, what grade would the drain be laid at if it was 10m long
1:70
1:10
1:12.9
1: 77
33
Well Done!
Thank you for completing this lesson and your final assessment
Lines/Levels & Gradients
Note: You need 100% in this lesson on the self checks.
Show answer
Auto Play
Slide 1 / 33
SLIDE
Similar Resources on Wayground
26 questions
Quizizz Presentation
Presentation
•
Professional Development
26 questions
Sosialisasi Quizizz
Presentation
•
Professional Development
25 questions
Stairs
Presentation
•
Professional Development
26 questions
PHẦN THI KIẾN THỨC TRẺ 5 TUỔI
Presentation
•
Professional Development
26 questions
REFRESH-- RICE (1)-BIJIRIN
Presentation
•
Professional Development
24 questions
MOORE ENGAGED Presentation
Presentation
•
Professional Development
29 questions
Vocabulario de Navidad
Presentation
•
Professional Development
26 questions
B1A - Review Mid2
Presentation
•
Professional Development
Popular Resources on Wayground
20 questions
STAAR Review Quiz #3
Quiz
•
8th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
6 questions
Marshmallow Farm Quiz
Quiz
•
2nd - 5th Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
20 questions
Inferences
Quiz
•
4th Grade
19 questions
Classifying Quadrilaterals
Quiz
•
3rd Grade
12 questions
What makes Nebraska's government unique?
Quiz
•
4th - 5th Grade