2 Slides • 26 Questions

1

​Unit 306 Self study
Part 5
Work programmes

media

2

​Click on the following link to open the text:

Unit 306 P5 Work programmes.pdf


then use the text to answer the questions that follow.

3

Multiple Choice

What is a work programme?

1

A plan to manage finances

2

A detailed document to record and assess activity

3

A schedule for employee breaks

4

A list of materials needed for a project

4

Multiple Choice

What can poor supervision contribute to in the workplace?

1

Increased productivity

2

Accidents

3

Higher profits

4

Better communication

5

Multiple Choice

What is the role of the main contractor in a work programme?

1

To design the building

2

To oversee the work programme

3

To hire subcontractors

4

To purchase materials

6

Multiple Choice

What is the purpose of using work programmes in private installation work?

1

To increase the cost of the project

2

To ensure customer needs and requirements are met

3

To delay the project timeline

4

To reduce the quality of work

7

Multiple Choice

What is a legal requirement for landlords regarding appliance safety?

1

Ignoring safety checks

2

Conducting yearly boiler servicing

3

Keeping accurate records and planning

4

Reducing maintenance activities

8

Multiple Choice

What should be checked for effective operation in a radiator circuit?

1

The color of the radiator

2

The manufacturer's logo

3

The circuit's effectiveness

4

The radiator's paint quality

9

Multiple Choice

What is recommended by manufacturers for boiler servicing?

1

Monthly servicing

2

Yearly servicing

3

Servicing every five years

4

No servicing required

10

Multiple Choice

What is the purpose of job specifications in large projects?

1

To identify precise details of a job and complement services and site drawings.

2

To provide a general overview of the project.

3

To list the names of all workers involved.

4

To determine the budget for the project.

11

Multiple Choice

What must be done if changes are needed in a job specification?

1

Changes can be made without any permission.

2

Changes must be agreed upon with the management.

3

Changes are not allowed under any circumstances.

4

Changes can be made by the installers themselves.

12

Multiple Choice

Why is it important to check the delivery note when goods arrive on-site?

1

To ensure that all ordered items are present and correct.

2

To verify the identity of the delivery person.

3

To calculate the total cost of the delivery.

4

To determine the delivery time.

13

Multiple Choice

What is the best solution if there are delays due to health and safety issues?

1

To ignore the issues and continue work.

2

To work around the problem safely until it is resolved.

3

To stop all work indefinitely.

4

To speed up other tasks to compensate.

14

Multiple Choice

What does the first fix in plumbing include?

1

Installation of appliances like radiators, boiler, and sinks

2

Painting the external surfaces

3

Installing electrical wiring

4

Landscaping the garden

15

Multiple Choice

What is the purpose of a tender in a construction project?

1

To submit a price or quotation for a job or contract

2

To finalize the construction design

3

To hire subcontractors

4

To purchase construction materials

16

Multiple Choice

What does the second fix in plumbing involve?

1

Plastering and painting internal surfaces

2

Connecting appliances to the first-fix pipework

3

Installing the roof

4

Laying the foundation

17

Multiple Choice

What is a variation order in construction projects?

1

A document that records any agreement made with a client to alter the existing work specified in a building contract.

2

A document that outlines the initial design of a construction project.

3

A report detailing the financial status of a construction project.

4

A contract that specifies the materials to be used in construction.

18

Multiple Choice

Why is it important to produce a variation order as early as possible?

1

To ensure the project is completed under budget.

2

To save money by reducing the time taken to reach an agreement.

3

To increase the number of workers on the project.

4

To avoid using any written communication.

19

Multiple Choice

What must be done if a variation in work is caused by poor installation?

1

The contractor is liable for any subsequent costs.

2

The project is immediately canceled.

3

The client must pay for all additional costs.

4

The original design is discarded.

20

Multiple Choice

What advantage does written communication have in confirming changes to a contract?

1

It provides a permanent record.

2

It speeds up the construction process.

3

It eliminates the need for client approval.

4

It reduces the overall cost of the project.

21

Multiple Choice

What does the chart in Figure 4.12 show?

1

A list of construction materials.

2

A range of causes for variations.

3

A timeline of project completion.

4

A budget breakdown for the project.

22

Multiple Choice

Which of the following is a cause of owner-related variations?

1

Change of plans or scope by owner

2

Contractor's lack of involvement in design

3

Weather conditions

4

Technology change

23

Multiple Choice

What is a consultant-related variation?

1

Inadequate scope of work for contractor

2

Unavailability of equipment

3

Safety considerations

4

Change in economic regulations

24

Multiple Choice

Which of the following is a contractor-related variation?

1

Contractor's financial difficulties

2

Change in government regulations

3

Errors and omissions in design

4

Owner's financial problems

25

Multiple Choice

What is an example of other variations?

1

Weather conditions

2

Contractor's desired profitability

3

Inadequate project objectives

4

Conflicts between contract documents

26

Multiple Choice

What is the purpose of a toolbox talk in the workplace?

1

To discuss financial strategies

2

To plan marketing campaigns

3

To deal with health and safety matters

4

To organize social events

27

Multiple Choice

What can a well-designed work programme help a building service supervisor do?

1

Increase the cost of materials

2

Organize a toolbox talk

3

Delay the project timeline

4

Reduce the number of workers

28

Multiple Choice

What are deficiencies in the context of work performance related to?

1

Increasing the number of workers

2

Problems affecting safety, quality, and cost effectiveness

3

Enhancing the design of the building

4

Improving communication skills