Planning and overseeing

Planning and overseeing

Assessment

Presentation

Construction

Vocational training

Practice Problem

Hard

Created by

Donna Hollett

FREE Resource

38 Slides • 35 Questions

1

media

2

Multiple Choice

What is the main focus of Unit 301?

1

Planning electrical work activities

2

Overseeing electrical work activities

3

Organising work programmes

4

Understanding electrical safety

3

media

4

Multiple Choice

What are the factors that influence the overall cost of a contract in electrical work activities?

1

Cost of materials

2

Expected hours

3

Cost and profit

4

All of the above

5

media

6

Multiple Choice

What considerations should be made before starting work allocations?

1

Availability of skilled workers

2

Type of materials needed

3

Weather conditions

4

All of the above

7

media

8

Multiple Choice

What factors influence the deployment and availability of suitable personnel on a work site?

1

Too many people on site

2

Different skills and abilities

3

Experience of electricians

4

All of the above

9

Multiple Choice

Jaron is very athletic and an excellent baseball player. Jaron's skills are considered his:

1

aptitudes

2

attitudes

3

flaws

4

standards

10

media

11

Multiple Choice

What are the methods to ensure the delivery and availability of equipment, components, and material on site?

1

Deliveries from your company's store

2

Mass deliveries to site

3

Just in time deliveries from a supplier/wholesaler

4

None of the above

12

media

13

Multiple Choice

What factors can influence work completion time at construction sites due to weather conditions?

1

Exposure to elements

2

Availability of materials

3

Worker efficiency

4

Construction design

14

Multiple Choice

The project duration in a network can be determined by the largest value of which variable associated with the critical​ path?

1

Slack Time

2

Earliest Start Time

3

Earliest Finish Time

4

Activity Time

15

Multiple Choice

Which process puts more resources on the critical path?

1. Activity e with preceding activities STart, and duration of 8 days

2. Activity F with preceding activities E and duration of 4 days

3. Activity G with preceding activities E and duration of 10 days

4. Activity H with preceding activities F and G and duration of 2 days

5. Activity I with preceding activities H and duration of 2 days

6. Activity J with preceding activities H and duration of 2 days

7. Activity K with preceding activities H and duration of 3 daus

8. Activity L with preceding activities I, J, and K and duration of 2 days

9. Activity M with preceding activities L and duration of 1 day

1

19 days

2

25 days

3

26 days

4

27 days

16

Multiple Choice

Which of the following best describes critical path analysis?

1

It shows how a project can be completed with maximum labour resources

2

It shows how a project can be completed in the minimum time

3

It takes account for unforeseen events

4

It predicts the success of a project

17

Multiple Choice

Which best describes the critical path slack?

1

the activities on the critical path

2

the delay after the drywall is completed in a house to allow it to dry

3

the earliest a new HVAC system can be ordered from a manufacturer

4

the earliest a new HVAC system can be ordered from a manufacturer without delaying the project

18

media

19

Multiple Choice

What factors should be considered when planning work completion time due to other services?

1

Delays caused by other services

2

Availability of materials

3

Weather conditions

4

Labor costs

20

media

21

Multiple Choice

What must a contractor have recorded on a variation order?

1

The changes requested

2

The original contract

3

The client's payment details

4

The project timeline

22

media

23

Multiple Choice

What is the consequence of a breach of contract?

1

Formation of a new contract

2

Legal remedies

3

Automatic termination

4

No consequence

24

media

25

Multiple Choice

What is the purpose of a Gantt chart in work planning?

1

To allocate resources

2

To track expenses

3

To schedule activities

4

To measure performance

26

media

27

Multiple Choice

According to the bar chart, which task takes the longest to complete?

1

Install cladding

2

Windows & main doors

3

Roof frame

4

Concrete slab

28

Multiple Choice

What does the histogram represent in terms of the mass of each package?

1

Number of packages

2

Average mass

3

Total mass

4

Standard deviation

29

media

30

Multiple Choice

What are the steps involved in installing the floodlighting in a car park?

1

Dig trenches

2

Deliver lampposts

3

Fix lampposts

4

Inspect and test

31

media

32

Multiple Choice

What is the total estimated time required to dig trenches and deliver lampposts?

1

12 hours

2

13 hours

3

14 hours

4

15 hours

33

media

34

Multiple Choice

What is the significance of the start and end dates in a Gantt chart?

1

They indicate the duration of the project

2

They show when the team is on holiday

3

They are used for color coding

4

They determine the complexity of the project

35

media

36

Multiple Choice

What are the stages involved in Critical Path Network planning?

1

Identify the operations and components

2

Determine the duration of each operation

3

Form a network that relates the operations in a logical sequence

4

Calculate the total cost of the project

37

media

38

Multiple Choice

What is the total number of days required to complete the following tasks: Lay Foundations, Build walls, Fit roof, Electric 1st fix, Electric 2nd fix, Plumbing 1st fix, Plumbing 2nd fix, and Inspect and test?

1

10 days

2

12 days

3

14 days

4

8 days

39

media

40

Open Ended

What are the tasks that are part of the critical path network?

41

Fill in the Blanks

Type answer...

42

Multiple Choice

What is the start date for the 'Electrics 1st fix' task?

1

Day 7

2

Day 8

3

Day 9

4

Day 10

43

Multiple Choice

What is the duration of the task 'Lay foundations'?

1

1 day

2

2 days

3

3 days

4

4 days

44

media

45

Multiple Choice

What is the total duration for the tasks in the Critical Path Network?

1

6 days

2

8 days

3

10 days

4

12 days

46

media

47

Open Ended

Explain the significance of the critical path in project management.

48

media

49

Multiple Choice

What is the critical path in project management?

1

The shortest path of events

2

The path that takes the longest time

3

The path with the least resources

4

The path that is easiest to follow

50

media

51

Multiple Choice

What does the bar chart represent in terms of work progress?

1

Tasks completed

2

Tasks pending

3

Tasks in progress

4

Tasks not started

52

media

53

Multiple Choice

What should your management plan include when overseeing work programmes?

1

Working from plans and specifications

2

Ignoring health and safety procedures

3

Not coordinating with other trades

4

Avoiding conflict resolution

54

media

55

media

56

Multiple Choice

What are the sources of technical and functional information provided by manufacturers?

1

Catalogues

2

Data sheets

3

User manuals

4

Installation guides

57

media

58

Multiple Choice

What types of information do companies supply to their employees?

1

Working hours

2

Health and safety requirements

3

Pay rates

4

All of the above

59

media

60

Multiple Choice

What are the hourly rates for JIB graded operatives and apprentices registered before January 7th, 2013?

1

£17.57

2

£18.88

3

£16.82

4

£15.46

61

media

62

media

63

media

64

media

65

media

66

media

67

media

68

media

69

media

70

media

71

media

72

media

73

Poll

How confident do you feel about this topic now?

Very confident
Somewhat confident
Not confident
media

Show answer