Planning and overseeing
Presentation
•
Construction
•
Vocational training
•
Practice Problem
•
Hard
Donna Hollett
FREE Resource
38 Slides • 35 Questions
1
2
Multiple Choice
What is the main focus of Unit 301?
Planning electrical work activities
Overseeing electrical work activities
Organising work programmes
Understanding electrical safety
3
4
Multiple Choice
What are the factors that influence the overall cost of a contract in electrical work activities?
Cost of materials
Expected hours
Cost and profit
All of the above
5
6
Multiple Choice
What considerations should be made before starting work allocations?
Availability of skilled workers
Type of materials needed
Weather conditions
All of the above
7
8
Multiple Choice
What factors influence the deployment and availability of suitable personnel on a work site?
Too many people on site
Different skills and abilities
Experience of electricians
All of the above
9
Multiple Choice
Jaron is very athletic and an excellent baseball player. Jaron's skills are considered his:
aptitudes
attitudes
flaws
standards
10
11
Multiple Choice
What are the methods to ensure the delivery and availability of equipment, components, and material on site?
Deliveries from your company's store
Mass deliveries to site
Just in time deliveries from a supplier/wholesaler
None of the above
12
13
Multiple Choice
What factors can influence work completion time at construction sites due to weather conditions?
Exposure to elements
Availability of materials
Worker efficiency
Construction design
14
Multiple Choice
The project duration in a network can be determined by the largest value of which variable associated with the critical path?
Slack Time
Earliest Start Time
Earliest Finish Time
Activity Time
15
Multiple Choice
Which process puts more resources on the critical path?
1. Activity e with preceding activities STart, and duration of 8 days
2. Activity F with preceding activities E and duration of 4 days
3. Activity G with preceding activities E and duration of 10 days
4. Activity H with preceding activities F and G and duration of 2 days
5. Activity I with preceding activities H and duration of 2 days
6. Activity J with preceding activities H and duration of 2 days
7. Activity K with preceding activities H and duration of 3 daus
8. Activity L with preceding activities I, J, and K and duration of 2 days
9. Activity M with preceding activities L and duration of 1 day
19 days
25 days
26 days
27 days
16
Multiple Choice
Which of the following best describes critical path analysis?
It shows how a project can be completed with maximum labour resources
It shows how a project can be completed in the minimum time
It takes account for unforeseen events
It predicts the success of a project
17
Multiple Choice
Which best describes the critical path slack?
the activities on the critical path
the delay after the drywall is completed in a house to allow it to dry
the earliest a new HVAC system can be ordered from a manufacturer
the earliest a new HVAC system can be ordered from a manufacturer without delaying the project
18
19
Multiple Choice
What factors should be considered when planning work completion time due to other services?
Delays caused by other services
Availability of materials
Weather conditions
Labor costs
20
21
Multiple Choice
What must a contractor have recorded on a variation order?
The changes requested
The original contract
The client's payment details
The project timeline
22
23
Multiple Choice
What is the consequence of a breach of contract?
Formation of a new contract
Legal remedies
Automatic termination
No consequence
24
25
Multiple Choice
What is the purpose of a Gantt chart in work planning?
To allocate resources
To track expenses
To schedule activities
To measure performance
26
27
Multiple Choice
According to the bar chart, which task takes the longest to complete?
Install cladding
Windows & main doors
Roof frame
Concrete slab
28
Multiple Choice
What does the histogram represent in terms of the mass of each package?
Number of packages
Average mass
Total mass
Standard deviation
29
30
Multiple Choice
What are the steps involved in installing the floodlighting in a car park?
Dig trenches
Deliver lampposts
Fix lampposts
Inspect and test
31
32
Multiple Choice
What is the total estimated time required to dig trenches and deliver lampposts?
12 hours
13 hours
14 hours
15 hours
33
34
Multiple Choice
What is the significance of the start and end dates in a Gantt chart?
They indicate the duration of the project
They show when the team is on holiday
They are used for color coding
They determine the complexity of the project
35
36
Multiple Choice
What are the stages involved in Critical Path Network planning?
Identify the operations and components
Determine the duration of each operation
Form a network that relates the operations in a logical sequence
Calculate the total cost of the project
37
38
Multiple Choice
What is the total number of days required to complete the following tasks: Lay Foundations, Build walls, Fit roof, Electric 1st fix, Electric 2nd fix, Plumbing 1st fix, Plumbing 2nd fix, and Inspect and test?
10 days
12 days
14 days
8 days
39
40
Open Ended
What are the tasks that are part of the critical path network?
41
Fill in the Blanks
Type answer...
42
Multiple Choice
What is the start date for the 'Electrics 1st fix' task?
Day 7
Day 8
Day 9
Day 10
43
Multiple Choice
What is the duration of the task 'Lay foundations'?
1 day
2 days
3 days
4 days
44
45
Multiple Choice
What is the total duration for the tasks in the Critical Path Network?
6 days
8 days
10 days
12 days
46
47
Open Ended
Explain the significance of the critical path in project management.
48
49
Multiple Choice
What is the critical path in project management?
The shortest path of events
The path that takes the longest time
The path with the least resources
The path that is easiest to follow
50
51
Multiple Choice
What does the bar chart represent in terms of work progress?
Tasks completed
Tasks pending
Tasks in progress
Tasks not started
52
53
Multiple Choice
What should your management plan include when overseeing work programmes?
Working from plans and specifications
Ignoring health and safety procedures
Not coordinating with other trades
Avoiding conflict resolution
54
55
56
Multiple Choice
What are the sources of technical and functional information provided by manufacturers?
Catalogues
Data sheets
User manuals
Installation guides
57
58
Multiple Choice
What types of information do companies supply to their employees?
Working hours
Health and safety requirements
Pay rates
All of the above
59
60
Multiple Choice
What are the hourly rates for JIB graded operatives and apprentices registered before January 7th, 2013?
£17.57
£18.88
£16.82
£15.46
61
62
63
64
65
66
67
68
69
70
71
72
73
Poll
How confident do you feel about this topic now?
Show answer
Auto Play
Slide 1 / 73
SLIDE
Similar Resources on Wayground
66 questions
みんなの日本語初級1第2課
Presentation
•
Professional Development
71 questions
Accounting advanced
Presentation
•
Professional Development
64 questions
Revision Lesson 1 Junior Intermediate
Presentation
•
Professional Development
68 questions
Pengetahuan Umum
Presentation
•
Professional Development
68 questions
AI for business week 6
Presentation
•
Professional Development
68 questions
Present Simple
Presentation
•
Professional Development
67 questions
연습 13
Presentation
•
Professional Development
66 questions
Tenses, Aspects and Voice 2: Past and Past Progressive
Presentation
•
Professional Development
Popular Resources on Wayground
20 questions
STAAR Review Quiz #3
Quiz
•
8th Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
6 questions
Marshmallow Farm Quiz
Quiz
•
2nd - 5th Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
20 questions
Inferences
Quiz
•
4th Grade
19 questions
Classifying Quadrilaterals
Quiz
•
3rd Grade
12 questions
What makes Nebraska's government unique?
Quiz
•
4th - 5th Grade