PMP Communication Management

PMP Communication Management

University

20 Qs

quiz-placeholder

Similar activities

Chapter 4

Chapter 4

University

20 Qs

Rehab 105 Short Quiz 4 - Endterms

Rehab 105 Short Quiz 4 - Endterms

University

20 Qs

Freight Rate

Freight Rate

University

16 Qs

Statistics Quiz

Statistics Quiz

University

20 Qs

Passive Voice(S. Present& S. Past)

Passive Voice(S. Present& S. Past)

University

16 Qs

GGSR Midterm Review 10/07/21

GGSR Midterm Review 10/07/21

University

20 Qs

BASIC OF RESEARCH

BASIC OF RESEARCH

11th Grade - Professional Development

15 Qs

PMP Communication Management

PMP Communication Management

Assessment

Quiz

Other

University

Medium

Used 134+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

If there were 4 people on the project team and 9 more are added, how many additional channels of communication does this create? 
72
30
36
6

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The process to create a plan showing how all project communication will be conducted is known as: 
Plan Communication Modeling
Communication Modeling
Communication Distribution Planning 
Project Communication

3.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Who is responsible for decoding the message?
Receiver
Sender 
Communication Model
Communications Management Plan

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Which is FALSE regarding Manage Communications? 
Ends when the product has been accepted 
Part of the execution process
involves unexpected requests from stakeholders
Carries out the communications management plan

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Acknowledgement in the context of the communication model indicates: 
Confirmation of receipt
Agreement with the sender's message
Comprehension of sender's message 
Agreement upon a protocol and frequency of communication

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Your latest review of the project status shows it to be more than 3 weeks behind your schedule. You are required to communicate this to the customer. Your message should be:
Formal and written
Informal and written
Formal and verbal
Informal and verbal

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

What is TRUE regarding issues?
Each issue should be assigned to a single owner
All issues must be resolved in order for the project to be closed
The issue log is a tool for stakeholders to manage project issues
Issue management may be treated as a sub- project on a larger/ complex projects 

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?