PMP- Scope (Basics)-Green Book

PMP- Scope (Basics)-Green Book

University

10 Qs

quiz-placeholder

Similar activities

ESL Vocabulary: Technology 1

ESL Vocabulary: Technology 1

University - Professional Development

10 Qs

INTO Artificial Intelligence

INTO Artificial Intelligence

University - Professional Development

10 Qs

Term 1 Reflection

Term 1 Reflection

KG - Professional Development

11 Qs

Communication and Sales by Vishal Jaiswal

Communication and Sales by Vishal Jaiswal

KG - Professional Development

12 Qs

Learning through Projects

Learning through Projects

9th Grade - University

10 Qs

AXIE 101

AXIE 101

KG - Professional Development

10 Qs

Radio Interface

Radio Interface

University

15 Qs

Bone tumors 2

Bone tumors 2

University

10 Qs

PMP- Scope (Basics)-Green Book

PMP- Scope (Basics)-Green Book

Assessment

Quiz

Professional Development

University

Medium

Used 82+ times

FREE Resource

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is not a Group Creativity Technique used in the Collect Requirements process?
Nominal group technique
Pareto chart
Mind mapping
Affinity diagram

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Linda is a project manager in charge of an online banking project. The project has completed phase 1 and is moving into the next phase of the project. Which of the following processes must be carried out first for the phase 2?
Define Scope
Identify Stakeholders
Develop Project Charter
Develop Project Management Plan

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following processes is not a part of the Project Scope Management?
Create WBS
Control Quality
Control Scope
Collect Requirements

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The WBS is finalized by establishing control accounts for the work packages and a unique identifier from a code of accounts. This provides a structure for hierarchical summation of:
Schedule and requirements information
Cost and requirements information
Cost and resource information
Cost, schedule and resource information

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Uncontrolled project scope changes are often referred to as ________ 
Scope Creep
Scope Verification
Value Added Scope
Scope Control

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

While managing a project, you have included the product acceptance criteria in the Quality Management Plan. When reviewing your plan, a senior manager asks you look at this closely. You then realize that what you have done is incorrect. Where should you actually place the product acceptance criteria?
Project Charter 
Change Control Process 
Project Scope Statement 
Scope Verification Plan

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The Project Scope Management is primarily concerned with:
Defining the scope of work that is included in the project
Defining and controlling what is and what is not included in the project.
The scope of work that is required during the initiation phase
Defining the specifications and functionality of the work product

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?