Project Management Framework (Rita's)

Quiz
•
Professional Development
•
Professional Development
•
Medium
Used 22+ times
FREE Resource
24 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Understanding the culture, policies, and procedures of the organization in which the project is being performed is most challenging in:
Global organizations
Manufacturing organizations
Small organizations
Agile organizations
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks relative to the strong matrix structure the organization used to have. In a project-oriented team, the project team:
Reports to many bosses
Has no loyalty to the project
Reports to the functional manager
Will not always have a "home"
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is trying to complete a software development project but cannot get enough attention for the project. Resources are focused on completing process-related work, and the project manager has little authority to assign resources. What form of organization must the project manager be working in?
Functional
Matrix
Expediter
Coordinator
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has little experience, but she has been assigned as the project manager of a new project. Because she will be working in a matrix organization to complete her project, she can expect communication to be:
Simple
Open and accurate
Complex
Hard to automate
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team member is talking to another team member and complaining that many people are asking him to do things. If he works in a functional organization, who has the power to give direction to the team member?
The project manager
The functional manager
The team
The PMO
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Two project managers have just realized that they are in a weak matrix organization and that their power as project managers is quite limited. One figures out that he is really a project expediter, and the other realizes she is really a project coordinator. How is a project expediter different from a project coordinator?
The project expediter cannot make decisions
The project expediter can make more decisions
The project expediter reports to a higher-level manager
The project expediter has some authority.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Who has the most power in a project-oriented organization
The project manager
The functional manager
The team
They all share power
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
Project Management 101

Quiz
•
Professional Development
20 questions
PMP Assessment

Quiz
•
Professional Development
20 questions
PMP Procurement Exercise

Quiz
•
Professional Development
20 questions
ITIL 4 Foundation_ITIL Practices

Quiz
•
Professional Development
20 questions
[Scrum Master]-Primer-Examen-Primer-Intento

Quiz
•
Professional Development
25 questions
Project Quality Management I (25)

Quiz
•
Professional Development
20 questions
TAYL - Product Quiz

Quiz
•
Professional Development
20 questions
Pre-Test Project Management [15/04/25]

Quiz
•
Professional Development
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade