scrum.sm.a

scrum.sm.a

Professional Development

15 Qs

quiz-placeholder

Similar activities

Test Your "Scrum" Knowledge

Test Your "Scrum" Knowledge

Professional Development

15 Qs

[Scrum Master]-Primer-Examen-Primer-Intento

[Scrum Master]-Primer-Examen-Primer-Intento

Professional Development

20 Qs

scrum.sm.b

scrum.sm.b

Professional Development

15 Qs

scrum.assessment.event.a

scrum.assessment.event.a

Professional Development

17 Qs

Agile & Scrum Method

Agile & Scrum Method

Professional Development

15 Qs

Teko Data Clan - Scrum Quiz #2 - Scrum Artifacts

Teko Data Clan - Scrum Quiz #2 - Scrum Artifacts

12th Grade - Professional Development

20 Qs

Agile Knowledge Quiz

Agile Knowledge Quiz

Professional Development

13 Qs

Agile Training

Agile Training

Professional Development

15 Qs

scrum.sm.a

scrum.sm.a

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Aurélien BALMAS

Used 19+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the role of Management in Scrum?

Continually monitor staffing levels of the Development Team.

Monitor the Development Team's productivity.

Support the Product Owner with insights and information into high value product and system capabilities. Support the Scrum Master to cause organizational change that fosters empiricism, self-organization, bottom-up intelligence, and intelligent release of software.

Identify and remove people that aren't working hard enough.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The purpose of a Sprint is to produce a done increment of working product.
True
False

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done?
Without a new vocabulary as a reminder of the change, very little change may actually happen.
The organization may not understand what has changed with Scrum and the benefits of Scrum may be lost.
Management may feel less anxious.
All of the above.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The time-box for the Sprint Planning meeting is?
4 hours.
8 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
Whenever it is done.
Monthly.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
True
False

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Development Team membership should change:
Every Sprint to promote shared learning.
Never, because it reduces productivity.
As needed, while taking into account a short term reduction in productivity.
As needed, with no special allowance for changes in productivity.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the main reason for the Scrum Master to be at the Daily Scrum?
To make sure every team member answers the three questions.
He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.
To write down any changes to the Sprint Backlog, including adding new items, and tracking  progress on the burn-down.
To gather status and progress information to report to management.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?