Chapter 2 - Managing the Information Systems Project
Authored by Palanichamy Palanichamy Naveen
Other
University
Used 24+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the following is FALSE with respect to the Gantt chart and network diagram?
Gantt charts visually show the duration of tasks, whereas a network diagram visually shows the sequence dependencies between tasks.
Gantt charts visually show the time overlap of tasks, whereas a network diagram does not show time overlap but does show which tasks could be done in parallel.
Gantt charts visually show the time overlap of tasks, whereas a network diagram shows time overlap but does show which tasks could be done in parallel.
Some forms of Gantt charts can visually show slack time available within an earliest start and latest finish duration.
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
A network diagram depicts a Gantt chart.
True
False
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
________ is a critical path scheduling technique used for controlling resources.
Network programming
Network diagramming
Networking
Network scheduling
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A critical path refers to a sequence of task activities whose ________ and ________ directly affect the completion date of a project.
Duration; network
Order; network
Task; sequence
Order; duration
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A network diagram will never be used when the tasks ________.
Cannot be worked on independently of other tasks
Can be worked on independently of other tasks
Are well defined and have a clear beginning and end point
Serve the purpose of the project
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a feature of a network diagram?
It represents how completion times vary for activities.
It is more often used than Gantt charts to manage projects such as information systems development.
Connecting arrows are not used.
Variability in the duration of activities is the norm.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is NOT a feature of PERT?
Uses optimistic estimate
Uses pessimistic estimate
Uses realistic estimate
Calculates budget for a project
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?