12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the following is FALSE with respect to the Gantt chart and network diagram?

Gantt charts visually show the duration of tasks, whereas a network diagram visually shows the sequence dependencies between tasks.

Gantt charts visually show the time overlap of tasks, whereas a network diagram does not show time overlap but does show which tasks could be done in parallel.

Gantt charts visually show the time overlap of tasks, whereas a network diagram shows time overlap but does show which tasks could be done in parallel.

Some forms of Gantt charts can visually show slack time available within an earliest start and latest finish duration.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A network diagram depicts a Gantt chart.

True

False

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

________ is a critical path scheduling technique used for controlling resources.

Network programming

Network diagramming

Networking

Network scheduling

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A critical path refers to a sequence of task activities whose ________ and ________ directly affect the completion date of a project.

Duration; network

Order; network

Task; sequence

Order; duration

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A network diagram will never be used when the tasks ________.

Cannot be worked on independently of other tasks

Can be worked on independently of other tasks

Are well defined and have a clear beginning and end point

Serve the purpose of the project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a feature of a network diagram?

It represents how completion times vary for activities.

It is more often used than Gantt charts to manage projects such as information systems development.

Connecting arrows are not used.

Variability in the duration of activities is the norm.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a feature of PERT?

Uses optimistic estimate

Uses pessimistic estimate

Uses realistic estimate

Calculates budget for a project

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?