Project Management 4

Project Management 4

University

15 Qs

quiz-placeholder

Similar activities

Quiz 3 - Hybrid Project Management

Quiz 3 - Hybrid Project Management

University

10 Qs

Day two review

Day two review

University

10 Qs

PJMT 2103: Week 4: PM Scope Management

PJMT 2103: Week 4: PM Scope Management

University

10 Qs

Project Management POP Quiz 1

Project Management POP Quiz 1

University

20 Qs

Kuis Praktisi Mengajar

Kuis Praktisi Mengajar

University

20 Qs

Enterprise System Review

Enterprise System Review

University

10 Qs

PROJECT MANAGEMENT (CHAPTER 7 & 8)

PROJECT MANAGEMENT (CHAPTER 7 & 8)

University

10 Qs

Project Quest

Project Quest

University

20 Qs

Project Management 4

Project Management 4

Assessment

Quiz

Other

University

Easy

Created by

El Awad Osman

Used 7+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

All of the following are inputs to Manage Project Knowledge EXCEPT:

Deliverables.

Knowledge management.

Lessons learned register.

Project management plan.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

All of the following are true about the project scope management plan EXCEPT:

It enables the creation of the WBS from the detailed project scope statement.

It describes how the scope will be defined, developed, monitored, controlled, and validated.

It can be formal or informal, broadly framed or highly detailed, based on the needs of the project.

It is not related to the project management plan.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

An output of the Define Scope process is:

Work breakdown structure (WBS).

Resource breakdown structure (RBS).

Project scope statement.

Scope and schedule delays control plan.

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

An input to the Define Scope process is:

The type of contract detail language.

Project charter.

Work breakdown structure (WBS).

Decomposition.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The following is true about the WBS:

The WBS is another term for the bar (Gantt) chart.

Each descending level of the WBS represents an increasingly detailed definition of the project work.

Work not in the WBS is usually defined in the scope statement of the project.

The WBS shows only the critical path activities.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Scope verification is concerned with:

Ensuring that all the elements necessary are included in the WBS

Receiving buy-in from team members

The acceptance of the work results

Developing a project base line

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A driver’s license is required by law before an individual can drive a car .Similarly the project manager requires a ____________ document in order to plan, execute and control a project.


Scope statement.

Project budget.

Project charter.

WBS.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?