1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

All of the following are inputs to Manage Project Knowledge EXCEPT:

Deliverables.

Knowledge management.

Lessons learned register.

Project management plan.

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

All of the following are true about the project scope management plan EXCEPT:

It enables the creation of the WBS from the detailed project scope statement.

It describes how the scope will be defined, developed, monitored, controlled, and validated.

It can be formal or informal, broadly framed or highly detailed, based on the needs of the project.

It is not related to the project management plan.

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

An output of the Define Scope process is:

Work breakdown structure (WBS).

Resource breakdown structure (RBS).

Project scope statement.

Scope and schedule delays control plan.

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

An input to the Define Scope process is:

The type of contract detail language.

Project charter.

Work breakdown structure (WBS).

Decomposition.

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

The following is true about the WBS:

The WBS is another term for the bar (Gantt) chart.

Each descending level of the WBS represents an increasingly detailed definition of the project work.

Work not in the WBS is usually defined in the scope statement of the project.

The WBS shows only the critical path activities.

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Scope verification is concerned with:

Ensuring that all the elements necessary are included in the WBS

Receiving buy-in from team members

The acceptance of the work results

Developing a project base line

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

A driver’s license is required by law before an individual can drive a car .Similarly the project manager requires a ____________ document in order to plan, execute and control a project.


Scope statement.

Project budget.

Project charter.

WBS.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?