Scrum Master Academy Day 5 Quiz
Authored by Veenit Kansal
Professional Development
Professional Development
Used 12+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Product Backlog items have the attributes of a
Description, Order and Size
Estimate
Value
(a) & (b)
All of the above
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which is “false” about the Product backlog:
It is never Complete
It is not Dynamic
It exists as long as the product exists
It evolves as the desired product
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Who is responsible for estimating the PBIs in the Product backlog?
Scrum team
Developers
Developers and Product Owner
Product Owner and Scrum Master
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
How do you know that a Developers is cross-functional?
Every member of the Developers is able to perform every task
A few of the Developer members pair program and do Test driven development
Developers have all the skills to create a potentially releasable increment by the end of every sprint
There is no conflicts in the Developers
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Who is responsible for clearly expressing Product Backlog items?
The Scrum Master
The Scrum Master, or the Scrum Master may have the Developers do it.
The Product Owner
The business analyst who represents the Product Owner in the Developers
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
True
False
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Scrum Master is working with a Developers that has members in different physical locations. The Developers meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before beginning the Daily Scrum. What action should the Scrum Master take?
Ask the Developer members to alternate who is responsible for meeting setup.
Set up the meeting and tell the Developers that is how it will be done.
Allow the Developers to self-manage and determine for itself what to do.
Inform management and ask them to solve it.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?