quiz on PERT

quiz on PERT

University

15 Qs

quiz-placeholder

Similar activities

KUIS 5,6,7 PEMASARAN FARMASI

KUIS 5,6,7 PEMASARAN FARMASI

University

10 Qs

CSS- Quiz 2

CSS- Quiz 2

University

20 Qs

rubiks cube quiz

rubiks cube quiz

KG - Professional Development

13 Qs

Be / Past Tense

Be / Past Tense

12th Grade - University

18 Qs

RAPAT TELECONFERENCE

RAPAT TELECONFERENCE

12th Grade - University

10 Qs

Food Safety

Food Safety

University - Professional Development

10 Qs

FINANCIAL MANAGEMENT

FINANCIAL MANAGEMENT

12th Grade - University

20 Qs

Post-test Epidemiology - Study design

Post-test Epidemiology - Study design

University

10 Qs

quiz on PERT

quiz on PERT

Assessment

Quiz

Other

University

Practice Problem

Hard

Created by

kajal palan

Used 20+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

PERT analysis is based on

optimistic time

pessimistic time

most likely time

All of above

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The critical path

Is a path that operates from the starting node to the end node

Is a mixture of all paths.

Is the longest path

Is the shortest path

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three activities are 12, 15, and 10, then the earliest start time for Y will be

10

15

12

2

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

PERT technique is useful for

small projects

large and complex projects

research and development projects

deterministic activities

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

If the optimistic time, pessimistic time and most likely time for activity A are 4,8 and 6 respectively and for activity B are 5,9 and 5.5 respectively then

expected time of activity A is greater than the expected time of activity B

expected time of activity B is greater than the expected time of activity A

expected time of both activites A and B are same.

none of the above

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

If an activity has its optimistic, most likely and pessimistic times as 2,3 and 7 respectively, then its expected time and variance are respectively

3.5 and 5/6

5 and 25/36

3.5 and 25/36

4 and 5/6

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A father notes that when his teenage child uses the mobile, he/she takes not less than 6 minutes for a call and sometimes as much as an hour. Fifteen minutes calls are more frequent calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

15 minutes

20.143 minutes

21 minutes

27 minutes

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?