quiz on PERT

quiz on PERT

University

15 Qs

quiz-placeholder

Similar activities

Usability Testing Quiz

Usability Testing Quiz

University

20 Qs

Estimating in project management

Estimating in project management

University

10 Qs

IQ Quiz

IQ Quiz

10th Grade - University

20 Qs

Topic 1

Topic 1

University

15 Qs

Classroom Behavior and ROCK Matrix Assessment

Classroom Behavior and ROCK Matrix Assessment

6th Grade - University

15 Qs

Understanding Budgeting Decisions in Agribusiness

Understanding Budgeting Decisions in Agribusiness

12th Grade - University

10 Qs

POM: Permit System

POM: Permit System

10th Grade - Professional Development

20 Qs

T4- CURRICULUM IMPLEMENTATION THEORY

T4- CURRICULUM IMPLEMENTATION THEORY

University

12 Qs

quiz on PERT

quiz on PERT

Assessment

Quiz

Other

University

Hard

Created by

kajal palan

Used 20+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

PERT analysis is based on

optimistic time

pessimistic time

most likely time

All of above

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The critical path

Is a path that operates from the starting node to the end node

Is a mixture of all paths.

Is the longest path

Is the shortest path

3.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three activities are 12, 15, and 10, then the earliest start time for Y will be

10

15

12

2

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

PERT technique is useful for

small projects

large and complex projects

research and development projects

deterministic activities

5.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

If the optimistic time, pessimistic time and most likely time for activity A are 4,8 and 6 respectively and for activity B are 5,9 and 5.5 respectively then

expected time of activity A is greater than the expected time of activity B

expected time of activity B is greater than the expected time of activity A

expected time of both activites A and B are same.

none of the above

6.

MULTIPLE CHOICE QUESTION

3 mins • 1 pt

If an activity has its optimistic, most likely and pessimistic times as 2,3 and 7 respectively, then its expected time and variance are respectively

3.5 and 5/6

5 and 25/36

3.5 and 25/36

4 and 5/6

7.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A father notes that when his teenage child uses the mobile, he/she takes not less than 6 minutes for a call and sometimes as much as an hour. Fifteen minutes calls are more frequent calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

15 minutes

20.143 minutes

21 minutes

27 minutes

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?