PROJECT SCHEDULING MINI QUIZ

PROJECT SCHEDULING MINI QUIZ

University

15 Qs

quiz-placeholder

Similar activities

Project Cost Optimisation Quiz

Project Cost Optimisation Quiz

University

10 Qs

PM 3

PM 3

University

16 Qs

ROP Controls Quiz

ROP Controls Quiz

University

18 Qs

Exam - Business and Financial Project Management

Exam - Business and Financial Project Management

University

20 Qs

ABM101 -EXAM

ABM101 -EXAM

University

16 Qs

T Test

T Test

University

14 Qs

Standard Costing

Standard Costing

University

15 Qs

Quiz 4 - Hybrid Project Management

Quiz 4 - Hybrid Project Management

University

16 Qs

PROJECT SCHEDULING MINI QUIZ

PROJECT SCHEDULING MINI QUIZ

Assessment

Quiz

Other

University

Hard

Created by

Jenery Semblante

Used 4+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What does the expected time of an activity represent?

The time it will definitely take to complete the activity.

The weighted average of optimistic, pessimistic, and most likely time estimates.

The fastest time an activity can be completed.

The time with the highest probability of occurrence.

2.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What is the formula to calculate the variance of an activity?

Variance = (P-O/6)^2

Variance = (O-P/6)

Variance = (P+O/6)^2

Variance = (P-O/6)

3.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

In PERT, which formula is used to calculate the expected time for an activity?

TE = O+P/6

TE = O+2M+P/6

TE = O+4M+P/6

TE = O-4M-P/6

4.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

 What does a high variance in an activity indicate?

The activity will likely finish early.

There is more uncertainty in the activity's completion time.

The activity is part of the critical path.

The activity has zero slack.

5.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What is the total variance of a project determined by?

Summing the variances of all activities in the project.

 Summing the variances of the activities along the critical path.

 Averaging the variances of all activities.

Multiplying the variances of all activities.

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

If the expected project duration is 40 days and the variance along the critical path is 4, what is the standard deviation of the project?

2 days

4 days

6 days

10 days

7.

MULTIPLE CHOICE QUESTION

10 sec • 1 pt

What does a critical path consist of?

The activities with the shortest durations.

The longest non-overlapping activities.

The activities that are not dependent on others.

The sequence of activities with zero slack.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?