100 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 1 of 100Question ID: 612192
While reviewing the quality management plan, you notice that the cost of quality specified in the plan includes a wrong component.
Which component did you likely notice?
AChange costs
BAppraisal costs
CFailure costs
DPrevention costs
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 2 of 100Question ID: 626008
Using the appropriate tools and techniques, the project team have collected a set of requirements for the project.
What is the next step in defining which requirements will be included as part of the project?
ACreating a work breakdown structure
BDeveloping a scope management plan
CBuilding a working prototype
DPerforming the Define Scope process
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 3 of 100Question ID: 612454
You are identifying the specific actions that will be required to complete the project deliverables. As part of this process, you have created a project document which describes portions of work to be performed during the project. Each portion of work specified in the document has various details such as leads and lags, imposed dates, constraints, assumptions, as well as logical relationships.
Which project document have you created?
AActivity list
BActivity attributes
CActivity register
DMilestone list
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 4 of 100Question ID: 613716
You are preparing the plan for the acquisition of the team, which will manufacture product prototypes. Given the highly regulated nature of the work, you will need assistance in ensuring compliance with all the various government and union regulations.
What tool or technique is most useful in this situation?
AExpert judgment
BProject management information systems (PMIS)
CVariance analysis
DAnalogous estimating
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 5 of 100Question ID: 612315
A project to develop a new e-commerce website server has been completed. However, when the server was deployed on the customer network, it was unable to meet reliability and performance requirements and frequently crashed resulting in lost sales and customer dissatisfaction.
What type of requirements was most likely overlooked during testing?
ABusiness
BProject
CSolution
DStakeholder
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 6 of 100Question ID: 612441
During a meeting to determine the requirements for a software development project, everyone agrees to include a particular feature except the director of finance who is adamant that it is too costly. After a lengthy debate, the director of finance changes his mind and agrees to the inclusion of the feature. The decision is finally made to move forward with the feature.
What decision-making technique has been used in this scenario?
APlurality
BUnanimity
CMajority
DAutocratic decision making
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 7 of 100Question ID: 613352
Following are the activities and durations on a project schedule. The project is in planning.
If activities C, D and F are on the critical path, what is the total float for activity D?
A4 days
B7 days
C0 Days
DCannot be determined
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
100 questions
Moody's Practice Test 2
Quiz
•
Professional Development
100 questions
Electrical Prep Test
Quiz
•
Professional Development
97 questions
cpns
Quiz
•
Professional Development
100 questions
KOMPETENSI TEKNIS PPPK PGSD PART 2
Quiz
•
Professional Development
100 questions
Essay 4
Quiz
•
Professional Development
101 questions
D59 MASTER THE DAY
Quiz
•
Professional Development
104 questions
D51 MASTER THE DAY
Quiz
•
Professional Development
100 questions
20250721 AMTBLK02 Final Study Guide
Quiz
•
Professional Development
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade