
PLANNING

Quiz
•
Professional Development
•
Professional Development
•
Hard

Edi Giyanto
Used 8+ times
FREE Resource
100 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 1 of 100Question ID: 612192
While reviewing the quality management plan, you notice that the cost of quality specified in the plan includes a wrong component.
Which component did you likely notice?
AChange costs
BAppraisal costs
CFailure costs
DPrevention costs
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 2 of 100Question ID: 626008
Using the appropriate tools and techniques, the project team have collected a set of requirements for the project.
What is the next step in defining which requirements will be included as part of the project?
ACreating a work breakdown structure
BDeveloping a scope management plan
CBuilding a working prototype
DPerforming the Define Scope process
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 3 of 100Question ID: 612454
You are identifying the specific actions that will be required to complete the project deliverables. As part of this process, you have created a project document which describes portions of work to be performed during the project. Each portion of work specified in the document has various details such as leads and lags, imposed dates, constraints, assumptions, as well as logical relationships.
Which project document have you created?
AActivity list
BActivity attributes
CActivity register
DMilestone list
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 4 of 100Question ID: 613716
You are preparing the plan for the acquisition of the team, which will manufacture product prototypes. Given the highly regulated nature of the work, you will need assistance in ensuring compliance with all the various government and union regulations.
What tool or technique is most useful in this situation?
AExpert judgment
BProject management information systems (PMIS)
CVariance analysis
DAnalogous estimating
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 5 of 100Question ID: 612315
A project to develop a new e-commerce website server has been completed. However, when the server was deployed on the customer network, it was unable to meet reliability and performance requirements and frequently crashed resulting in lost sales and customer dissatisfaction.
What type of requirements was most likely overlooked during testing?
ABusiness
BProject
CSolution
DStakeholder
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 6 of 100Question ID: 612441
During a meeting to determine the requirements for a software development project, everyone agrees to include a particular feature except the director of finance who is adamant that it is too costly. After a lengthy debate, the director of finance changes his mind and agrees to the inclusion of the feature. The decision is finally made to move forward with the feature.
What decision-making technique has been used in this scenario?
APlurality
BUnanimity
CMajority
DAutocratic decision making
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 7 of 100Question ID: 613352
Following are the activities and durations on a project schedule. The project is in planning.
If activities C, D and F are on the critical path, what is the total float for activity D?
A4 days
B7 days
C0 Days
DCannot be determined
Create a free account and access millions of resources
Similar Resources on Wayground
100 questions
Moody's Practice Test 2

Quiz
•
Professional Development
97 questions
ServiceNow CSM Practice Exam 3

Quiz
•
Professional Development
100 questions
Coronal Polish 100 Questions

Quiz
•
Professional Development
100 questions
Day 1 - Pre Course Test

Quiz
•
Professional Development
100 questions
100 Essential Salesforce Terms

Quiz
•
Professional Development
100 questions
EXECUTING 2

Quiz
•
Professional Development
99 questions
PMP101-199

Quiz
•
Professional Development
98 questions
CISSP Final

Quiz
•
Professional Development
Popular Resources on Wayground
55 questions
CHS Student Handbook 25-26

Quiz
•
9th Grade
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
10 questions
Chaffey

Quiz
•
9th - 12th Grade
15 questions
PRIDE

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
22 questions
6-8 Digital Citizenship Review

Quiz
•
6th - 8th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade