Question 1 of 100Question ID: 612192
While reviewing the quality management plan, you notice that the cost of quality specified in the plan includes a wrong component.
Which component did you likely notice?
PLANNING
Quiz
•
Professional Development
•
Professional Development
•
Hard
Edi Giyanto
Used 8+ times
FREE Resource
100 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 1 of 100Question ID: 612192
While reviewing the quality management plan, you notice that the cost of quality specified in the plan includes a wrong component.
Which component did you likely notice?
AChange costs
BAppraisal costs
CFailure costs
DPrevention costs
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 2 of 100Question ID: 626008
Using the appropriate tools and techniques, the project team have collected a set of requirements for the project.
What is the next step in defining which requirements will be included as part of the project?
ACreating a work breakdown structure
BDeveloping a scope management plan
CBuilding a working prototype
DPerforming the Define Scope process
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 3 of 100Question ID: 612454
You are identifying the specific actions that will be required to complete the project deliverables. As part of this process, you have created a project document which describes portions of work to be performed during the project. Each portion of work specified in the document has various details such as leads and lags, imposed dates, constraints, assumptions, as well as logical relationships.
Which project document have you created?
AActivity list
BActivity attributes
CActivity register
DMilestone list
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 4 of 100Question ID: 613716
You are preparing the plan for the acquisition of the team, which will manufacture product prototypes. Given the highly regulated nature of the work, you will need assistance in ensuring compliance with all the various government and union regulations.
What tool or technique is most useful in this situation?
AExpert judgment
BProject management information systems (PMIS)
CVariance analysis
DAnalogous estimating
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 5 of 100Question ID: 612315
A project to develop a new e-commerce website server has been completed. However, when the server was deployed on the customer network, it was unable to meet reliability and performance requirements and frequently crashed resulting in lost sales and customer dissatisfaction.
What type of requirements was most likely overlooked during testing?
ABusiness
BProject
CSolution
DStakeholder
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 6 of 100Question ID: 612441
During a meeting to determine the requirements for a software development project, everyone agrees to include a particular feature except the director of finance who is adamant that it is too costly. After a lengthy debate, the director of finance changes his mind and agrees to the inclusion of the feature. The decision is finally made to move forward with the feature.
What decision-making technique has been used in this scenario?
APlurality
BUnanimity
CMajority
DAutocratic decision making
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 7 of 100Question ID: 613352
Following are the activities and durations on a project schedule. The project is in planning.
If activities C, D and F are on the critical path, what is the total float for activity D?
A4 days
B7 days
C0 Days
DCannot be determined
99 questions
Monitoring & Controling
Quiz
•
Professional Development
101 questions
PMP200-300
Quiz
•
Professional Development
100 questions
National Section Practice Exam - Appendix A
Quiz
•
Professional Development
102 questions
ajax
Quiz
•
Professional Development
100 questions
D40 MASTER THE DAY
Quiz
•
Professional Development
100 questions
K3C3RD4S4N 1
Quiz
•
Professional Development
100 questions
Health and Safety
Quiz
•
Professional Development
103 questions
leadership final
Quiz
•
Professional Development
15 questions
Character Analysis
Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing
Quiz
•
9th - 12th Grade
10 questions
American Flag
Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension
Quiz
•
5th Grade
30 questions
Linear Inequalities
Quiz
•
9th - 12th Grade
20 questions
Types of Credit
Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25
Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers
Quiz
•
6th - 8th Grade