1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 1 of 100Question ID: 613192
During project execution, a change request is submitted to include a new set of high-priority requirements to the product. The change requires an increase in the project scope and budget. The change request is approved, and the project manager updates the document that will be used in the Control Scope process to detect any deviation in the agreed-upon scope.
Which of the following documents did the project manager update?
ARequirements documentation
BRequirements traceability matrix
CScope management plan
DConfiguration management plan
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 2 of 100Question ID: 612597
A project manager has found that by issuing laptops to the development team and allowing them to work from home two days per week, the developers are more productive and enjoy the extra time with their families.
What should the project manager do with this information to improve the performance of future projects?
AShare the information during the next iteration retrospective
BUpdate the lessons learned register with the knowledge gained
CRevise the issue log with the final resolution
DSubmit a change request to update the lessons learned repository
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 3 of 100Question ID: 612320
A project produces pistons and connecting rods with extremely tight tolerances. The first few pistons were scrapped, as they were not within the limits specified by the contract. The identified risk response was the acquisition of equipment that could machine pistons more precisely.
With the new equipment in place, what should be done next to determine the effectiveness of the risk response?
AMake a test run to gather work performance information
BPerform technical performance analysis
CProduce a test batch to gather work performance data
DProduce all of the pistons required by the contract and then scrap any that fall outside the specification limits
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 4 of 100Question ID: 651379
The project manager is trying to get sign off for a series of marketing materials. The work is rejected by the stakeholders responsible for sign off because of incorrect use of marketing standards.
What should the project manager do before sending materials to the stakeholders again?
APerform quality control checks before validating the scope
BValidate the scope before performing quality control
CCreate a work breakdown structure before validating the scope
DValidate scope before communicating the project status
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 5 of 100Question ID: 651429
The project is required to notify the public at various stages. A public relations specialist was involved in planning the communications for the project. Now, when the project is in execution, the communications with the public up to this point do not appear to be effective. A survey revealed only 2% of the public was aware of the project.
Whom should the project manager contact first?
AThe public relations specialist
BThe project sponsor
CThe project management office
DA quality specialist
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 6 of 100Question ID: 612295
As a project manager, you contracted with another company to develop a smartphone app. The company has demonstrated the completed app, and you have verified that it meets all technical and quality requirements. Overall, you are pleased with the performance of the seller and plan to use them again in the future.
Now that the project deliverables are complete, who is responsible for declaring the formal closure of the procurement contract?
AThe buyer is responsible for closing out the procurement contract.
BThe seller is responsible for closing out the procurement contract.
CBoth buyer and seller are mutually responsible for closing out the contract.
DA procurement contract is considered closed when the deliverables are accepted.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Question 7 of 100Question ID: 613176
A previously unknown risk surfaces on a project and creates an issue that is estimated to cost $50,000. The project manager submits a change request to adjust the cost baseline and uses contingency reserves to address the cost.
What did the project manager do wrong?
ADid not account for all possible risks during project planning
BDid not include the schedule baseline in the change request
CNothing has been done wrong. The project manager acted properly.
DUsed contingency reserves instead of management reserves
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
100 questions
6 - 10 N+
Quiz
•
University - Professi...
99 questions
National Portion Mock Test 2
Quiz
•
Professional Development
100 questions
1311 Chapter 1 Reading Quiz
Quiz
•
Professional Development
102 questions
Sascha´s Sachkundevorbereitung
Quiz
•
Professional Development
100 questions
IDA-101 Baseline Test
Quiz
•
Professional Development
100 questions
LATIHAN UP PPG PJOK PART 4
Quiz
•
Professional Development
100 questions
Health and Safety
Quiz
•
Professional Development
102 questions
ajax
Quiz
•
Professional Development
Popular Resources on Wayground
8 questions
2 Step Word Problems
Quiz
•
KG - University
20 questions
Comparing Fractions
Quiz
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Latin Bases claus(clois,clos, clud, clus) and ped
Quiz
•
6th - 8th Grade
22 questions
fractions
Quiz
•
3rd Grade
7 questions
The Story of Books
Quiz
•
6th - 8th Grade