Monitoring & Controling

Monitoring & Controling

Professional Development

99 Qs

quiz-placeholder

Similar activities

PROFESSIONAL PRACTICE | BUILDING LAWS P.B. PART 1

PROFESSIONAL PRACTICE | BUILDING LAWS P.B. PART 1

Professional Development

100 Qs

EUREX Exam

EUREX Exam

University - Professional Development

94 Qs

CLOSING

CLOSING

Professional Development

99 Qs

RiskYMgt01

RiskYMgt01

Professional Development

102 Qs

CISSP Final

CISSP Final

Professional Development

98 Qs

Full Mock Up

Full Mock Up

Professional Development

100 Qs

INITIATION

INITIATION

Professional Development

100 Qs

EXECUTING 2

EXECUTING 2

Professional Development

100 Qs

Monitoring & Controling

Monitoring & Controling

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Edi Giyanto

Used 7+ times

FREE Resource

99 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 1 of 100Question ID: 613192

During project execution, a change request is submitted to include a new set of high-priority requirements to the product. The change requires an increase in the project scope and budget. The change request is approved, and the project manager updates the document that will be used in the Control Scope process to detect any deviation in the agreed-upon scope.

Which of the following documents did the project manager update?

ARequirements documentation

BRequirements traceability matrix

CScope management plan

DConfiguration management plan

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 2 of 100Question ID: 612597

A project manager has found that by issuing laptops to the development team and allowing them to work from home two days per week, the developers are more productive and enjoy the extra time with their families.

What should the project manager do with this information to improve the performance of future projects?

AShare the information during the next iteration retrospective

BUpdate the lessons learned register with the knowledge gained

CRevise the issue log with the final resolution

DSubmit a change request to update the lessons learned repository

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 3 of 100Question ID: 612320

A project produces pistons and connecting rods with extremely tight tolerances. The first few pistons were scrapped, as they were not within the limits specified by the contract. The identified risk response was the acquisition of equipment that could machine pistons more precisely.

With the new equipment in place, what should be done next to determine the effectiveness of the risk response?

AMake a test run to gather work performance information

BPerform technical performance analysis

CProduce a test batch to gather work performance data

DProduce all of the pistons required by the contract and then scrap any that fall outside the specification limits

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 4 of 100Question ID: 651379

The project manager is trying to get sign off for a series of marketing materials. The work is rejected by the stakeholders responsible for sign off because of incorrect use of marketing standards.

What should the project manager do before sending materials to the stakeholders again?

APerform quality control checks before validating the scope

BValidate the scope before performing quality control

CCreate a work breakdown structure before validating the scope

DValidate scope before communicating the project status

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 5 of 100Question ID: 651429

The project is required to notify the public at various stages. A public relations specialist was involved in planning the communications for the project. Now, when the project is in execution, the communications with the public up to this point do not appear to be effective. A survey revealed only 2% of the public was aware of the project.

Whom should the project manager contact first?

AThe public relations specialist

BThe project sponsor

CThe project management office

DA quality specialist

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 6 of 100Question ID: 612295

As a project manager, you contracted with another company to develop a smartphone app. The company has demonstrated the completed app, and you have verified that it meets all technical and quality requirements. Overall, you are pleased with the performance of the seller and plan to use them again in the future.

Now that the project deliverables are complete, who is responsible for declaring the formal closure of the procurement contract?

AThe buyer is responsible for closing out the procurement contract.

BThe seller is responsible for closing out the procurement contract.

CBoth buyer and seller are mutually responsible for closing out the contract.

DA procurement contract is considered closed when the deliverables are accepted.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Question 7 of 100Question ID: 613176

A previously unknown risk surfaces on a project and creates an issue that is estimated to cost $50,000. The project manager submits a change request to adjust the cost baseline and uses contingency reserves to address the cost.

What did the project manager do wrong?

ADid not account for all possible risks during project planning

BDid not include the schedule baseline in the change request

CNothing has been done wrong. The project manager acted properly.

DUsed contingency reserves instead of management reserves

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?