Project Cost Management

Project Cost Management

Professional Development

20 Qs

quiz-placeholder

Similar activities

Quiziz Week 2 Day 3

Quiziz Week 2 Day 3

Professional Development

20 Qs

Govt. Initiatives

Govt. Initiatives

Professional Development

15 Qs

Change Management

Change Management

Professional Development

17 Qs

Project Management

Project Management

Professional Development

15 Qs

November W-2 III

November W-2 III

Professional Development

15 Qs

Project Management - 2nd Day

Project Management - 2nd Day

Professional Development

17 Qs

SY53012FP PM Chapter 5

SY53012FP PM Chapter 5

Professional Development

20 Qs

Project management Cycle

Project management Cycle

Professional Development

20 Qs

Project Cost Management

Project Cost Management

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Vilas Chaudhari

Used 4+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is a valid way of evaluating the financial feasibility of a project?

Return on Investment

Net Present Value

Internal Rate of Return

All of the above

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The calculation of the total cost of a product, from R & D to operational support and disposal, is called

Birth-to-death costing

Life-cycle costing

Summary costing

Depreciation costing

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is

Ahead of Schedule and under budget

Behind Schedule and under budget

Ahead of Schedule and over budget

Behind Schedule and over budget

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If BAC = Rs.20,000/- and the project is 40% complete, then the earned value is

Rs. 8,000/-

Rs. 5,000/-

Rs. 20,000/-

Cannot be determined

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If BAC = Rs.12,000/- and CPI = 1.2, then the variance at completion is

Rs. -2,000/-

Rs. 2,000/-

Rs. 3,000/-

Rs. -3,000/-

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If a project manager is looking for revenue for a value-added scope change, the project manager's first choice would be

Management reserve

Customer funded scope change

Undistributed budget

Retained profits

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

EAC, ETC, SPI and CPI most often appear in which type of report?

Performance

Status

Forecast

Exception

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?