Project Cost Management

Project Cost Management

Professional Development

20 Qs

quiz-placeholder

Similar activities

Project Management

Project Management

Professional Development

15 Qs

Project Schedule Management

Project Schedule Management

Professional Development

15 Qs

Nokia ID SG_Quiz All Chapter

Nokia ID SG_Quiz All Chapter

Professional Development

20 Qs

PMP Lesson 7

PMP Lesson 7

Professional Development

16 Qs

Budget Insights 2024 - PG Commerce, Thiagarajar College - Quiz

Budget Insights 2024 - PG Commerce, Thiagarajar College - Quiz

Professional Development

20 Qs

PMP® Quiz Session #194

PMP® Quiz Session #194

Professional Development

25 Qs

PMP Questions 6th Edition Quiz 3

PMP Questions 6th Edition Quiz 3

Professional Development

20 Qs

November W III - 1

November W III - 1

Professional Development

15 Qs

Project Cost Management

Project Cost Management

Assessment

Quiz

Professional Development

Professional Development

Medium

Created by

Vilas Chaudhari

Used 4+ times

FREE Resource

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is a valid way of evaluating the financial feasibility of a project?

Return on Investment

Net Present Value

Internal Rate of Return

All of the above

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

The calculation of the total cost of a product, from R & D to operational support and disposal, is called

Birth-to-death costing

Life-cycle costing

Summary costing

Depreciation costing

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is

Ahead of Schedule and under budget

Behind Schedule and under budget

Ahead of Schedule and over budget

Behind Schedule and over budget

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If BAC = Rs.20,000/- and the project is 40% complete, then the earned value is

Rs. 8,000/-

Rs. 5,000/-

Rs. 20,000/-

Cannot be determined

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If BAC = Rs.12,000/- and CPI = 1.2, then the variance at completion is

Rs. -2,000/-

Rs. 2,000/-

Rs. 3,000/-

Rs. -3,000/-

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

If a project manager is looking for revenue for a value-added scope change, the project manager's first choice would be

Management reserve

Customer funded scope change

Undistributed budget

Retained profits

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

EAC, ETC, SPI and CPI most often appear in which type of report?

Performance

Status

Forecast

Exception

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?