1. What is the duration of the critical path in this network?

Project Schedule Management Dr. Ginger Levin, PMP, PgMP

Quiz
•
Professional Development
•
Professional Development
•
Hard

Edi Giyanto
Used 1+ times
FREE Resource
40 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
a. 10
b. 12
c. 14
d. 15
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2. What is the float for Activity G?
a. –2
b. 0
c. 1
d. 4
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3. If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
a. –1
b. 0
c. 2
d. Cannot be determined
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4. If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?
a. –11
b. 11
c. –13
d. 13
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5. Your company, which operates one of the region’s largest chemical processing plants, has been convicted of illegally dumping toxic substances into the local river. The court has mandated that the required cleanup activities be completed by February 15. This date is an example of—
a. A key event
b. A milestone
c. A discretionary dependency
d. An external dependency
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be installed. In this example, the 10-day period is defined as—
a. Lag
b. Lead
c. Float
d. Slack
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7. You are working to control your schedule. You have a number of tools and techniques you can use and may need to use several of them for effectiveness. You decide you want to track work remaining to be done so you will use—
a. Iteration burndown charts
b. Milestone charts
c. Applied schedule reserves
d. Calculation of multiple work package durations
Create a free account and access millions of resources
Similar Resources on Quizizz
38 questions
Competency showdown

Quiz
•
Professional Development
35 questions
SCRUM Master Certification

Quiz
•
Professional Development
36 questions
Whose lane is it anyway?

Quiz
•
Professional Development
40 questions
ISTQB Foundations Examen I

Quiz
•
Professional Development
35 questions
Post Test Day 1 - SMDP 2024

Quiz
•
Professional Development
41 questions
ITIL 4-5

Quiz
•
Professional Development
41 questions
ITIL 4-3

Quiz
•
Professional Development
36 questions
PDE-2022-4

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade