Project Schedule Management Dr. Ginger Levin, PMP, PgMP

Project Schedule Management Dr. Ginger Levin, PMP, PgMP

Professional Development

40 Qs

quiz-placeholder

Similar activities

ISTQB CTAL-TM

ISTQB CTAL-TM

Professional Development

40 Qs

COST and SCHEDULE

COST and SCHEDULE

Professional Development

35 Qs

Post Test Day 1 - SMDP 2024

Post Test Day 1 - SMDP 2024

Professional Development

35 Qs

Educational Practice

Educational Practice

Professional Development

40 Qs

MA (New Mock 2023 - 5)

MA (New Mock 2023 - 5)

Professional Development

38 Qs

PMP Atoha lesson 13

PMP Atoha lesson 13

Professional Development

40 Qs

PMI ACP SG NOKIA Agile Extra 45 Qns

PMI ACP SG NOKIA Agile Extra 45 Qns

Professional Development

45 Qs

Project Schedule Management Dr. Ginger Levin, PMP, PgMP

Project Schedule Management Dr. Ginger Levin, PMP, PgMP

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Edi Giyanto

Used 1+ times

FREE Resource

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

1. What is the duration of the critical path in this network?

a. 10

b. 12

c. 14

d. 15

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

2. What is the float for Activity G?

a. –2

b. 0

c. 1

d. 4

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

3. If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?

a. –1

b. 0

c. 2

d. Cannot be determined

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

4. If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?

a. –11

b. 11

c. –13

d. 13

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. Your company, which operates one of the region’s largest chemical processing plants, has been convicted of illegally dumping toxic substances into the local river. The court has mandated that the required cleanup activities be completed by February 15. This date is an example of—

a. A key event

b. A milestone

c. A discretionary dependency

d. An external dependency

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be installed. In this example, the 10-day period is defined as—

a. Lag

b. Lead

c. Float

d. Slack

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. You are working to control your schedule. You have a number of tools and techniques you can use and may need to use several of them for effectiveness. You decide you want to track work remaining to be done so you will use—

a. Iteration burndown charts

b. Milestone charts

c. Applied schedule reserves

d. Calculation of multiple work package durations

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?