Search Header Logo

Project Schedule Management Dr. Ginger Levin, PMP, PgMP

Authored by Edi Giyanto

Professional Development

Professional Development

Used 1+ times

Project Schedule Management Dr. Ginger Levin, PMP, PgMP
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

1. What is the duration of the critical path in this network?

a. 10

b. 12

c. 14

d. 15

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

2. What is the float for Activity G?

a. –2

b. 0

c. 1

d. 4

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

3. If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?

a. –1

b. 0

c. 2

d. Cannot be determined

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Media Image

4. If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?

a. –11

b. 11

c. –13

d. 13

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

5. Your company, which operates one of the region’s largest chemical processing plants, has been convicted of illegally dumping toxic substances into the local river. The court has mandated that the required cleanup activities be completed by February 15. This date is an example of—

a. A key event

b. A milestone

c. A discretionary dependency

d. An external dependency

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

6. You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be installed. In this example, the 10-day period is defined as—

a. Lag

b. Lead

c. Float

d. Slack

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

7. You are working to control your schedule. You have a number of tools and techniques you can use and may need to use several of them for effectiveness. You decide you want to track work remaining to be done so you will use—

a. Iteration burndown charts

b. Milestone charts

c. Applied schedule reserves

d. Calculation of multiple work package durations

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?