
Project Schedule Management Dr. Ginger Levin, PMP, PgMP
Authored by Edi Giyanto
Professional Development
Professional Development
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
40 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
1. What is the duration of the critical path in this network?
a. 10
b. 12
c. 14
d. 15
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
2. What is the float for Activity G?
a. –2
b. 0
c. 1
d. 4
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
3. If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?
a. –1
b. 0
c. 2
d. Cannot be determined
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
4. If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?
a. –11
b. 11
c. –13
d. 13
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
5. Your company, which operates one of the region’s largest chemical processing plants, has been convicted of illegally dumping toxic substances into the local river. The court has mandated that the required cleanup activities be completed by February 15. This date is an example of—
a. A key event
b. A milestone
c. A discretionary dependency
d. An external dependency
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
6. You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be installed. In this example, the 10-day period is defined as—
a. Lag
b. Lead
c. Float
d. Slack
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
7. You are working to control your schedule. You have a number of tools and techniques you can use and may need to use several of them for effectiveness. You decide you want to track work remaining to be done so you will use—
a. Iteration burndown charts
b. Milestone charts
c. Applied schedule reserves
d. Calculation of multiple work package durations
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?