1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
PERT analysis is based on
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All the above.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Activities P, Q and R instantly follow activity M, and their current start times are 12, 19, and 10. Therefore, the latest finish time for activity M is
A) 11
B) 10
C) 18
D) Cannot be determined
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While scheduling a project by CPM
A. A project is divided into various activities
B. Required time for each activity is established
C. A sequence of various activities is made according to their importance
D. All the above.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Critical path is the
Longest path
Shortest path
Longest+ Shortest
None
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What do you call a style of leadership that takes account of others' views, opinions and ideas?
a) Laissez-faire
b) People-oriented
c) Democratic
d) Autocratic
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to Lewin, Lippet and White's 1939 experiment, which form of leadership produced the most work from participants?
a) Laissez-faire
b) Democratic
c) Authoritarian
d) A mix of laissez-faire and democratic
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the following approach to leadership, the leader will sets up clear path and clear guidance through which the subordinates will follow
Fiedlers contingency approach
House path goal approach
NA
NA
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?