MICROSOFT PROJECT

MICROSOFT PROJECT

Assessment

Quiz

Computers

11th Grade

Hard

Created by

Siti Nurakmal Politeknik Kota Kinabalu

Used 15+ times

FREE Resource

Student preview

quiz-placeholder

21 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Defined sequence of steps that achieve an identified goals refers to

Project goal

Work Breakdown Structure.

Network Diagram.

Project Management

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An employee who plans and organizes the resources necessary to complete a project.

Resource Manager

Project Manager

Workflow Manager

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The work that needs to be accomplished to deliver of product, service, or result with specified features and function refers to

project risk.

project goals.

project scope.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Microsoft Project will assist the project manager to

allocate the time for site visit.

manage the rules of the project.

communicate the status of the project easily

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The Standard calendar specifies all of the following EXCEPT

2 hours of lunch break.

Monday through Friday are working days.

Saturday and Sunday are nonworking days.

8 hours of work completed each day.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Summary tasks are also known as

general tasks.

outlining tasks.

subtasks.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The default timescale setting of the Gantt chart view is

one tier

two tiers

four tiers

three tiers

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?