Andrew is the prom committee chairman. He is on-site at the prom to make sure all vendors show up at the event and all vendors' activities are falling within the scope of work contracted. Which process stage is
Andrew in?
PM1 1.04 Quiz
Quiz
•
Business
•
9th - 12th Grade
•
Medium
Bobbie Jones
Used 84+ times
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Andrew is the prom committee chairman. He is on-site at the prom to make sure all vendors show up at the event and all vendors' activities are falling within the scope of work contracted. Which process stage is
Andrew in?
initiating
executing
monitoring and controlling
closing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?
initiating
executing
monitoring and controlling
closing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Joe holds a team meeting to discuss lessons learned. He is in which process stage?
planning
executing
monitoring and controlling
closing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The organizational structure in which the project manager has the greatest amount of authority is a:
composite organization.
functional organization.
matrix organization.
projectized organization.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Sierra is visiting and calling venues to see who is available to host her parents' anniversary party. What process stage is she in?
planning
executing
monitoring and controlling
closing
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Tara is meeting with her stakeholders to determine the scope of work. What process stage is she in?
initiating
executing
monitoring and controlling
closing
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After a wedding, Christina meets with the newlyweds to deliver the photographs she took and get the customer's signature and payment for the work done. Which process stage is Christina in?
planning
executing
monitoring and controlling
closing
10 questions
PLANNING AND ORGANIZING
Quiz
•
11th Grade
13 questions
RRHH 3UA
Quiz
•
12th Grade
20 questions
Project Mgmt. I Final Review 2 21-22
Quiz
•
9th - 12th Grade
18 questions
Quiz #4 - OrgMan
Quiz
•
11th Grade
14 questions
office orientation Quiz
Quiz
•
9th Grade
19 questions
size and organisation
Quiz
•
12th Grade - University
20 questions
Posttest U1 QAO
Quiz
•
10th Grade
10 questions
Organizing Function of Management
Quiz
•
10th - 12th Grade
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade
25 questions
Spanish preterite verbs (irregular/changed)
Quiz
•
9th - 10th Grade
10 questions
Identify Slope and y-intercept (from equation)
Quiz
•
8th - 9th Grade
10 questions
Juneteenth: History and Significance
Interactive video
•
7th - 12th Grade
8 questions
"Keeping the City of Venice Afloat" - STAAR Bootcamp, Day 1
Quiz
•
9th - 12th Grade
26 questions
June 19th
Quiz
•
4th - 9th Grade
20 questions
Distance, Midpoint, and Slope
Quiz
•
10th Grade
20 questions
Figurative Language Review
Quiz
•
10th Grade
27 questions
STAAR English 1 Review
Quiz
•
9th Grade